PRINCE2F People: organizations, teams, and leadership Practice Question
Who is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior Responsible Owner (SRO)
The Senior Responsible Owner (SRO) is the single person accountable for the Business Case and ensuring the project delivers the expected benefits. The Project Manager maintains the project documentation but the SRO owns the Business Case.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Senior Responsible Owner (SRO)
Why this is correct
The SRO is accountable for the Business Case and its maintenance throughout the project.
- ✗
Project Manager
Why it's wrong here
The Project Manager maintains the project documentation but does not own the Business Case.
- ✗
Project Assurance
Why it's wrong here
Project Assurance provides independent oversight but does not maintain the Business Case.
- ✗
Senior User
Why it's wrong here
The Senior User represents the users and specifies the requirements but is not accountable for the Business Case.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.