PRINCE2F People: organizations, teams, and leadership Practice Question
A team manager has completed a work package and is ready to hand over the deliverables. To whom should the team manager report the completion?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Team Manager reports to the Project Manager, who manages the work packages within a stage.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Manager
Why this is correct
The Team Manager reports completion to the Project Manager.
- ✗
Project Board
Why it's wrong here
The Project Board is not involved in day-to-day team management.
- ✗
Senior Responsible Owner
Why it's wrong here
The SRO does not receive direct reports from the Team Manager.
- ✗
Project Assurance
Why it's wrong here
Project Assurance is independent and does not manage work packages.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.