Which role is responsible for ensuring that the project is being managed correctly from the business perspective?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Assurance
Project Assurance provides independent oversight to the Project Board, ensuring the project is managed correctly from business, user, and supplier perspectives. The Executive is accountable but Project Assurance performs the checks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Assurance
Why this is correct
Project Assurance is independent and assures the Project Board.
- ✗
Senior User
Why it's wrong here
The Senior User represents users, not assurance.
- ✗
Project Support
Why it's wrong here
Project Support is administrative.
- ✗
Project Manager
Why it's wrong here
The Project Manager manages the project but is not independent.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.