PRINCE2F PRINCE2 Practices Practice Question
Which role is responsible for managing the project on a day-to-day basis?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager is delegated by the Project Board to manage the project on a day-to-day basis within agreed tolerances.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Executive
Why it's wrong here
The Executive has overall accountability but does not manage day-to-day.
- ✗
Senior User
Why it's wrong here
The Senior User specifies benefits and user requirements, not day-to-day management.
- ✓
Project Manager
Why this is correct
The Project Manager is responsible for day-to-day management.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier provides resources and expertise but does not manage day-to-day.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.