CCNA People: organizations, teams, and leadership Questions

75 of 335 questions · Page 1/5 · People: organizations, teams, and leadership · Answers revealed

1
MCQeasy

In PRINCE2, who is responsible for day-to-day management of the project within tolerances?

A.Team Manager
B.Project Manager
C.Project Support
D.Senior Responsible Owner
AnswerB

The PM has delegated authority for day-to-day management.

Why this answer

The Project Manager manages the project on a day-to-day basis within the tolerances set by the Project Board.

2
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Manager?

Select 2 answers
A.Managing the stage boundary activities
B.Performing Project Assurance
C.Preparing Highlight Reports for the Project Board
D.Approving stage plans
E.Defining project tolerances
AnswersA, C

The PM manages the stage boundary process, including preparing the next Stage Plan.

Why this answer

The Project Manager is responsible for day-to-day management, including preparing Highlight Reports for the Project Board and managing stage boundaries. Project Assurance is independent, and the Project Board defines tolerances.

3
MCQhard

In PRINCE2, why is the Project Manager role separated from the Project Assurance role?

A.To comply with regulatory requirements
B.To reduce the cost of the project
C.To ensure independent oversight of the project
D.To allow the Project Manager to focus on team management
AnswerC

Independence is the key reason.

Why this answer

Separation ensures independence and objectivity in assurance, preventing conflicts of interest where the PM would be checking their own work.

4
MCQeasy

Who is responsible for providing independent assurance to the Project Board that the project is on track?

A.Project Support
B.Project Assurance
C.Project Manager
D.Team Manager
AnswerB

Project Assurance is the correct role.

Why this answer

Project Assurance provides independent oversight, reporting to the Project Board, and cannot be delegated to the Project Manager.

5
MCQmedium

During the Managing a Stage Boundary process, the Project Manager prepares an Exception Plan. What is the trigger for this activity?

A.The Project Board requests a new Stage Plan.
B.The project is at the end of a stage.
C.The Team Manager reports a Work Package is complete.
D.An Exception Report is raised because stage tolerances are forecast to be exceeded.
AnswerD

The Exception Report triggers the need for an Exception Plan.

Why this answer

In PRINCE2, the trigger for preparing an Exception Plan during the Managing a Stage Boundary process is the raising of an Exception Report. This report is created when the Project Manager forecasts that stage tolerances will be exceeded, indicating that the current Stage Plan cannot be completed within its agreed tolerances. The Exception Plan then replaces the existing Stage Plan to bring the project back within tolerance.

Exam trap

The trap here is that candidates often confuse the trigger for an Exception Plan with the routine end-of-stage planning, forgetting that an Exception Plan is a corrective response to a forecast tolerance breach, not a normal planning activity.

How to eliminate wrong answers

Option A is wrong because the Project Board does not request a new Stage Plan as a trigger; they may approve an Exception Plan, but the trigger is the Exception Report. Option B is wrong because the end of a stage triggers the normal production of a Stage Plan for the next stage, not an Exception Plan. Option C is wrong because a completed Work Package is a routine event that triggers the next activity in the Controlling a Stage process, not the creation of an Exception Plan.

6
MCQmedium

Which document is produced in the Initiating a Project process and defines how the project will be managed?

A.Stage Plan
B.Project Initiation Documentation
C.Project Brief
D.Business Case
AnswerB

The PID is the output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project and defines the project's approach, controls, and plans.

7
Multi-Selectmedium

Which TWO roles are permanent members of the Project Board in PRINCE2?

Select 2 answers
A.Team Manager
B.Senior Responsible Owner (Executive)
C.Change Authority
D.Project Manager
E.Senior User
AnswersB, E

The Executive is a permanent Project Board member.

Why this answer

The three permanent roles on the Project Board are the Executive (SRO), Senior User, and Senior Supplier. The Project Manager is not a permanent member; they attend but are not on the Board.

8
MCQhard

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are synonyms
B.An RFC is always approved; an off-specification is always rejected
C.An RFC is about cost; an off-specification is about time
D.An RFC is a proposed change; an off-specification is a failure to meet a specified requirement
AnswerD

This is the core distinction.

Why this answer

Option D is correct because in PRINCE2, a Request for Change (RFC) is a formal proposal to change a product, baseline, or agreed scope, while an Off-specification is a formal notification that a product or deliverable does not meet its specified requirements. The key distinction is that an RFC is a proactive suggestion for change, whereas an Off-specification is a reactive report of a deviation or failure against an agreed specification.

Exam trap

The trap here is that candidates confuse the proactive nature of an RFC with the reactive nature of an Off-specification, often assuming both are just 'problems' or that they are interchangeable terms for any issue.

How to eliminate wrong answers

Option A is wrong because RFC and Off-specification are distinct concepts with different purposes and triggers; they are not synonyms. Option B is wrong because an RFC is not always approved—it goes through change control and can be rejected, and an Off-specification is not always rejected; it can be resolved via a concession or corrective action. Option C is wrong because an RFC can involve cost, time, scope, or quality changes, and an Off-specification can relate to any requirement failure, not just time.

9
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Project Manager
C.Senior Responsible Owner (SRO)
D.Senior Supplier
AnswerC

The SRO is accountable for the Business Case and its maintenance throughout the project.

Why this answer

The Senior Responsible Owner (SRO) is accountable for the Business Case and ensures it remains viable throughout the project.

10
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Authorize expenditure beyond delegated authority
B.Approve the Stage Plans
C.Manage the day-to-day activities of the team
D.Produce the Project Plan
E.Update the Business Case
AnswersA, B

The Project Board approves exceptions beyond their delegated tolerances.

Why this answer

The Project Board is responsible for overall project governance, including authorizing expenditure beyond the delegated authority of the Project Manager. This ensures that financial control remains at the senior management level, preventing unauthorized spending that could jeopardize the project's budget.

Exam trap

PeopleCert often tests the distinction between strategic and operational responsibilities, where candidates mistakenly assign day-to-day management or plan production to the Project Board instead of the Project Manager.

11
Multi-Selecthard

Which THREE of the following are characteristics of Project Assurance?

Select 3 answers
A.Independent of the Project Manager
B.Involved in day-to-day team management
C.Responsible for administrative support
D.Can be performed by multiple individuals or a committee
E.Provides objective oversight to the Project Board
AnswersA, D, E

Assurance must be independent to provide objective oversight.

Why this answer

Project Assurance is a PRINCE2 role that provides an independent, objective view of the project's progress, ensuring that it remains viable and compliant with the business case, quality standards, and risks. Option A is correct because the Project Assurance role must be independent of the Project Manager to avoid conflicts of interest and provide unbiased oversight to the Project Board.

Exam trap

PeopleCert often tests the distinction between Project Assurance (independent oversight) and Project Support (administrative tasks), leading candidates to confuse the two roles.

12
MCQhard

Refer to the exhibit. According to PRINCE2, to whom should the Team Manager report the potential delay?

A.The Executive, John Smith
B.The Project Manager, Sarah Lee
C.The Project Assurance, Peter Black
D.The Senior User, Mary Johnson
AnswerB

Correct: The Team Manager reports to the Project Manager.

Why this answer

In PRINCE2, the Team Manager is responsible for delivering the work package and reports to the Project Manager on progress, issues, and risks. The Project Manager (Sarah Lee) is the single point of contact for the Team Manager within the project management team. Therefore, any potential delay must be reported to the Project Manager, who will then escalate to the Project Board if necessary.

Exam trap

The trap here is that candidates confuse the reporting lines within the project management team, mistakenly thinking a Team Manager should report directly to a Project Board member (Executive, Senior User, or Project Assurance) rather than to the Project Manager who coordinates all delivery-level communications.

How to eliminate wrong answers

Option A is wrong because the Executive (John Smith) is the project's business representative and chair of the Project Board, not the direct line of communication for a Team Manager; the Team Manager reports to the Project Manager, not to the Executive. Option C is wrong because Project Assurance (Peter Black) is an independent oversight role that monitors compliance and performance, not a recipient of operational progress reports from the Team Manager. Option D is wrong because the Senior User (Mary Johnson) represents user requirements and benefits, but the Team Manager's reporting line is to the Project Manager, not to any individual Project Board member.

13
MCQmedium

In PRINCE2, who is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

A.Executive (SRO)
B.Senior User
C.Senior Supplier
D.Project Manager
AnswerD

The Project Manager is responsible for day-to-day management.

Why this answer

The Project Manager is responsible for the day-to-day management of the project within the tolerances set by the Project Board. This includes planning, delegating, monitoring, and controlling all aspects of the project, while reporting any deviations that exceed the agreed tolerances to the Project Board.

Exam trap

The trap here is confusing the Project Manager's operational role with the strategic or representational roles of the Executive, Senior User, or Senior Supplier, leading candidates to incorrectly select a board member for day-to-day management.

How to eliminate wrong answers

Option A is wrong because the Executive (Senior Responsible Owner) is the project's business champion, responsible for the business case and overall project justification, not for day-to-day management. Option B is wrong because the Senior User represents the interests of those who will use the project's outputs and specifies user requirements, but does not manage the project on a daily basis. Option C is wrong because the Senior Supplier represents the interests of those providing the project's products and ensures supplier resources are available, but is not involved in daily project management.

14
MCQmedium

Which document describes the detailed activities, resources, and costs for a single management stage?

A.Stage Plan
B.Team Plan
C.Project Plan
D.Exception Plan
AnswerA

The Stage Plan details activities, resources, and costs for a specific stage.

Why this answer

The Stage Plan is the detailed plan for each management stage, created at the end of the previous stage.

15
MCQmedium

During a project, the Project Board is informed that a major change to the project scope is required. Which role is best placed to assess the impact on the Business Case?

A.Project Assurance
B.Senior User
C.Team Manager
D.Project Manager
AnswerA

Project Assurance independently assesses impacts on the Business Case and advises the Board.

Why this answer

Project Assurance provides independent assessment of project issues, including impact on the Business Case, to the Project Board.

16
Drag & Dropmedium

Drag and drop the steps to close a project in PRINCE2 into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Closing a Project involves preparing closure, handing over products, evaluating, recommending closure, and then formally closing.

17
MCQeasy

In PRINCE2, who is responsible for managing the delivery of a Work Package?

A.Team Manager
B.Senior Supplier
C.Project Manager
D.Project Assurance
AnswerA

The Team Manager manages the delivery of Work Packages.

Why this answer

The Team Manager is responsible for managing the delivery of one or more Work Packages as assigned by the Project Manager.

18
MCQeasy

In PRINCE2, how often does the Project Board typically meet?

A.Daily
B.Monthly
C.Exception-driven
D.Weekly
AnswerC

The Project Board meets when needed, typically at stage boundaries or for exceptions.

Why this answer

In PRINCE2, the Project Board is not a day-to-day management body; it meets only when decisions are needed outside the delegated authority of the Project Manager. The correct frequency is exception-driven, meaning the Board convenes when a stage boundary is reached, an exception report is raised, or the project is ready for closure. This aligns with PRINCE2's principle of management by exception, where the Board's involvement is triggered by specific events rather than a fixed schedule.

Exam trap

The trap here is that candidates often confuse the Project Board's meeting frequency with that of a daily stand-up or weekly team meeting, failing to recognize PRINCE2's core principle of management by exception, which dictates that the Board only convenes when triggered by specific events or stage boundaries.

How to eliminate wrong answers

Option A is wrong because daily meetings would imply hands-on, operational management, which contradicts the Project Board's strategic, governance role in PRINCE2. Option B is wrong because a fixed monthly schedule would force unnecessary meetings even when no decisions are required, violating the management-by-exception principle. Option D is wrong because weekly meetings are too frequent for a board that should only intervene when the Project Manager exceeds tolerances or a stage boundary is reached.

19
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior Responsible Owner (SRO/Executive)
C.Project Assurance
D.Senior User
AnswerB

The SRO owns the Business Case and ensures its viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) owns the Business Case and is responsible for ensuring it remains viable throughout the project.

20
MCQeasy

Which role is responsible for managing the delivery of one or more Work Packages?

A.Project Assurance
B.Team Manager
C.Project Manager
D.Senior User
AnswerB

Correct: the Team Manager manages the team's work on Work Packages.

Why this answer

The Team Manager is responsible for coordinating the team to deliver Work Packages as defined by the Project Manager.

21
Multi-Selecthard

Which THREE of the following are true about the role of the Team Manager in PRINCE2?

Select 3 answers
A.Is accountable for the management of the entire stage
B.Manages the delivery of one or more Work Packages
C.Is an optional role in PRINCE2
D.Is a member of the Project Board
E.Reports to the Project Manager on progress
AnswersB, C, E

The Team Manager is responsible for Work Package delivery.

Why this answer

The Team Manager manages the delivery of one or more Work Packages (A), reports to the Project Manager (B), and is an optional role (C). They do not manage the entire stage (D) and are not part of the Project Board (E).

22
MCQeasy

Which role provides independent assurance to the Project Board that the project is being managed correctly?

A.Project Manager
B.Project Assurance
C.Project Support
D.Team Manager
AnswerB

Project Assurance provides independent oversight to the Project Board.

Why this answer

Project Assurance is independent of the Project Manager and reports to the Project Board.

23
MCQeasy

Who is responsible for appointing the Project Manager?

A.The Project Board
B.The Senior User
C.The Senior Supplier
D.The Change Authority
AnswerA

The Project Board appoints the Project Manager, usually on the recommendation of the Executive.

Why this answer

In PRINCE2, the Project Board is responsible for appointing the Project Manager. This is because the Project Board represents the business, user, and supplier interests and has the authority to delegate day-to-day management to the Project Manager. The Project Board's responsibility includes ensuring the right person is appointed to manage the project on their behalf.

Exam trap

The trap here is that candidates may confuse the Project Board's collective responsibility with the individual roles of Senior User or Senior Supplier, or mistakenly think the Change Authority has broader management powers than it actually does.

How to eliminate wrong answers

Option B is wrong because the Senior User is a member of the Project Board and does not have sole authority to appoint the Project Manager; that responsibility lies with the Project Board as a whole. Option C is wrong because the Senior Supplier, like the Senior User, is a single role on the Project Board and cannot unilaterally appoint the Project Manager. Option D is wrong because the Change Authority is a role responsible for authorizing changes to project baselines, not for appointing the Project Manager.

24
MCQeasy

Which role chairs the Project Board?

A.Executive (SRO)
B.Project Manager
C.Senior User
D.Senior Supplier
AnswerA

The Executive chairs the Project Board.

Why this answer

The Executive (SRO) chairs the Project Board and is accountable for the project's success.

25
MCQmedium

Which role is responsible for managing the delivery of a Work Package?

A.Senior User
B.Project Support
C.Team Manager
D.Project Manager
AnswerC

The Team Manager manages the delivery of the Work Package.

Why this answer

The Team Manager is responsible for delivering the Work Package as defined by the Project Manager.

26
MCQhard

A project is in its Controlling a Stage process. The Team Manager reports that a Work Package is likely to be completed late. The Project Manager reviews the Stage Plan and sees that stage tolerance is not forecast to be exceeded. What should the Project Manager do?

A.Instruct the Team Manager to continue as planned.
B.Close the stage early.
C.Take corrective action within the tolerances delegated by the Project Board.
D.Escalate to the Project Board via an Exception Report.
AnswerC

The Project Manager can manage within tolerances without escalation.

Why this answer

Since stage tolerance is not threatened, the Project Manager can take corrective action within the delegated tolerances, such as re-planning or re-assigning resources, without escalating to the Project Board.

27
MCQmedium

During the Initiating a Project process, which document is created to define the project's scope, objectives, and how it will be managed?

A.Project Brief
B.Project Initiation Documentation (PID)
C.Business Case
D.Benefits Management Approach
AnswerB

The PID is the comprehensive document created during initiation.

Why this answer

The Project Initiation Documentation (PID) is the definitive document created during the Initiating a Project process. It consolidates the project's scope, objectives, and management controls, serving as the foundation for project governance and decision-making. PRINCE2 mandates the PID to ensure all stakeholders have a single source of truth for how the project will be managed.

Exam trap

PeopleCert often tests the distinction between the Project Brief (created in Starting Up a Project) and the PID (created in Initiating a Project), leading candidates to confuse the two documents and their respective purposes.

How to eliminate wrong answers

Option A is wrong because the Project Brief is created during the Starting Up a Project process, not Initiating a Project, and it provides initial context and justification but does not define detailed management approaches. Option C is wrong because the Business Case is a component of the PID, not a standalone document that defines scope and management; it focuses on justification and benefits. Option D is wrong because the Benefits Management Approach is a separate management product that details how benefits will be realized and measured, but it does not define the project's overall scope or management structure.

28
MCQeasy

Who chairs the Project Board in PRINCE2?

A.Senior Responsible Owner (Executive)
B.Senior Supplier
C.Senior User
D.Project Manager
AnswerA

The SRO/Executive chairs the Project Board.

Why this answer

In PRINCE2, the Project Board is chaired by the Executive (also known as the Senior Responsible Owner in many organizations). The Executive is ultimately accountable for the project's success, provides business justification, and ensures the project remains viable. The chairperson role is explicitly assigned to the Executive in the PRINCE2 management structure, not to the Senior Supplier, Senior User, or Project Manager.

Exam trap

The trap here is that candidates often confuse the Project Manager as the chair because they lead project meetings, but PRINCE2 explicitly assigns the Project Board chair to the Executive, not the Project Manager.

How to eliminate wrong answers

Option B (Senior Supplier) is wrong because the Senior Supplier represents the interests of those providing the project's products and resources, but does not chair the Project Board; they are a board member, not the chair. Option C (Senior User) is wrong because the Senior User represents the users' needs and operational requirements, but they are also a board member without the chairing authority. Option D (Project Manager) is wrong because the Project Manager is responsible for day-to-day management and reporting to the Project Board, but they are not a member of the board and certainly do not chair it.

29
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is raised by the Project Manager; an Off-spec is raised by the Project Board
B.An RFC affects the Business Case; an Off-spec does not
C.There is no difference; the terms are interchangeable
D.An RFC is a request for a change to an agreed product; an Off-spec is a product that does not meet its specification
AnswerD

This correctly distinguishes the two.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to change any baselined product, while an Off-specification (Off-spec) is a product that has been identified as not meeting its agreed specification. Option D correctly captures this distinction: an RFC seeks a change to an agreed product, whereas an Off-spec reports a deviation from the specification. This is a fundamental difference in issue handling within PRINCE2's change control approach.

Exam trap

The trap here is that candidates often assume RFCs and Off-specs are the same or that only certain roles can raise them, but PRINCE2 explicitly distinguishes them by purpose and allows any stakeholder to raise either type of issue.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specs can be raised by any project stakeholder, not exclusively by the Project Manager or Project Board. Option B is wrong because an Off-spec can affect the Business Case if the deviation impacts costs, benefits, or risks, just as an RFC can. Option C is wrong because the terms are not interchangeable; they represent distinct types of issues with different purposes and handling procedures.

30
Multi-Selectmedium

Which TWO of the following are elements of a Work Package?

Select 2 answers
A.The product description(s) to be delivered
B.The Business Case
C.The reporting requirements for the Work Package
D.The project's risk register
E.The composition of the project team
AnswersA, C

Work Packages include the description of the products to be produced.

Why this answer

A Work Package includes the product description(s) to be produced and the reporting requirements (e.g., Checkpoint Reports). The Business Case is not part of a Work Package; it is a project-level document. The team's composition is defined in the Project Plan, not in the Work Package.

31
Multi-Selectmedium

Which THREE of the following are responsibilities of the Senior Supplier on the Project Board?

Select 3 answers
A.Providing the necessary resources and expertise for the project
B.Managing the project budget
C.Defining user acceptance criteria
D.Ensuring that the supplier's products meet the required quality standards
E.Advising on the design and feasibility of supplier solutions
AnswersA, D, E

The Senior Supplier secures supplier resources.

Why this answer

The Senior Supplier is responsible for providing supplier resources, ensuring the quality of supplier deliverables, and advising on design and feasibility. The Senior Supplier does not define user acceptance criteria (that's the Senior User) nor manage the project budget (that's the SRO/Executive).

32
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Manager?

Select 3 answers
A.Provide independent assurance to the Project Board
B.Set project tolerances
C.Prepare the Stage Plan for approval
D.Manage the project on a day-to-day basis
E.Manage risks and issues
AnswersC, D, E

The PM prepares stage plans.

Why this answer

Option C is correct because the Project Manager is responsible for preparing the Stage Plan for approval by the Project Board. This is a key task in the PRINCE2 'Planning' process, where the Project Manager develops detailed plans for each management stage based on the Project Plan and stage-level tolerances.

Exam trap

The trap here is confusing the Project Manager's role with that of the Project Board or Project Assurance, leading candidates to incorrectly select 'Set project tolerances' (a board responsibility) or 'Provide independent assurance' (an assurance responsibility) instead of focusing on the manager's operational duties.

33
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Approving the Stage Plan for the next stage
B.Preparing the Highlight Report
C.Maintaining the Business Case
D.Managing the delivery of Work Packages
E.Authorizing deviations from stage tolerances
AnswersA, E

The Board approves Stage Plans.

Why this answer

The Project Board is responsible for authorizing the project, providing direction, and making key decisions. Option A (approve stage plans) and Option C (authorize deviations from stage tolerances) are Board responsibilities. Option B (manage Work Packages) is Team Manager; Option D (prepare Highlight Reports) is PM; Option E (maintain the Business Case) is PM with SRO accountability.

34
MCQmedium

Which role is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager?

A.Project Manager
B.Senior Supplier
C.Team Manager
D.Project Support
AnswerC

Correct role.

Why this answer

In PRINCE2, the Team Manager is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager. This role ensures that the products defined in the Work Package are created to the required quality, within time and cost constraints, and provides regular progress reports to the Project Manager.

Exam trap

The trap here is that candidates often confuse the Team Manager with the Project Manager, assuming the Project Manager directly manages all work, but PRINCE2 explicitly separates these roles to enable delegation and management by exception.

How to eliminate wrong answers

Option A is wrong because the Project Manager is responsible for overall project management, not for the direct delivery of Work Packages; they delegate that to the Team Manager. Option B is wrong because the Senior Supplier represents the supplier interests on the Project Board and is not involved in day-to-day Work Package delivery or progress reporting to the Project Manager. Option D is wrong because Project Support provides administrative and advisory services, such as maintaining registers and providing planning support, but does not manage Work Packages or report progress on their delivery.

35
MCQhard

In PRINCE2, what is the purpose of the 'Managing a Stage Boundary' process?

A.To manage the delivery of work packages and monitor progress
B.To define the project scope and create the Project Plan
C.To produce an Exception Plan when a stage is forecast to exceed tolerances
D.To enable the Project Board to review the current stage and approve the next stage plan
AnswerD

This is the correct purpose of the Managing a Stage Boundary process.

Why this answer

The 'Managing a Stage Boundary' process in PRINCE2 is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and confirm continued business justification. This process ensures that the project remains viable and that the Project Board can make informed go/no-go decisions before committing resources to the next stage.

Exam trap

The trap here is that candidates often confuse the primary purpose of 'Managing a Stage Boundary' (review and approval of the next stage) with the specific activity of producing an Exception Plan, which is a conditional output, not the core purpose.

How to eliminate wrong answers

Option A is wrong because managing the delivery of work packages and monitoring progress is the purpose of the 'Controlling a Stage' process, not 'Managing a Stage Boundary'. Option B is wrong because defining the project scope and creating the Project Plan is the purpose of the 'Initiating a Project' process. Option C is wrong because producing an Exception Plan is an activity that occurs within the 'Managing a Stage Boundary' process when tolerances are forecast to be exceeded, but it is not the primary purpose of the process; the main purpose is to enable the Project Board to review and approve the next stage.

36
MCQhard

The Project Board consists of three roles. Which of the following is NOT a mandatory role on the Project Board?

A.Senior Responsible Owner (Executive)
B.Project Manager
C.Senior Supplier
D.Senior User
AnswerB

The Project Manager attends Project Board meetings but is not a member.

Why this answer

The mandatory roles are Senior User, Senior Supplier, and Senior Responsible Owner. The Project Manager is not a member of the Project Board.

37
MCQmedium

In PRINCE2, what is the main reason for separating the Project Manager role from the Project Assurance role?

A.To reduce the workload of the Project Manager
B.To ensure independent monitoring and control of the project
C.To allow the Project Manager to focus on technical tasks
D.To enable the Project Board to delegate more responsibilities
AnswerB

Project Assurance provides an independent view to the Project Board, not influenced by the Project Manager.

Why this answer

Separation ensures independent and objective assurance that the project is running correctly, free from the biases or conflicts of day-to-day management.

38
MCQmedium

According to PRINCE2, who is responsible for authorizing the work packages to be executed by the team?

A.Project Board
B.Senior Responsible Owner
C.Project Manager
D.Team Manager
AnswerC

The Project Manager authorizes work packages.

Why this answer

The Project Manager authorizes work packages to Team Managers as part of the Controlling a Stage process.

39
Multi-Selecthard

Which TWO of the following statements about the Project Board are correct?

Select 2 answers
A.The Project Board meets on a regular basis (e.g., weekly)
B.The Project Board meets only when decisions are required (exception-driven)
C.The Project Board is accountable for the success of the project
D.The Senior User chairs the Project Board
E.The Project Board authorizes the Work Packages
AnswersB, C

Correct: Project Board meetings are held at stage boundaries or when exceptions occur.

Why this answer

Option B is correct because the Project Board in PRINCE2 is designed to be an exception-driven body; it convenes only when decisions are required, such as approving stage plans or exception plans, rather than on a fixed schedule. This aligns with the PRINCE2 principle of management by exception, where the board delegates day-to-day management to the Project Manager and escalates only when tolerances are forecast to be exceeded.

Exam trap

The trap here is that candidates often confuse the Project Board's meeting frequency with a typical steering committee that meets regularly, but PRINCE2 specifically mandates an exception-driven approach, not a fixed schedule.

40
MCQmedium

What is the minimum frequency of Project Board meetings?

A.Monthly
B.At each stage boundary and when an exception occurs
C.Only at the start and end of the project
D.Weekly
AnswerB

The Project Board meets at key decision points and when exceptions arise.

Why this answer

The Project Board meets at predetermined points (stage boundaries) and when an exception is raised. They are exception-driven, so there is no fixed minimum frequency.

41
MCQmedium

The Project Board has delegated authority for change control decisions to a separate body. What is this body called?

A.Change Authority
B.Project Support
C.Project Assurance
D.Senior Supplier
AnswerA

The Change Authority is an optional role to which the Project Board delegates change control decisions.

Why this answer

PRINCE2 allows the Project Board to delegate change control decisions to a Change Authority, which can approve changes within defined limits.

42
MCQeasy

Which role is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

A.Project Assurance
B.Team Manager
C.Project Manager
D.Senior Responsible Owner (SRO/Executive)
AnswerC

This is a core responsibility of the Project Manager.

Why this answer

The Project Manager manages the project on a day-to-day basis within the tolerances delegated by the Project Board.

43
MCQmedium

In PRINCE2, what is the role of the Senior Supplier on the Project Board?

A.To manage the project budget
B.To chair the Project Board meetings
C.To represent the interests of the users
D.To provide the necessary resources and expertise for the project
AnswerD

The Senior Supplier ensures the project has the required supplier resources and that the supplier's view is represented.

Why this answer

The Senior Supplier represents those who provide the necessary goods, services, and expertise to the project.

44
MCQmedium

The Project Manager notes that a Work Package is at risk of being delivered late. What should the Project Manager do?

A.Agree corrective actions with the Team Manager within the Work Package tolerances
B.Update the Project Plan immediately
C.Immediately escalate to the Project Board
D.Cancel the Work Package and reassign it to another team
AnswerA

The PM manages within stage tolerances and works with the Team Manager.

Why this answer

The Project Manager should first discuss with the Team Manager and consider options before escalating to the Project Board if necessary.

45
MCQeasy

Which PRINCE2 role is optional and provides administrative support to the project?

A.Change Authority
B.Project Assurance
C.Team Manager
D.Project Support
AnswerD

Project Support is optional and provides admin support.

Why this answer

In PRINCE2, Project Support is an optional role that provides administrative services to the project, such as maintaining files, collecting progress data, and managing project documentation. The role is not mandatory because the project manager can perform these tasks or they can be delegated to a separate support function. This distinguishes it from the other roles, which have specific governance or delivery responsibilities.

Exam trap

The trap here is that candidates often confuse Project Support with Project Assurance, thinking both are mandatory oversight roles, but PRINCE2 explicitly separates administrative support (optional) from independent assurance (optional but distinct).

How to eliminate wrong answers

Option A is wrong because the Change Authority is a role that authorizes changes to baselines, not administrative support; it is optional but focuses on change control decisions. Option B is wrong because Project Assurance is an optional role that provides independent oversight and checks compliance with PRINCE2, not administrative support. Option C is wrong because the Team Manager is an optional role that manages the technical delivery of products within a team, not administrative support for the project.

46
MCQeasy

Which of the following is an optional role in the PRINCE2 project management team?

A.Executive
B.Senior User
C.Project Support
D.Project Manager
AnswerC

Project Support is optional and can be provided by a separate team member.

Why this answer

In PRINCE2, the Project Support role is optional and is only required when the project is large or complex enough to need administrative or specialist support. The PRINCE2 manual explicitly lists Project Support as a role that may be filled, whereas the Executive, Senior User, and Project Manager are mandatory roles on every project.

Exam trap

The trap here is that candidates often assume all roles listed in the PRINCE2 team structure are mandatory, but PRINCE2 explicitly designates Project Support as optional, while the Executive, Senior User, and Project Manager are always required.

How to eliminate wrong answers

Option A is wrong because the Executive is a mandatory role who owns the business case and provides overall accountability for the project. Option B is wrong because the Senior User is a mandatory role who represents the interests of those who will use the project's outputs. Option D is wrong because the Project Manager is a mandatory role who manages the day-to-day work and is required on every PRINCE2 project.

47
MCQmedium

In PRINCE2, what is the role of the Change Authority?

A.To manage the configuration of project products
B.To authorize Work Packages on behalf of the Project Manager
C.To make decisions on change requests within delegated authority
D.To approve all changes to the project scope
AnswerC

This is the definition of Change Authority.

Why this answer

The Change Authority is an optional role that can make decisions on change requests within delegated limits, relieving the Project Board.

48
Multi-Selectmedium

Which TWO of the following statements about the Change Authority role in PRINCE2 are correct?

Select 2 answers
A.The Change Authority must be a single individual
B.The Change Authority is delegated by the Project Board to make decisions on change requests within agreed tolerances
C.The Change Authority is an optional role
D.The Change Authority is responsible for updating the Project Plan
E.The Change Authority cannot approve changes that affect the Business Case
AnswersB, C

This is the purpose of the Change Authority.

Why this answer

The Change Authority is an optional role that can make decisions on change requests within agreed limits, and it can be a person or group.

49
MCQmedium

During which process is the Project Initiation Documentation (PID) created?

A.Starting Up a Project
B.Initiating a Project
C.Managing a Stage Boundary
D.Directing a Project
AnswerB

The PID is the key output of the Initiating a Project process.

Why this answer

The PID is created during the Initiating a Project process, which formalizes the project's start.

50
MCQhard

Why does PRINCE2 separate the Project Manager role from Project Assurance?

A.To provide independent oversight and avoid conflicts of interest
B.To allow the Project Manager to focus on technical tasks
C.To reduce the workload of the Project Manager
D.To ensure the Project Board can delegate assurance to the Project Manager
AnswerA

Independence is key to effective assurance.

Why this answer

PRINCE2 separates the Project Manager from Project Assurance to ensure independent oversight of the project's ongoing viability, compliance, and quality. The Project Manager is responsible for day-to-day management and delivery, while Project Assurance provides an objective check that the project remains aligned with business justifications, standards, and controls. This separation prevents the Project Manager from being both the doer and the sole judge of their own work, avoiding conflicts of interest that could compromise governance.

Exam trap

The trap here is that candidates confuse Project Assurance with a support or delegation function, rather than recognizing it as a mandatory independent oversight role that cannot be combined with the Project Manager's responsibilities.

How to eliminate wrong answers

Option B is wrong because PRINCE2 does not define 'technical tasks' as a primary focus for the Project Manager; the role is about management, coordination, and control, not technical execution. Option C is wrong because workload reduction is not the purpose of the separation; the roles are distinct to provide checks and balances, not to lighten the Project Manager's load. Option D is wrong because the Project Board cannot delegate Project Assurance to the Project Manager; doing so would eliminate the independent oversight that the role is designed to provide, violating the principle of separation of duties.

51
MCQhard

A Project Manager is appointed to a project during the Starting Up a Project process. The project has a complex technical scope. The SRO wants to ensure that the Project Board receives independent assurance on technical decisions. Who should provide this assurance?

A.The Senior Supplier, as they represent the supplier interests.
B.A Team Manager assigned to the project.
C.The Project Manager, as they have the technical expertise.
D.A person appointed to the Project Assurance role with technical expertise.
AnswerD

Project Assurance is independent and can be staffed with technical expertise.

Why this answer

Project Assurance is an independent oversight role that reports to the Project Board. The SRO can assign technical assurance to an individual with appropriate skills, separate from the Project Manager.

52
MCQmedium

Which role is responsible for ensuring that the project is being managed correctly from the business perspective?

A.Project Assurance
B.Senior User
C.Project Support
D.Project Manager
AnswerA

Project Assurance is independent and assures the Project Board.

Why this answer

Project Assurance provides independent oversight to the Project Board, ensuring the project is managed correctly from business, user, and supplier perspectives. The Executive is accountable but Project Assurance performs the checks.

53
Multi-Selecteasy

Which TWO of the following are true about Project Assurance?

Select 2 answers
A.It is a mandatory role in all projects
B.It ensures the project is being conducted correctly
C.It is a role that can be performed by the Project Manager
D.It focuses only on quality management
E.It provides independent oversight on behalf of the Project Board
AnswersB, E

Assurance ensures compliance with standards and processes.

Why this answer

Option B is correct because Project Assurance is a PRINCE2 role that verifies the project is being conducted correctly, meaning it checks that the project remains viable, adheres to its business case, and follows the defined management stages. It is not about doing the work but about ensuring compliance with the project's plans, controls, and standards. This aligns with PRINCE2's principle of continued business justification and the need for independent oversight.

Exam trap

The trap here is that candidates often confuse Project Assurance with Project Support or Quality Management, or assume the Project Manager can double-hat as the assurance role, but PRINCE2 explicitly requires independence to avoid bias and ensure objective oversight.

54
Multi-Selectmedium

Which TWO statements about the project board are correct? (Choose two.)

Select 2 answers
A.The project board provides unified direction to the project
B.The project board is responsible for managing the project team on a day-to-day basis
C.The project board is responsible for identifying and managing risks
D.The project board is accountable for the success of the project
E.The project board produces the project's products
AnswersA, D

The board provides unified direction.

Why this answer

Option A is correct because the project board provides unified direction to the project, ensuring that the business, user, and supplier interests are represented and aligned. This is a core PRINCE2 principle: the board makes key decisions and approves stage plans, but does not get involved in day-to-day management.

Exam trap

The trap here is confusing accountability with responsibility: candidates often think the board handles day-to-day tasks or product creation, but PRINCE2 strictly separates strategic oversight from operational management.

55
MCQhard

Why does PRINCE2 separate the Project Manager from Project Assurance?

A.To reduce the workload of the Project Manager
B.To allow the Project Manager to focus on technical work
C.To ensure that the Project Board is kept informed
D.To provide independent oversight and avoid conflicts of interest
AnswerD

Correct. Project Assurance is independent from the PM.

Why this answer

Separation ensures independent oversight of the Project Manager's work, preventing conflicts of interest and providing objective assurance to the Project Board.

56
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Senior Responsible Owner (Executive)
D.Project Support
AnswerC

The SRO is accountable for the Business Case and its viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and ensuring the project remains viable. The Project Manager maintains the Business Case on a day-to-day basis but the SRO holds ultimate responsibility.

57
MCQhard

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are interchangeable terms
B.An RFC is always approved; an Off-specification is always rejected
C.An RFC is raised by the Project Board; an Off-specification is raised by the Project Manager
D.An RFC proposes a change to an agreed baseline; an Off-specification identifies a product that does not meet its specification
AnswerD

Correct distinction.

Why this answer

An RFC requests a desired change not in the original specification; an Off-specification is a deliverable that does not meet agreed specifications.

58
MCQmedium

In PRINCE2, who manages the delivery of Work Packages?

A.Team Manager
B.Project Support
C.Project Manager
D.Senior User
AnswerA

Correct. The Team Manager manages Work Package delivery.

Why this answer

The Team Manager is responsible for managing the delivery of one or more Work Packages and reports to the Project Manager.

59
MCQeasy

Which role delegates change control decisions to a Change Authority?

A.Team Manager
B.Project Board
C.Senior Supplier
D.Project Manager
AnswerB

The Project Board delegates change control decisions to the Change Authority.

Why this answer

In PRINCE2, the Project Board is responsible for overall project governance, including delegating change control decisions to a Change Authority. This delegation allows the Change Authority to approve or reject change requests within predefined limits, freeing the Board from day-to-day change management while retaining strategic oversight.

Exam trap

The trap here is that candidates often confuse the Project Manager's role in recommending changes with the authority to delegate change control, but PRINCE2 explicitly reserves that delegation power for the Project Board.

How to eliminate wrong answers

Option A is wrong because the Team Manager focuses on delivering the work packages within their team and does not have authority over change control decisions. Option C is wrong because the Senior Supplier is a specific role on the Project Board representing the supplier's interests, not a separate role that delegates change authority. Option D is wrong because the Project Manager manages day-to-day activities and may recommend changes but does not have the authority to delegate change control decisions; that authority rests with the Project Board.

60
MCQmedium

Which role is responsible for the independent assurance that the project remains on track?

A.Project Assurance
B.Project Support
C.Team Manager
D.Project Manager
AnswerA

Project Assurance provides independent assurance to the Project Board.

Why this answer

Project Assurance is the role responsible for providing independent assurance that the project remains on track, as defined by PRINCE2. It ensures that the project is being conducted correctly, adheres to the business case, and meets quality standards, without being involved in the day-to-day management. This role is separate from the Project Manager and Project Support to maintain objectivity.

Exam trap

The trap here is that candidates often confuse Project Assurance with Project Support, thinking both are administrative roles, but Project Assurance is a governance function focused on independent oversight, while Project Support is purely administrative.

How to eliminate wrong answers

Option B is wrong because Project Support provides administrative and clerical services to the project team, not independent oversight or assurance. Option C is wrong because the Team Manager is responsible for delivering the work packages within their team, not for independent assurance across the entire project. Option D is wrong because the Project Manager manages the project on a day-to-day basis and cannot provide independent assurance due to their direct involvement and potential bias.

61
Multi-Selecthard

Which THREE of the following are reasons why PRINCE2 recommends separating the Project Manager from Project Assurance?

Select 3 answers
A.To ensure objective and independent monitoring of the project
B.To provide the Project Board with an independent view that the project is being managed correctly
C.To reduce the overall cost of project management
D.To avoid a conflict of interest between managing and assuring the project
E.To speed up decision-making by the Project Board
AnswersA, B, D

Independence is key for unbiased assurance.

Why this answer

Independence ensures objective oversight, reduces conflict of interest, and helps identify issues early. It does not speed up decisions (that may be slower) nor reduce costs (it adds overhead).

62
Multi-Selectmedium

Which TWO of the following are roles that are part of the Project Board?

Select 2 answers
A.Senior User
B.Team Manager
C.Executive
D.Project Assurance
E.Project Support
AnswersA, C

The Senior User is a mandatory Project Board role.

Why this answer

The Project Board is the PRINCE2 management layer responsible for overall project direction and key decision-making. The Senior User is a mandatory Project Board role representing the interests of those who will use the project's products, ensuring the project delivers the required benefits. The Executive is also a mandatory Project Board role, acting as the project's ultimate decision-maker and owner of the business case.

Exam trap

PeopleCert often tests the distinction between roles that are part of the Project Board (Executive, Senior User, Senior Supplier) and roles that support or execute within the Project Management Team (Project Manager, Team Manager, Project Assurance, Project Support), tempting candidates to select Project Assurance or Project Support as Board members.

63
MCQmedium

A large IT project is implementing a new customer relationship management (CRM) system for a multinational corporation. The project is organized with a Project Board comprising the Executive (VP of Sales), Senior User (Regional Sales Director), and Senior Supplier (IT Director). The Project Manager is an experienced PMP-certified professional. The team includes several business analysts and developers from an external supplier. The project has just completed the Initiating a Project process and received authorization to proceed to the next stage. However, during the first week of the Delivery Stage, the Project Manager notices that the business analysts are not collaborating effectively with the developers, leading to misunderstandings about requirements. The Project Manager holds a meeting and discovers that the business analysts feel excluded from decision-making and the developers complain about unclear specifications. The Project Manager wants to resolve this using PRINCE2 principles and practices. Which of the following is the BEST course of action?

A.Ignore the issue as it is a normal part of team dynamics and will resolve itself over time.
B.Replace the business analysts with more experienced ones who can work better with developers.
C.Revisit the Communication Management Strategy and clarify roles and responsibilities in the team.
D.Escalate the issue to the Project Board for a decision on how to restructure the team.
AnswerC

Correct: The Project Manager should use the Communication Management Strategy to facilitate collaboration and ensure roles are clear.

Why this answer

Option C is correct because PRINCE2's Communication Management Strategy is the formal mechanism for defining roles, responsibilities, and information flows. By revisiting it, the Project Manager can clarify the business analysts' and developers' roles in decision-making and requirements specification, directly addressing the root cause of misunderstandings. This aligns with the 'Manage by Stages' and 'Defined Roles and Responsibilities' principles, ensuring the team collaborates effectively without unnecessary escalation or personnel changes.

Exam trap

The trap here is that candidates may assume any team conflict requires escalation to the Project Board (Option D), but PRINCE2 reserves escalation only for issues exceeding stage tolerances or requiring business-level decisions, not for internal team coordination problems.

How to eliminate wrong answers

Option A is wrong because ignoring the issue violates PRINCE2's 'Manage by Exception' principle; unresolved team dynamics can escalate into requirements errors and rework, jeopardizing stage tolerances. Option B is wrong because replacing team members without first addressing the communication breakdown ignores the PRINCE2 focus on process improvement and the 'Learn from Experience' principle; the problem is likely procedural, not individual competence. Option D is wrong because the issue is within the Project Manager's authority to resolve via the Communication Management Strategy; escalating to the Project Board for a team restructuring decision bypasses the PM's responsibility and violates the 'Manage by Stages' principle where the PM manages day-to-day issues.

64
MCQeasy

Who is responsible for managing the delivery of a Work Package?

A.Project Manager
B.Project Support
C.Team Manager
D.Senior Supplier
AnswerC

The Team Manager manages Work Package delivery.

Why this answer

The Team Manager is responsible for the delivery of one or more Work Packages and reports to the Project Manager.

65
MCQmedium

In PRINCE2, the Project Board typically meets on which basis?

A.Weekly
B.Exception-driven
C.Daily
D.At the end of each stage
AnswerB

The Project Board meets only when needed to make decisions outside delegated tolerances.

Why this answer

In PRINCE2, the Project Board is a decision-making body that manages by exception. It does not meet on a fixed schedule like weekly or daily; instead, it convenes only when a deviation from the plan (an exception) requires its intervention, such as when a stage plan exceeds tolerance levels. This exception-driven approach ensures the Board focuses on strategic oversight rather than operational details.

Exam trap

The trap here is that candidates confuse the Project Board's meeting frequency with the project manager's regular reporting (e.g., Highlight Reports) or with the mandatory end-stage assessments, mistakenly thinking the Board meets on a fixed schedule or only at stage ends.

How to eliminate wrong answers

Option A is wrong because PRINCE2 does not prescribe a weekly meeting cadence for the Project Board; such a fixed schedule would undermine the management-by-exception principle and burden the Board with routine updates. Option C is wrong because daily meetings are far too frequent for a strategic oversight body and would conflict with the project manager's day-to-day management responsibilities. Option D is wrong because while the Board does approve stage boundaries, it does not meet only at the end of each stage; it may also convene for ad-hoc decisions or exception situations between stages.

66
MCQhard

Why does PRINCE2 separate the Project Manager from Project Assurance?

A.To create a career path for team members
B.To ensure that the Project Board receives independent and objective assurance
C.To reduce the workload of the Project Manager
D.To allow the Project Manager to focus on team management
AnswerB

Correct.

Why this answer

The separation ensures independent oversight. The Project Manager is responsible for day-to-day management, while Project Assurance provides an impartial view to the Project Board to avoid conflicts of interest.

67
MCQmedium

What is the difference between a Request for Change (RFC) and an Off-specification?

A.An RFC proposes a change; an Off-specification reports a failure to meet the specification
B.An RFC impacts time; an Off-specification impacts cost
C.An RFC is handled by the Project Manager; an Off-specification goes to the Project Board
D.An RFC is raised by the Project Board; an Off-specification is raised by the Project Manager
AnswerA

Correct: RFCs are for desired modifications; Off-specifications are for deviations from the original specification.

Why this answer

An RFC is a proposal for a modification (change) to the project's products, while an Off-specification is a situation where a product does not meet its specification (a deviation).

68
MCQmedium

In PRINCE2, a Team Manager reports to the Project Manager. What is the primary responsibility of a Team Manager?

A.Provide independent assurance to the Project Board
B.Deliver one or more Work Packages as defined in the Stage Plan
C.Update the Business Case
D.Manage day-to-day project activities across all stages
AnswerB

Correct. The Team Manager manages work package delivery.

Why this answer

The Team Manager is responsible for delivering one or more Work Packages as defined in the Stage Plan. This role focuses on the technical delivery of products within the constraints agreed with the Project Manager, ensuring quality, time, and cost targets are met for those specific work packages.

Exam trap

The trap here is confusing the Team Manager's scope with the Project Manager's broader responsibilities, leading candidates to select Option D, which describes the Project Manager's role, not the Team Manager's.

How to eliminate wrong answers

Option A is wrong because providing independent assurance to the Project Board is the responsibility of the Project Assurance role, not the Team Manager. Option C is wrong because updating the Business Case is the responsibility of the Senior User or Executive, not the Team Manager. Option D is wrong because managing day-to-day project activities across all stages is the responsibility of the Project Manager, while the Team Manager only manages activities within their assigned Work Packages.

69
MCQhard

What is the key difference between Project Assurance and Project Support?

A.Project Assurance is a role performed by the Project Manager, whereas Project Support is performed by the team
B.Project Assurance provides independent oversight on behalf of the Project Board; Project Support provides administrative services to the Project Manager
C.Project Assurance focuses on quality, while Project Support focuses on risk management
D.Project Assurance is optional, while Project Support is mandatory
AnswerB

This is the correct distinction as defined in PRINCE2.

Why this answer

Option B is correct because Project Assurance is an independent oversight function, performed on behalf of the Project Board, to ensure that the project is being conducted correctly and remains viable. Project Support, in contrast, is a set of administrative and advisory services provided to the Project Manager to help them manage the project effectively. This distinction is fundamental to PRINCE2's separation of 'doing' from 'checking'.

Exam trap

The trap here is confusing the independent oversight of Project Assurance with the administrative assistance of Project Support, leading candidates to incorrectly assign Assurance to the Project Manager or to think Support is optional.

How to eliminate wrong answers

Option A is wrong because Project Assurance is not performed by the Project Manager; it is an independent role, often fulfilled by someone outside the project management team, while Project Support is provided to the Project Manager, not by the team. Option C is wrong because both Project Assurance and Project Support can address quality and risk; the key difference is not the focus area but the independence and accountability (Assurance reports to the Board, Support assists the Manager). Option D is wrong because both Project Assurance and Project Support are mandatory roles in PRINCE2; neither is optional.

70
Multi-Selectmedium

Which THREE of the following statements about the Project Board are correct?

Select 3 answers
A.The Project Board authorizes stage boundaries
B.The Project Board is accountable for the success of the project
C.The Project Board approves the Project Plan
D.The Project Board includes the Project Manager
E.The Project Board meets on a fixed schedule monthly
AnswersA, B, C

Yes, the Board authorizes stage transitions.

Why this answer

Option A is correct because the Project Board is responsible for authorizing the movement from one stage to the next, which includes approving the Stage Plan for the next stage and reviewing the current stage's completion. This is a key control point in PRINCE2's stage-gate management approach, ensuring that the project only proceeds when the Board is satisfied with progress and the business case remains viable.

Exam trap

The trap here is that candidates often confuse the Project Board's composition with the project team, mistakenly including the Project Manager, or assume a fixed meeting schedule similar to a steering committee in other methodologies, whereas PRINCE2 mandates event-driven rather than time-driven Board meetings.

71
MCQmedium

What is the key difference between Project Assurance and a quality review?

A.Project Assurance is performed by the Project Manager; quality review is performed by the team
B.Quality review is a role; Project Assurance is a process
C.They are the same thing
D.Project Assurance is a role; quality review is a technique
AnswerD

Correct. Project Assurance is a continuous role; quality review is a technique used to assess product quality.

Why this answer

Project Assurance is a role within the PRINCE2 management structure, responsible for ensuring that the project remains viable and compliant with the business case, while a quality review is a technique used to assess the quality of a product. Option D correctly distinguishes between these two concepts: Project Assurance is a role, and quality review is a technique. This aligns with PRINCE2's separation of management responsibilities from quality control activities.

Exam trap

The trap here is that candidates confuse the hierarchical nature of PRINCE2 roles and techniques, often misidentifying Project Assurance as a process or quality review as a role, due to the similar-sounding names and overlapping involvement in quality activities.

How to eliminate wrong answers

Option A is wrong because Project Assurance is not performed by the Project Manager; it is an independent role performed by the Project Board or its delegates, while quality review involves the team, but the key difference is not about who performs them. Option B is wrong because it reverses the definitions: quality review is a technique, not a role, and Project Assurance is a role, not a process. Option C is wrong because they are fundamentally different concepts: Project Assurance is a governance role ensuring ongoing compliance, while quality review is a specific technique for product quality assessment.

72
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Manager?

Select 3 answers
A.Producing Highlight Reports
B.Performing Project Assurance
C.Day-to-day management of the project
D.Chairing the Project Board
E.Maintaining the Business Case
AnswersA, C, E

The PM produces Highlight Reports for the board.

Why this answer

The Project Manager manages day-to-day activities, produces Highlight Reports for the board, and updates the Business Case as needed. The PM does not chair the board or perform assurance.

73
MCQmedium

Which role is responsible for the day-to-day management of a Work Package?

A.Project Support
B.Senior User
C.Team Manager
D.Project Manager
AnswerC

The Team Manager manages the delivery of Work Packages.

Why this answer

The Team Manager is responsible for delivering Work Packages and managing the team's day-to-day work, reporting to the Project Manager.

74
Multi-Selectmedium

Which TWO of the following are roles defined in PRINCE2?

Select 2 answers
A.Team Manager
B.Project Assurance
C.Project Sponsor
D.Business Analyst
E.Project Sponsor
AnswersA, B

Team Manager is a PRINCE2 role responsible for managing work packages.

Why this answer

Team Manager and Project Assurance are PRINCE2 roles. The others are not.

75
MCQhard

In PRINCE2, what is the difference between accountability and responsibility?

A.There is no difference; the terms are synonyms.
B.Accountability is ultimately held by one person; responsibility can be shared or delegated.
C.Accountability is assigned to individuals; responsibility is shared among teams.
D.Accountability can be delegated; responsibility cannot.
AnswerB

Accountability cannot be delegated, while responsibility can be shared or delegated.

Why this answer

In PRINCE2, accountability refers to the ultimate answerability for the successful completion of a deliverable or objective, and it is always held by a single person (e.g., the project manager is accountable for the project). Responsibility, in contrast, can be shared among multiple team members or delegated to others who perform the work. Option B correctly captures this distinction, which is fundamental to the PRINCE2 management product structure and role definitions.

Exam trap

The trap here is that candidates often confuse accountability with responsibility, assuming they are interchangeable or that accountability can be delegated like responsibility, leading them to pick Option A or D.

How to eliminate wrong answers

Option A is wrong because PRINCE2 explicitly distinguishes between accountability (ultimate ownership, held by one person) and responsibility (task execution, can be shared or delegated); they are not synonyms. Option C is wrong because while accountability is assigned to individuals, responsibility is not necessarily shared among teams—it can be assigned to a single individual as well, and the key difference is that accountability cannot be shared or delegated. Option D is wrong because it reverses the PRINCE2 principle: accountability cannot be delegated (it remains with the person who holds it), whereas responsibility can be delegated to others to perform the work.

Page 1 of 5 · 335 questions totalNext →

Ready to test yourself?

Try a timed practice session using only People: organizations, teams, and leadership questions.