The Project Board consists of three roles. Which of the following is NOT a mandatory role on the Project Board?
⚠ Common exam trap
PRINCE2F often tests the distinction between the Project Board (directing) and the Project Manager (managing), and candidates may incorrectly assume the Project Manager is a board member due to their central role.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The PRINCE2 Project Board is composed of three mandatory roles: the Executive (Senior Responsible Owner), the Senior Supplier, and the Senior User. The Project Manager is not a member of the Project Board; instead, the Project Manager reports to the Project Board and manages the project on a day-to-day basis. Therefore, the Project Manager is NOT a mandatory role on the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior Responsible Owner (Executive)
Why it's wrong here
The Executive is a mandatory Project Board role, so it cannot be the exception. Senior Responsible Owner is tempting because it is a genuine governance accountability, but in PRINCE2 it maps onto the Executive rather than being an optional fourth role.
- ✓
Project Manager
Why this is correct
The Project Board comprises Business Sponsor, Senior User and Senior Supplier, all mandatory. The Project Manager manages the project on the Board's behalf and may attend, but is not a Board member, so this role is not mandatory on the Project Board.
- ✗
Senior Supplier
Why it's wrong here
Senior Supplier is a mandatory Project Board role in PRINCE2, representing those who provide resources. The question asks which is not mandatory; all three roles—Executive, Senior User, and Senior Supplier—are required. It is tempting to think suppliers are optional, but PRINCE2 mandates this role.
- ✗
Senior User
Why it's wrong here
Senior User is one of the three mandatory Project Board roles, alongside Executive and Senior Supplier, so it cannot be the answer. The question asks which role is not mandatory; the Project Board requires all three. It is tempting because Senior User represents user interests, but PRINCE2 mandates it.
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.