PRINCE2F PRINCE2 Practices Practice Question
What is the primary difference between a Highlight Report and a Checkpoint Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
A Highlight Report is sent to the Project Board; a Checkpoint Report is sent to the Project Manager
Highlight Reports are from PM to Project Board; Checkpoint Reports are from Team Manager to PM.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
A Highlight Report is sent to the Project Board; a Checkpoint Report is sent to the Project Manager
Why this is correct
Correct. Highlight: PM to Board; Checkpoint: Team Manager to PM.
- ✗
A Highlight Report is produced weekly; a Checkpoint Report is produced daily
Why it's wrong here
Frequency is not the defining difference.
- ✗
A Highlight Report covers the entire project; a Checkpoint Report covers a stage
Why it's wrong here
Both are periodic; Highlight covers stage progress.
- ✗
There is no difference; they are the same report with different names
Why it's wrong here
They have different audiences and purposes.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.