In PRINCE2, what is the main reason for separating the Project Manager role from the Project Assurance role?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To ensure independent monitoring and control of the project
Separation ensures independent and objective assurance that the project is running correctly, free from the biases or conflicts of day-to-day management.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To reduce the workload of the Project Manager
Why it's wrong here
While workload may be affected, the primary reason is independence.
- ✓
To ensure independent monitoring and control of the project
Why this is correct
Project Assurance provides an independent view to the Project Board, not influenced by the Project Manager.
- ✗
To allow the Project Manager to focus on technical tasks
Why it's wrong here
The Project Manager focuses on management, not technical tasks.
- ✗
To enable the Project Board to delegate more responsibilities
Why it's wrong here
The Board delegates to PM, but Assurance remains independent.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.