PRINCE2F People: organizations, teams, and leadership Practice Question
Who is responsible for the day-to-day management of a project within the tolerances set by the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager is delegated the authority to manage the project on a day-to-day basis within agreed tolerances.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior Responsible Owner
Why it's wrong here
The SRO has overall accountability but does not manage day-to-day.
- ✗
Team Manager
Why it's wrong here
The Team Manager manages the work package delivery, not the whole project.
- ✗
Project Board
Why it's wrong here
The Project Board sets tolerances and makes strategic decisions.
- ✓
Project Manager
Why this is correct
The Project Manager manages the project within tolerances set by the Project Board.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.