PRINCE2F People: organizations, teams, and leadership Practice Question
Which TWO of the following are responsibilities of the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Managing the stage boundary activities
The Project Manager is responsible for day-to-day management, including preparing Highlight Reports for the Project Board and managing stage boundaries. Project Assurance is independent, and the Project Board defines tolerances.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Managing the stage boundary activities
Why this is correct
The PM manages the stage boundary process, including preparing the next Stage Plan.
- ✗
Performing Project Assurance
Why it's wrong here
Project Assurance must be independent of the PM.
- ✓
Preparing Highlight Reports for the Project Board
Why this is correct
The PM prepares and sends Highlight Reports to the Board.
- ✗
Approving stage plans
Why it's wrong here
Stage plans are approved by the Project Board.
- ✗
Defining project tolerances
Why it's wrong here
Tolerances are set by the Project Board, not the PM.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.