Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

According to PRINCE2, who is responsible for authorizing the work packages to be executed by the team?

⚠ Common exam trap

Candidates often confuse the Project Board's high-level authority with the Project Manager's delegated authority for operational work package authorization, leading them to incorrectly select the Project Board.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

In PRINCE2, the Project Manager is responsible for authorizing work packages to be executed by the team. This is because the Project Manager manages the day-to-day activities and has the authority to assign work to team members or Team Managers, ensuring that the work packages align with the project plan and stage tolerances. The Project Board provides overall direction and approves stage plans, but the authorization of individual work packages is delegated to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Board

    Why it's wrong here

    The Project Board authorizes stages, not work packages.

  • Senior Responsible Owner

    Why it's wrong here

    The SRO does not authorize work packages.

  • Project Manager

    Why this is correct

    The Project Manager authorizes work packages.

  • Team Manager

    Why it's wrong here

    The Team Manager receives and executes work packages.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.