PRINCE2F People: organizations, teams, and leadership Practice Question

Who chairs the Project Board meetings?

⚠ Common exam trap

PeopleCert often tests the misconception that the Project Manager chairs the Project Board, because candidates confuse operational management with governance authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Senior Responsible Owner (SRO/Executive)

In PRINCE2, the Project Board is chaired by the Executive, also known as the Senior Responsible Owner (SRO). The Executive is ultimately accountable for the project's success and ensures the business case remains viable. The Project Manager manages day-to-day activities but does not chair board meetings.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests and specifies requirements; chairing Project Board meetings belongs to the Executive. Tempting because Senior User is a Board role with decision authority, and would be correct if the question asked who represents users' needs on the Board.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents supplier interests and provides resources; chairing Board meetings is the Executive's responsibility. Tempting because Senior Supplier is a Board role with voting rights, and would be correct if asked who represents the supplier perspective on the Board.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day and reports to the Board but is not a Board member, so cannot chair its meetings. Tempting because the role coordinates meetings and information flow, and would be correct if asked who prepares and circulates Board documentation.

  • ✓

    Senior Responsible Owner (SRO/Executive)

    Why this is correct

    The Executive, titled Senior Responsible Owner, chairs Project Board meetings and owns the business case, ensuring decisions align with strategic direction. PRINCE2 assigns this accountability to the Executive role, satisfying the stem's requirement for the single individual ultimately answerable for the project's viability and governance.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.