Which TWO of the following statements about the Change Authority role in PRINCE2 are correct?

⚠ Common exam trap

PRINCE2 often tests the misconception that the Change Authority must be a single individual or that it cannot approve changes affecting the Business Case, but PRINCE2 explicitly allows group authority and within-tolerance Business Case impacts.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Change Authority is delegated by the Project Board to make decisions on change requests within agreed tolerances

The Change Authority role is explicitly delegated by the Project Board to make decisions on change requests within agreed tolerances. This delegation allows the Change Authority to approve or reject changes without requiring the Project Board to convene for every minor change, streamlining the change control process while keeping decisions within predefined limits.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Change Authority must be a single individual

    Why it's wrong here

    It can be a person or a group.

  • ✓

    The Change Authority is delegated by the Project Board to make decisions on change requests within agreed tolerances

    Why this is correct

    This is the purpose of the Change Authority.

  • ✓

    The Change Authority is an optional role

    Why this is correct

    PRINCE2 allows the Change Authority to be delegated from the Project Board.

  • ✗

    The Change Authority is responsible for updating the Project Plan

    Why it's wrong here

    Updating the Project Plan is the Project Manager's responsibility.

  • ✗

    The Change Authority cannot approve changes that affect the Business Case

    Why it's wrong here

    It can if the limits are set by the Project Board.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.