PRINCE2F People: organizations, teams, and leadership Practice Question
What is the purpose of the Change Authority role in PRINCE2?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To make decisions on change requests within agreed limits.
The Change Authority is an optional role that is delegated by the Project Board to make decisions on change requests within defined limits, to streamline the change control process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To manage the project's risk register.
Why it's wrong here
Risk register ownership belongs to the Project Manager, who maintains and updates it throughout the project. The Change Authority assesses and approves or rejects change requests, so it tempts when changes introduce risks, yet risk management is not its remit.
- ✗
To authorize the project budget.
Why it's wrong here
Budget authorisation sits with the Project Board, exercised through the business case and stage tolerances; the Change Authority only decides on change requests escalated to it. It tempts because change decisions often carry cost implications, but PRINCE2 separates financial authority from change authority.
- ✗
To audit the project's compliance with PRINCE2.
Why it's wrong here
Compliance auditing falls to project assurance roles, which monitor adherence to standards independently of change control. The Change Authority evaluates change requests against tolerances and business justification, so it tempts as a governance role, but auditing is not its purpose.
- ✓
To make decisions on change requests within agreed limits.
Why this is correct
The Change Authority exists precisely to decide change requests within tolerances delegated by the Project Board, satisfying the stem's requirement for a defined decision-making purpose. This preserves board-level control while enabling timely responses, since escalation only occurs when a request exceeds the agreed limits set for that authority.
Go deeper
Related to this question
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.