In PRINCE2, who is responsible for day-to-day management of the project within tolerances?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The Project Manager manages the project on a day-to-day basis within the tolerances set by the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team Manager

    Why it's wrong here

    The Team Manager manages a team within a work package, not the whole project.

  • Project Manager

    Why this is correct

    The PM has delegated authority for day-to-day management.

  • Project Support

    Why it's wrong here

    Project Support provides administrative assistance.

  • Senior Responsible Owner

    Why it's wrong here

    The SRO is accountable for the project, not day-to-day management.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which role is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

easy
  • A.Project Assurance
  • B.Team Manager
  • C.Project Manager
  • D.Senior Responsible Owner (SRO/Executive)

Why C: The Project Manager manages the project on a day-to-day basis within the tolerances delegated by the Project Board.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.