PRINCE2F People: organizations, teams, and leadership Practice Question
What is the minimum frequency of Project Board meetings?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
At each stage boundary and when an exception occurs
The Project Board meets at predetermined points (stage boundaries) and when an exception is raised. They are exception-driven, so there is no fixed minimum frequency.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Monthly
Why it's wrong here
Monthly is not prescribed.
- ✓
At each stage boundary and when an exception occurs
Why this is correct
The Project Board meets at key decision points and when exceptions arise.
- ✗
Only at the start and end of the project
Why it's wrong here
They also meet during stage boundaries and for exceptions.
- ✗
Weekly
Why it's wrong here
PRINCE2 does not require weekly meetings.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.