PRINCE2F People: organizations, teams, and leadership Practice Question
In PRINCE2, which role is responsible for the day-to-day management of the project within the tolerances set by the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager is delegated authority by the Project Board to manage the project on a day-to-day basis within agreed tolerances.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
The Team Manager manages the delivery of Work Packages within a stage, not the whole project.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier represents the supplier interests on the Project Board.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative services, not management.
- ✓
Project Manager
Why this is correct
The Project Manager manages the project day-to-day within tolerances set by the Project Board.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.