Courseiva
People: organizations, teams, and leadershiphardMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

The Project Board consists of three roles. Which of the following is NOT a mandatory role on the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The mandatory roles are Senior User, Senior Supplier, and Senior Responsible Owner. The Project Manager is not a member of the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Responsible Owner (Executive)

    Why it's wrong here

    This is a mandatory role.

  • Project Manager

    Why this is correct

    The Project Manager attends Project Board meetings but is not a member.

  • Senior Supplier

    Why it's wrong here

    This is a mandatory role.

  • Senior User

    Why it's wrong here

    This is a mandatory role.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.