Courseiva
People: organizations, teams, and leadershiphardMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

Exhibit

Refer to the exhibit.

Project Organization:
- Executive: John Smith
- Senior User: Mary Johnson
- Senior Supplier: Tom Brown
- Project Manager: Sarah Lee
- Team Manager: David Wilson (for software development)
- Project Assurance: Peter Black
- Project Support: Emma White

During a team planning session, the software development team reports a potential delay to a key deliverable. The Team Manager, David Wilson, is unsure how to handle this and wants guidance. According to PRINCE2, who should David Wilson report this issue to?

Refer to the exhibit. According to PRINCE2, to whom should the Team Manager report the potential delay?

⚠ Common exam trap

It's easy for candidates to confuse the reporting lines within the project management team, mistakenly thinking a Team Manager should report directly to a Project Board member (Executive, Senior User, or Project Assurance) rather than to the Project Manager who coordinates all delivery-level communications.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Manager, Sarah Lee

In PRINCE2, the Team Manager is responsible for delivering the work package and reports to the Project Manager on progress, issues, and risks. The Project Manager (Sarah Lee) is the single point of contact for the Team Manager within the project management team. Therefore, any potential delay must be reported to the Project Manager, who will then escalate to the Project Board if necessary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Executive, John Smith

    Why it's wrong here

    Wrong: The Team Manager does not report directly to the Executive; that is the Project Manager's responsibility.

  • The Project Manager, Sarah Lee

    Why this is correct

    Correct: The Team Manager reports to the Project Manager.

  • The Project Assurance, Peter Black

    Why it's wrong here

    Wrong: Project Assurance provides independent oversight, not management direction.

  • The Senior User, Mary Johnson

    Why it's wrong here

    Wrong: The Senior User represents user interests but is not the direct line for team management issues.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.