PRINCE2F People: organizations, teams, and leadership Practice Question
The Project Board consists of three roles. Which of the following is NOT a mandatory role on the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The mandatory roles are Senior User, Senior Supplier, and Senior Responsible Owner. The Project Manager is not a member of the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior Responsible Owner (Executive)
Why it's wrong here
This is a mandatory role.
- ✓
Project Manager
Why this is correct
The Project Manager attends Project Board meetings but is not a member.
- ✗
Senior Supplier
Why it's wrong here
This is a mandatory role.
- ✗
Senior User
Why it's wrong here
This is a mandatory role.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.