PRINCE2F People: organizations, teams, and leadership Practice Question
Which document is produced in the Initiating a Project process and defines how the project will be managed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Initiation Documentation
The Project Initiation Documentation (PID) is the key output of Initiating a Project and defines the project's approach, controls, and plans.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stage Plan
Why it's wrong here
Stage Plans are created during Managing a Stage Boundary.
- ✓
Project Initiation Documentation
Why this is correct
The PID is the output of Initiating a Project.
- ✗
Project Brief
Why it's wrong here
The Project Brief is created in Starting Up a Project.
- ✗
Business Case
Why it's wrong here
The Business Case is developed during Initiating a Project but is part of the PID.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.