During which process is the Project Initiation Documentation (PID) created?

⚠ Common exam trap

It's easy for candidates to confuse the creation of the PID with its approval or subsequent updates; candidates often select Starting Up a Project because they think the PID is created early, but PRINCE2 clearly separates the initial Project Brief from the detailed PID developed in Initiating a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiating a Project

The Project Initiation Documentation (PID) is created during the Initiating a Project process. This process takes the initial project mandate and outline business case from Starting Up a Project and develops them into a comprehensive, baselined set of documents that define the project's scope, objectives, risks, and controls. The PID is formally approved by the Project Board during this process, providing the authority to proceed with the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why it's wrong here

    SU produces the Project Brief, not the PID.

  • Initiating a Project

    Why this is correct

    The PID is the key output of the Initiating a Project process.

  • Managing a Stage Boundary

    Why it's wrong here

    MSB updates the PID but does not create it.

  • Directing a Project

    Why it's wrong here

    DP is the process for the Project Board's decision-making; it does not create the PID.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which document is produced in the Initiating a Project process and defines how the project will be managed?

medium
  • A.Stage Plan
  • B.Project Initiation Documentation
  • C.Project Brief
  • D.Business Case

Why B: The Project Initiation Documentation (PID) is the key output of Initiating a Project and defines the project's approach, controls, and plans.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.