PRINCE2F People: organizations, teams, and leadership Practice Question

Exhibit

Refer to the exhibit.

Project Organization:
- Executive: John Smith
- Senior User: Mary Johnson
- Senior Supplier: Tom Brown
- Project Manager: Sarah Lee
- Team Manager: David Wilson (for software development)
- Project Assurance: Peter Black
- Project Support: Emma White

During a team planning session, the software development team reports a potential delay to a key deliverable. The Team Manager, David Wilson, is unsure how to handle this and wants guidance. According to PRINCE2, who should David Wilson report this issue to?

Refer to the exhibit. According to PRINCE2, to whom should the Team Manager report the potential delay?

⚠ Common exam trap

It's easy for candidates to confuse the reporting lines within the project management team, mistakenly thinking a Team Manager should report directly to a Project Board member (Executive, Senior User, or Project Assurance) rather than to the Project Manager who coordinates all delivery-level communications.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Manager, Sarah Lee

In PRINCE2, the Team Manager is responsible for delivering the work package and reports to the Project Manager on progress, issues, and risks. The Project Manager (Sarah Lee) is the single point of contact for the Team Manager within the project management team. Therefore, any potential delay must be reported to the Project Manager, who will then escalate to the Project Board if necessary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Executive, John Smith

    Why it's wrong here

    The Executive owns the business case and sits above the Project Board, receiving only Highlight Reports via the Board; a Team Manager escalates delays to the Project Manager, who then informs the Board. Direct Executive reporting is reserved for project-level tolerance breaches, not team-level slippage.

  • ✓

    The Project Manager, Sarah Lee

    Why this is correct

    In PRINCE2, the Team Manager reports to the Project Manager, who owns day-to-day delivery within the project's tolerances. Escalating a potential delay to Sarah Lee therefore follows the defined line of authority rather than bypassing it.

  • ✗

    The Project Assurance, Peter Black

    Why it's wrong here

    Project Assurance independently monitors the project on the Board's behalf and has no line authority over Team Managers; it advises rather than receives escalations. A Team Manager raises exceptions with the Project Manager. Assurance is the right channel when the Board needs independent verification of the Project Manager's reporting.

  • ✗

    The Senior User, Mary Johnson

    Why it's wrong here

    The Senior User represents user interests on the Project Board and receives progress through Board reporting, not direct Team Manager escalation. A Team Manager reports exceptions to the Project Manager, who decides whether Board-level tolerance is threatened. Senior User involvement suits benefits and acceptance issues, not team schedule slippage.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.