PRINCE2F People: organizations, teams, and leadership Practice Question

A team manager has completed a work package and is ready to hand over the deliverables. To whom should the team manager report the completion?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

The Team Manager reports to the Project Manager, who manages the work packages within a stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Manager

    Why this is correct

    The team manager reports work package completion directly to the Project Manager, who authorised the work package and owns progress tracking within the controlling a stage process. This satisfies PRINCE2's defined reporting line, since the Project Manager must update the stage plan and checkpoint against actual completion before authorising the next work package.

  • ✗

    Project Board

    Why it's wrong here

    The Project Board sets tolerances and approves stage boundaries, not individual work packages. Reporting completion to it is tempting because the board authorises the project, but PRINCE2 requires the team manager to notify the project manager, who accepts the deliverables and escalates only exceptions to the board.

  • ✗

    Senior Responsible Owner

    Why it's wrong here

    The Senior Responsible Owner owns the business case and chairs the project board; work package completion is never reported to them directly. This is tempting because the SRO is accountable for project success, but PRINCE2 routes completion through the project manager, who updates the board via checkpoint and highlight reports.

  • ✗

    Project Assurance

    Why it's wrong here

    Project Assurance monitors the project against its business, user and supplier interests; it does not receive work package completion notifications. Reporting to it is tempting because assurance checks that deliverables meet requirements, but the team manager reports completion to the project manager, who then accepts the work package on the board's behalf.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.