Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Who is responsible for defining the project's tolerance levels?

⚠ Common exam trap

A common misconception is that the Project Manager defines project tolerances, but in PRINCE2, the Project Manager only sets stage and work package tolerances, while the Project Board sets the overarching project tolerances.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

In PRINCE2, the Project Board is responsible for defining project-level tolerance levels for time, cost, quality, scope, risk, and benefits. This is because the Project Board represents the business, user, and supplier interests and sets the boundaries within which the Project Manager can operate without needing to escalate. The Project Manager works within these tolerances and only escalates if forecasts exceed them.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    Tolerance levels are set by the Project Board, which owns the project's boundaries; the Senior User represents user interests and specifies requirements, so cannot authorise tolerances. Delegating tolerance-setting to a Senior User is tempting because that role does define acceptance criteria and benefits, but authority over tolerances sits with the Board.

  • ✗

    Project Manager

    Why it's wrong here

    Tolerance levels are set by the project board, which owns the project within the boundaries delegated by corporate or programme management; the project manager works within them. It is tempting because the project manager manages day-to-day delivery, and would be correct for escalating a forecast breach of those tolerances.

  • ✗

    Team Manager

    Why it's wrong here

    Team managers manage the delivery of work packages within the tolerances the project manager assigns to them; they do not define project-level tolerances. It is tempting because team managers handle work-package-level boundaries, and would be correct for agreeing the tolerance for a single work package.

  • ✓

    Project Board

    Why this is correct

    The Project Board sets the tolerances within which the Project Manager may manage by exception, defining the permissible deviation in time, cost, scope, quality, risk and benefit. This authority cannot be delegated to the Project Manager or Team Manager, since tolerances bound the delegated mandate itself.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.