PRINCE2F People: organizations, teams, and leadership Practice Question

During project execution, a team member raises a concern that the project's objectives are not aligned with the organization's strategic goals. Which role is primarily responsible for ensuring alignment?

⚠ Common exam trap

The trap here is that candidates often mistake the Project Manager as the owner of all project aspects, but PRINCE2 explicitly separates management (Project Manager) from accountability (Executive) for strategic alignment.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive is ultimately accountable for the project's business justification and ensuring it remains aligned with the organization's strategic goals. In PRINCE2, the Executive owns the Business Case and must approve any changes that affect strategic alignment. The team member's concern about misalignment triggers the Executive's responsibility to review and, if necessary, revalidate the project's mandate.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those providing resources and expertise, so their remit covers supplier delivery, not strategic alignment. It is tempting because suppliers do influence project viability, but the Project Board's business-focused role, the Executive, owns the Business Case and ensures objectives match corporate strategy.

  • ✓

    Executive

    Why this is correct

    The Executive owns the business case and is accountable for ensuring the project remains aligned with corporate strategy and delivers the intended benefits. This directly addresses the stem's concern about objectives diverging from organisational strategic goals.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies requirements and represents those using the product, focusing on benefits realisation rather than corporate strategy. It is tempting because users care about outcomes, but the Executive owns the Business Case and is accountable for ensuring the project stays aligned with the organisation's strategic objectives.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day against the agreed business case, but strategic alignment is owned by the Project Board, which confirms continued viability. The Project Manager would be right for delivering within tolerances, not for judging organisational strategy.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A stakeholder is concerned that the project is not delivering value for money. Which role should this concern be raised with?

medium
  • A.Senior User
  • B.Project Assurance
  • ✓ C.Executive
  • D.Project Manager

Why C: The Executive is ultimately accountable for the project's business justification, including ensuring value for money. Concerns about cost versus benefits must be escalated to the Executive, who owns the Business Case and has the authority to approve changes or stop the project if value is not being delivered.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.