PRINCE2F People: organizations, teams, and leadership Practice Question
Which role is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Executive (Senior Responsible Owner)
The Executive (Senior Responsible Owner) is accountable for the Business Case and ensuring it remains viable. The Project Manager maintains it on a day-to-day basis, but the Executive holds ultimate responsibility.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier provides resources and expertise but is not accountable for the Business Case.
- ✗
Project Manager
Why it's wrong here
The Project Manager maintains the Business Case on behalf of the Executive but does not hold overall accountability.
- ✗
Senior User
Why it's wrong here
The Senior User specifies the benefits and ensures the project delivers them, but does not own the Business Case.
- ✓
Executive (Senior Responsible Owner)
Why this is correct
The Executive is accountable for the Business Case and its viability throughout the project.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.