Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

A project is forecast to exceed its cost tolerance for the current stage. According to PRINCE2, what should the Project Manager do?

⚠ Common exam trap

Many exam-takers assume cost overruns can be handled within the Project Manager's authority or that the Business Case is automatically invalid, when PRINCE2 mandates escalation to the Project Board for any forecast tolerance breach.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction

According to PRINCE2, when a stage is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This triggers a formal decision process where the Board can authorize a revised Stage Plan or take other corrective action. Continuing without escalation violates the management by exception principle.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Increase the project budget to absorb the additional cost and continue with the current Stage Plan

    Why it's wrong here

    The Project Manager cannot unilaterally increase the budget; this requires Project Board approval.

  • Raise an Exception Report to the Project Board and await their direction

    Why this is correct

    When a stage’s cost tolerance is forecast to be exceeded, the Project Manager must escalate because the deviation is beyond the delegated authority. PRINCE2 requires an Exception Report to the Project Board, who then decide on corrective action. This mechanism satisfies the *management by exception* principle, which limits the Project Manager’s authority to within the agreed tolerance for the current stage.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    A cost tolerance breach does not automatically mean the Business Case is unviable; the Project Board decides.

  • Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation violates management by exception; the PM must escalate immediately.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.