PRINCE2F People: organizations, teams, and leadership Practice Question

According to PRINCE2, who is responsible for authorizing the work packages to be executed by the team?

⚠ Common exam trap

Candidates often confuse the Project Board's high-level authority with the Project Manager's delegated authority for operational work package authorization, leading them to incorrectly select the Project Board.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

In PRINCE2, the Project Manager is responsible for authorizing work packages to be executed by the team. This is because the Project Manager manages the day-to-day activities and has the authority to assign work to team members or Team Managers, ensuring that the work packages align with the project plan and stage tolerances. The Project Board provides overall direction and approves stage plans, but the authorization of individual work packages is delegated to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Board

    Why it's wrong here

    The Project Board provides overall direction and approves stage boundaries, not individual work packages. It is tempting because the Board authorises the project and each stage, but PRINCE2 delegates work-package authorisation to the Project Manager, who issues them to the Team Manager.

  • ✗

    Senior Responsible Owner

    Why it's wrong here

    The Senior Responsible Owner is a governance role outside PRINCE2's defined organisation; work packages are authorised by the Managing level, not this individual. It is tempting because the SRO owns overall project accountability in many governance frameworks, but PRINCE2 assigns work-package authorisation to the Project Manager.

  • ✓

    Project Manager

    Why this is correct

    In PRINCE2 the Project Manager controls the Work Package interface, agreeing tolerances with the Team Manager and authorising work to begin. The Project Board authorises the stage or project, not individual work packages, so this responsibility sits with the Project Manager.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager receives and executes authorised work packages, then reports progress; authorisation itself sits with the Managing level. It is tempting because the Team Manager controls day-to-day team work and agrees checkpoints, but PRINCE2 places work-package authorisation with the Project Manager.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.