The Team Manager receives a Work Package and proceeds with the work. A product is found to be defective. What should the Team Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Record the defect and raise a Problem/Concern to the Project Manager

If a product is defective, the Team Manager should first record the issue as an Off-specification and then raise a Problem/Concern to the Project Manager for resolution.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Correct the defect and continue with the work package

    Why it's wrong here

    Correcting the defect unilaterally hides a deviation from the agreed specification, so the Project Manager must be informed via an Off-specification and the Work Package reassessed. It is tempting because fixing faults feels productive, but PRINCE2 requires the deviation be escalated before work continues under the original tolerances.

  • ✓

    Record the defect and raise a Problem/Concern to the Project Manager

    Why this is correct

    Defects fall outside the Work Package's tolerances, so the Team Manager cannot resolve them alone. Recording the defect and raising a Problem/Concern escalates it to the Project Manager, who decides whether to instruct a change or exception, satisfying PRINCE2's escalation requirement.

  • ✗

    Inform the Project Board directly

    Why it's wrong here

    The Project Board sits above the Project Manager, so a Team Manager escalates through the Project Manager, who raises an Off-specification and decides within tolerance. It is tempting because the Board owns the business case, but direct reporting bypasses the management level responsible for handling the issue.

  • ✗

    Ignore the defect and continue as planned

    Why it's wrong here

    Ignoring the defect breaches the Work Package's specification and conceals a deviation the Project Manager must assess against stage tolerances. It is tempting when the fault appears minor, but PRINCE2 requires every Off-specification to be reported and resolved, not silently absorbed into the product.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.