Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Which TWO of the following are responsibilities of the Project Manager?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Managing the stage boundary activities

The Project Manager is responsible for day-to-day management, including preparing Highlight Reports for the Project Board and managing stage boundaries. Project Assurance is independent, and the Project Board defines tolerances.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Managing the stage boundary activities

    Why this is correct

    The Project Manager manages stage boundary activities, ensuring the End Stage Assessment is planned and the next stage is prepared. This responsibility sits with the Project Manager under PRINCE2, distinct from the Project Board's authorisation role.

  • ✗

    Performing Project Assurance

    Why it's wrong here

    Project Assurance is performed independently of the Project Manager, reporting to the Project Board to give it confidence. It tempts because assurance activities resemble the monitoring and controlling the Project Manager does daily, but independence is the point, so the role cannot sit with the manager being assured.

  • ✓

    Preparing Highlight Reports for the Project Board

    Why this is correct

    Preparing Highlight Reports is a Project Manager responsibility, satisfying the stem's requirement for progress reporting to the Project Board. The Project Manager collates work package status, tolerance exceptions and forecast data into the Highlight Report, escalating only agreed exception situations. This contrasts with the Project Board, which receives rather than authors the report.

  • ✗

    Approving stage plans

    Why it's wrong here

    Stage plans are approved by the Project Board, which authorises each stage; the Project Manager authors and updates them. It tempts because the Project Manager clearly produces stage plans, so approval appears a natural extension, yet approval is a Board decision under PRINCE2's organisation theme.

  • ✗

    Defining project tolerances

    Why it's wrong here

    Tolerances are set by the Project Board, which owns the project within the boundaries it defines; the Project Manager only works within them. It tempts because the Project Manager does propose tolerances for approval, so the activity feels familiar, but authority to define them stays with the Board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.