Who is responsible for providing independent assurance to the Project Board that the project is on track?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Assurance

Project Assurance provides independent oversight, reporting to the Project Board, and cannot be delegated to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Support

    Why it's wrong here

    Project Support provides administrative services.

  • Project Assurance

    Why this is correct

    Project Assurance is the correct role.

  • Project Manager

    Why it's wrong here

    The PM is not independent; they manage the project.

  • Team Manager

    Why it's wrong here

    Team Managers report to the PM.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.