Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

During the Managing a Stage Boundary process, the Project Manager prepares an Exception Plan. What is the trigger for this activity?

⚠ Common exam trap

Test-takers frequently confuse the trigger for an Exception Plan with the routine end-of-stage planning, forgetting that an Exception Plan is a corrective response to a forecast tolerance breach, not a normal planning activity.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

An Exception Report is raised because stage tolerances are forecast to be exceeded.

In PRINCE2, the trigger for preparing an Exception Plan during the Managing a Stage Boundary process is the raising of an Exception Report. This report is created when the Project Manager forecasts that stage tolerances will be exceeded, indicating that the current Stage Plan cannot be completed within its agreed tolerances. The Exception Plan then replaces the existing Stage Plan to bring the project back within tolerance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Project Board requests a new Stage Plan.

    Why it's wrong here

    The Project Board may request a new plan, but an Exception Plan is specifically for tolerance breaches.

  • The project is at the end of a stage.

    Why it's wrong here

    At the end of a stage, a normal Stage Plan is produced, not an Exception Plan.

  • The Team Manager reports a Work Package is complete.

    Why it's wrong here

    Completion of a Work Package is a routine event, not a trigger for an Exception Plan.

  • An Exception Report is raised because stage tolerances are forecast to be exceeded.

    Why this is correct

    The Exception Report triggers the need for an Exception Plan.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.