PRINCE2F People: organizations, teams, and leadership Practice Question
In PRINCE2, who is responsible for managing the delivery of a Work Package?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Manager
The Team Manager is responsible for the delivery of Work Packages and reports progress to the Project Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior User
Why it's wrong here
The Senior User specifies the requirements but does not manage Work Package delivery.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative services but does not manage Work Packages.
- ✗
Project Manager
Why it's wrong here
The Project Manager assigns Work Packages to Team Managers but does not manage the delivery directly.
- ✓
Team Manager
Why this is correct
The Team Manager is responsible for producing the products within the Work Package as agreed.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.