PRINCE2F People: organizations, teams, and leadership Practice Question

Who is responsible for maintaining the Business Case throughout the project?

⚠ Common exam trap

It's easy for candidates to confuse the Project Manager's role in producing the Business Case with the Executive's role in owning and maintaining it, leading them to incorrectly select the Project Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Executive (SRO)

The Executive (Senior Responsible Owner, SRO) is the single point of accountability for the Business Case in PRINCE2. They are responsible for ensuring that the project remains viable and that the Business Case is maintained and updated throughout the project lifecycle, including at stage boundaries and at the end of the project. The Project Manager may draft or update the document, but the Executive owns the justification and must approve any changes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The Project Manager manages the project but does not own the Business Case.

  • Senior User

    Why it's wrong here

    The Senior User is not responsible for maintaining the Business Case because that accountability lies with the Executive, who owns the project's justification and ensures its ongoing viability. The Senior User’s role is to specify the required outcomes and benefits, making this option tempting if one confuses specifying benefits with owning the financial justification. The Senior User would be the correct choice only if the question asked who defines the expected benefits from the user’s perspective.

  • Team Manager

    Why it's wrong here

    Team Managers deliver work packages and do not own the Business Case.

  • Executive (SRO)

    Why this is correct

    The Executive is responsible for the Business Case throughout the project.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.