PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are types of issue in PRINCE2?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Off-specification
PRINCE2 defines three issue types: Request for Change, Off-specification, and Problem/Concern. 'Risk' and 'Change budget' are not issue types.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Off-specification
Why this is correct
Correct issue type.
- ✗
Opportunity
Why it's wrong here
Opportunity is a type of risk, not an issue.
- ✗
Risk
Why it's wrong here
A risk is a separate concept, not an issue type.
- ✗
Change budget
Why it's wrong here
Change budget is a financial allocation, not an issue type.
- ✓
Request for Change
Why this is correct
Correct issue type.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.