PRINCE2F People: organizations, teams, and leadership Practice Question
During a project, the Project Board is informed that a major change to the project scope is required. Which role is best placed to assess the impact on the Business Case?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Assurance
Project Assurance provides independent assessment of project issues, including impact on the Business Case, to the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Assurance
Why this is correct
Project Assurance independently assesses impacts on the Business Case and advises the Board.
- ✗
Senior User
Why it's wrong here
The Senior User focuses on user needs, not independent assessment.
- ✗
Team Manager
Why it's wrong here
Team Manager focuses on Work Package delivery, not strategic impacts.
- ✗
Project Manager
Why it's wrong here
The PM may provide information, but independent assessment is best done by Assurance.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.