Courseiva

CCNA Prince2 Practices Questions

75 of 596 questions · Page 5/8 · Prince2 Practices topic · Answers revealed

301
MCQmedium

Which of the following is NOT a component of the Business Case?

A.Expected benefits
B.Major risks
C.Product description
D.Investment appraisal
AnswerC

A product description is part of quality and plans, not the Business Case.

Why this answer

The Business Case components include reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. A product description is part of product-based planning, not the Business Case.

302
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Project Board
D.Senior Supplier
AnswerB

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 assigns day-to-day management of the Business Case to the Project Manager, who must ensure it remains viable and aligned with the project's progress. The Project Manager updates the Business Case with actual costs, benefits, and risks, and presents it to the Project Board for approval at key decision points. This is defined in PRINCE2's Business Case management approach, where the Project Manager acts as the custodian of the document.

Exam trap

A common misconception is that the Project Board maintains the Business Case because it is a key governance document, but PRINCE2 clearly assigns the maintenance role to the Project Manager, with the Board only approving it.

How to eliminate wrong answers

Option A is wrong because the Senior User represents the users' interests and specifies the benefits, but does not maintain the Business Case; their role is to ensure the project delivers the required outcomes. Option C is wrong because the Project Board is responsible for approving the Business Case and making key decisions, not for its daily maintenance; they rely on the Project Manager to provide updates. Option D is wrong because the Senior Supplier provides resources and expertise, but maintaining the Business Case is not their responsibility; they focus on the technical feasibility and supplier obligations.

303
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
B.Close the project immediately as the Business Case is no longer viable
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation. Option A is wrong because the PM cannot increase the budget without Project Board approval.

Option B is wrong because closing the project is not the appropriate response to a stage tolerance breach; the Project Board may decide to close if the Business Case is no longer viable. Option C is wrong because continuing without escalation violates management by exception.

304
MCQeasy

Which of the following is NOT a component of the Business Case?

A.Investment appraisal
B.Risk Register
C.Major risks
D.Expected benefits
AnswerB

The Risk Register is a separate management product.

Why this answer

The Business Case includes reasons, options, benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. The Risk Register is separate.

305
MCQeasy

What is the purpose of the Highlight Report?

A.To detail the work packages for the next stage
B.To provide the Project Board with a summary of stage progress
C.To report issues to the Project Board
D.To report team progress to the Project Manager
AnswerB

This is the main purpose of the Highlight Report.

Why this answer

The Highlight Report is produced by the Project Manager and sent to the Project Board at regular intervals to provide a summary of progress during a stage.

306
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Investment appraisal
B.Configuration Item Records
C.Product Description
D.Risk Register
E.Expected benefits
AnswersA, E

Investment appraisal is a key component, showing the justification for the project.

Why this answer

The Business Case in PRINCE2 is the key document that justifies the project's initiation and continued viability. It must include an investment appraisal to evaluate the financial viability of the project, and it must define the expected benefits that the project aims to deliver. These two components are essential for decision-making and are explicitly required by the PRINCE2 methodology.

Exam trap

PeopleCert often tests the distinction between the Business Case components and other management products; the trap here is confusing the Risk Register or Product Descriptions as part of the Business Case, when they are separate documents with distinct purposes in PRINCE2.

307
Multi-Selectmedium

Which THREE of the following are components of the Business Case?

Select 3 answers
A.Major risks
B.Expected benefits
C.Project approach
D.Investment appraisal
E.Benefits review plan
AnswersA, B, D

Major risks are included.

Why this answer

'Major risks' are a formal component of the PRINCE2 Business Case. The Business Case must document the key risks that could affect the project's viability, ensuring that decision-makers understand the uncertainties before committing resources.

Exam trap

Candidates often confuse the Benefits Review Plan (a separate management product) with the Business Case's expected benefits component, or mistake the Project Approach for a Business Case element when it belongs to the Project Plan.

308
MCQeasy

According to PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior Supplier
C.Senior User
D.Project Board
AnswerA

Correct. The Project Manager maintains the Business Case.

Why this answer

In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains a living document that reflects the current justification for the project.

Exam trap

The trap here is that candidates often assume the Project Board, as the ultimate decision-making body, is responsible for maintaining the Business Case, but PRINCE2 explicitly assigns this maintenance role to the Project Manager.

How to eliminate wrong answers

Option B is wrong because the Senior Supplier is responsible for providing the necessary resources and expertise, not for maintaining the Business Case. Option C is wrong because the Senior User represents the users' interests and specifies the benefits, but does not maintain the Business Case document. Option D is wrong because the Project Board is responsible for approving the Business Case and making key decisions, but the day-to-day maintenance and monitoring of the Business Case is delegated to the Project Manager.

309
MCQmedium

During a project, a team manager reports that a work package is taking longer than expected. The project manager needs to assess the impact on the project schedule. Which practice should be used to evaluate the effect and determine whether to escalate?

A.Risk
B.Plans
C.Organizing
D.Progress
AnswerD

Progress practice covers monitoring, control, and escalations.

Why this answer

The Progress practice is used to monitor and compare actual achievements against planned performance, and to assess the impact of deviations. When a work package takes longer than expected, the project manager uses Progress to evaluate the effect on the schedule and decide whether to escalate to the project board. This aligns with PRINCE2's principle of managing by stages and using tolerances to control deviations.

Exam trap

PeopleCert often tests the distinction between 'Risk' (managing future uncertainties) and 'Progress' (monitoring actual performance against baselines), leading candidates to incorrectly select Risk when a delay is already occurring.

How to eliminate wrong answers

Option A is wrong because Risk practice focuses on identifying, assessing, and controlling uncertainties that could affect the project, not on evaluating schedule impact from a known delay. Option B is wrong because Plans practice is about defining how, when, and by whom the products are delivered, not about monitoring actual progress or assessing deviations. Option C is wrong because Organizing practice defines roles and responsibilities, not the mechanism for evaluating schedule impact or escalation decisions.

310
MCQeasy

What is the purpose of the Highlight Report?

A.To escalate exceptions
B.To report progress to the Project Board at regular intervals
C.To request changes
D.To report progress to the Team Manager
AnswerB

Correct.

Why this answer

The Highlight Report is produced by the Project Manager for the Project Board at regular intervals to summarize progress and issues.

311
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Project Initiation Documentation
B.The Business Case
C.The Risk Register
D.The Project Plan
AnswerA

The PID is the key output of Initiating a Project.

Why this answer

The Initiating a Project process is where the project's foundations are established, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—including the Business Case, Project Plan, and Risk Register—into a single, coherent document that defines what the project will deliver, why, how, and against what constraints. It serves as the baseline for decision-making and is formally approved before the project proceeds to the next stage.

Exam trap

PeopleCert often tests the distinction between the PID as the overarching output and its individual components (like the Business Case or Project Plan) to see if candidates understand that the PID is the consolidated deliverable, not any single part of it.

How to eliminate wrong answers

Option B is wrong because the Business Case is a component of the Project Initiation Documentation, not the key output of the Initiating a Project process; it is developed and refined during the Starting Up a Project process and updated in Initiating a Project. Option C is wrong because the Risk Register is a management product that is created and maintained throughout the project, but it is not the primary output of Initiating a Project; it is one of many components that feed into the PID. Option D is wrong because the Project Plan is also a component of the PID, not the key output itself; it is produced during the Initiating a Project process but is only one part of the comprehensive PID.

312
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
B.Close the project immediately as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerC

When a stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report. This is management by exception.

Why this answer

According to the management by exception principle, when a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The Project Manager cannot unilaterally increase the budget or ignore the breach.

313
MCQhard

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are synonyms in PRINCE2
B.An Off-specification is always raised by the Project Manager; an RFC is raised by the Project Board
C.An RFC only applies to project products; an Off-specification applies to the Business Case
D.An RFC is a proposal to change a baseline; an Off-specification is a failure to meet a baseline requirement
AnswerD

Correct. RFC proposes a change; Off-specification is a deviation from what was specified.

Why this answer

A Request for Change (RFC) is a formal proposal to modify a baseline (e.g., a product, plan, or scope), while an Off-specification is a documented deviation where a product or component fails to meet its agreed specification or baseline requirement. In PRINCE2, an RFC seeks approval for a change, whereas an Off-specification identifies a non-compliance that must be resolved, often through a change request or concession.

Exam trap

The trap here is that candidates confuse the purpose of an RFC (proactive change proposal) with an Off-specification (reactive non-compliance detection), leading them to incorrectly treat them as synonyms or misattribute who raises them.

How to eliminate wrong answers

Option A is wrong because RFC and Off-specification are distinct concepts in PRINCE2; an RFC proposes a change to a baseline, while an Off-specification identifies a failure to meet a baseline requirement. Option B is wrong because both RFCs and Off-specifications can be raised by any project role (e.g., team members, Project Manager, or Project Board), not exclusively by the Project Manager or Project Board. Option C is wrong because an RFC can apply to any baseline (including the Business Case, plans, or products), and an Off-specification applies to any product or component that fails to meet its specification, not just the Business Case.

314
MCQeasy

Which role is responsible for ensuring that project assurance is carried out independently of the Project Manager?

A.Project Manager
B.Project Board
C.Team Manager
D.Project Support
AnswerB

Correct. The Project Board is accountable for project assurance and ensures it is independent.

Why this answer

The Project Board members (Executive, Senior User, Senior Supplier) are responsible for project assurance. They delegate assurance tasks but remain accountable. The Project Manager does not perform assurance; that would compromise independence.

315
MCQmedium

A project is experiencing many changes due to evolving requirements. Which document should the Project Manager use to track all requests for change?

A.Risk Register
B.Configuration Item Record
C.Issue Register
D.Quality Register
AnswerC

All issues, including requests for change, are logged in the Issue Register.

Why this answer

The Issue Register is the PRINCE2 document specifically designed to capture, track, and manage all requests for change, including off-specifications, problems, and concerns. Since the project is experiencing many changes due to evolving requirements, the Project Manager must log each change request in the Issue Register to ensure proper impact analysis, decision-making, and audit trail. This aligns with the PRINCE2 practice of managing issues and changes through a controlled process.

Exam trap

The trap here is that candidates often confuse the Issue Register with the Risk Register, mistakenly thinking that a change request is a risk to be mitigated, rather than a formal issue that must be logged and managed through the change control procedure.

How to eliminate wrong answers

Option A is wrong because the Risk Register is used to record identified risks (threats and opportunities), not requests for change; changes are handled through the issue management process. Option B is wrong because a Configuration Item Record tracks the status and version of a specific product or component, not the lifecycle of a change request. Option D is wrong because the Quality Register logs quality activities such as inspections and audits, not change requests.

316
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; they are the same
B.Off-specification is raised by the Project Board; Request for Change by users
C.A Request for Change is always budgeted; Off-specification is not
D.A Request for Change proposes a modification; Off-specification identifies something that is missing or not working
AnswerD

Correct distinction per PRINCE2.

Why this answer

A Request for Change is a proposal for a modification, while an Off-specification is something that should have been provided but is missing or not working.

317
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Increase the project budget and continue
C.Close the project immediately
D.Raise an Exception Report to the Project Board
AnswerD

An Exception Report is raised to the Project Board to decide on corrective action.

Why this answer

Management by exception requires escalation via an Exception Report to the Project Board when a tolerance is forecast to be exceeded.

318
MCQmedium

A project is in the Initiating a Project process. The project manager is reviewing the Business Case and notes that the expected benefits are not clearly linked to the project's objectives. Which practice should the project manager use to address this issue?

A.Quality practice
B.Risk practice
C.Business Case practice
D.Plans practice
AnswerC

The Business Case practice ensures the project remains viable and benefits are defined and linked to objectives.

Why this answer

The Business Case practice is responsible for establishing and maintaining the justification for the project, including the link between objectives and expected benefits. During the Initiating a Project process, the Business Case must be refined to ensure that all benefits are clearly traceable to the project's objectives, as this alignment is critical for ongoing viability decisions. The project manager should use the Business Case practice to address this gap by updating the Business Case to explicitly map each benefit to a specific project objective.

Exam trap

PeopleCert often tests the distinction between the Business Case practice (which owns the justification and benefit-objective linkage) and the Plans practice (which owns the schedule and activities), leading candidates to incorrectly choose Plans when the issue is about benefit alignment rather than sequencing.

How to eliminate wrong answers

Option A is wrong because the Quality practice focuses on defining and verifying the quality criteria of products, not on linking benefits to objectives. Option B is wrong because the Risk practice deals with identifying, assessing, and controlling uncertainties that could affect the project, not with ensuring benefit-objective alignment. Option D is wrong because the Plans practice is concerned with defining the sequence of activities, resources, and schedules to deliver the project's products, not with the justification or benefit mapping in the Business Case.

319
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Senior User
B.The Project Assurance
C.The Project Manager
D.The Senior Supplier
AnswerC

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Executive (Senior Responsible Owner) is the owner of the Business Case. The Project Manager maintains (updates) the Business Case on behalf of the Executive.

320
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To plan the next stage and update the Project Plan and Business Case
B.To produce the Project Initiation Documentation
C.To manage the work of the current stage
D.To close the project
AnswerA

Correct. Managing a Stage Boundary produces the next stage plan and updates the PID.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and update the Project Plan and Business Case with any new information. This ensures that the project remains viable and aligned with business objectives before committing to the next stage.

Exam trap

The trap here is that candidates often confuse the Managing a Stage Boundary process with the Controlling a Stage process, because both involve stage-level activities, but Managing a Stage Boundary is specifically about planning the next stage and updating key documents, not managing current work.

How to eliminate wrong answers

Option B is wrong because producing the Project Initiation Documentation is the purpose of the Initiating a Project process, not the Managing a Stage Boundary process. Option C is wrong because managing the work of the current stage is the purpose of the Controlling a Stage process, which handles day-to-day work and issue management. Option D is wrong because closing the project is the purpose of the Closing a Project process, which ensures the project is formally completed and benefits are measured.

321
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To initiate the project and create the Project Plan
B.To plan the next stage in detail and obtain Project Board approval for the next stage
C.To manage the work of the current stage and report progress
D.To close the project and produce the End Project Report
AnswerB

This is the primary purpose of Managing a Stage Boundary.

Why this answer

The purpose of Managing a Stage Boundary is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification.

322
MCQeasy

Which management product defines the quality criteria and acceptance methods for a product?

A.The Business Case
B.The Project Plan
C.The Quality Register
D.The Product Description
AnswerD

The Product Description defines quality criteria and acceptance methods.

Why this answer

The Product Description is the PRINCE2 management product that defines the quality criteria, quality methods, and acceptance methods for a specific product. It is created during the Initiating a Project process and is used to ensure that the product meets its required quality standards before it is approved.

Exam trap

The trap here is that candidates often confuse the Quality Register (which tracks quality activities) with the Product Description (which defines the quality criteria and methods), leading them to select Option C instead of D.

How to eliminate wrong answers

Option A is wrong because the Business Case provides justification for the project, including costs, benefits, and risks, but does not define quality criteria or acceptance methods for individual products. Option B is wrong because the Project Plan defines the schedule, resources, and costs for the project, not the quality criteria or acceptance methods for a specific product. Option C is wrong because the Quality Register is a log used to record and track all quality activities and results, but it does not define the quality criteria or acceptance methods themselves.

323
MCQmedium

Which document describes the quality criteria and quality methods to be applied during the project?

A.Quality Register
B.Product Description
C.Project Plan
D.Quality Management Approach
AnswerD

The Quality Management Approach defines the quality procedures, criteria, and methods for the project.

Why this answer

The Quality Management Approach defines the quality management system, including quality criteria and methods. The Product Description defines quality for a specific product. The Quality Register logs quality activities.

The Project Plan includes schedules.

324
MCQeasy

Which document is used to capture and track all identified risks throughout the project?

A.Quality Register
B.Risk Register
C.Configuration Item Record
D.Issue Register
AnswerB

The Risk Register captures and tracks all risks.

Why this answer

The Risk Register is the document used to record and track risks.

325
MCQeasy

Which risk response is appropriate for a threat that the project team decides to eliminate by changing the project approach?

A.Transfer
B.Accept
C.Reduce
D.Avoid
AnswerD

Avoid eliminates the threat by changing the plan.

Why this answer

Avoid is the response where action is taken to eliminate the threat by changing the plan or approach.

326
MCQmedium

During which process are team plans typically created?

A.Managing a Stage Boundary
B.Initiating a Project
C.Directing a Project
D.Managing Product Delivery
AnswerD

Correct. Team plans are created by the team manager in MP.

Why this answer

Team plans are created by the team manager during the Managing Product Delivery process.

327
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To enable the Project Board to review the current stage and authorize the next
C.To control the work of the current stage
D.To plan the entire project
AnswerB

Correct. The process provides the basis for stage boundary decisions.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve its completion, and authorize the next stage plan. This ensures that the project remains viable and aligned with business justification before committing further resources.

Exam trap

The trap here is confusing the Managing a Stage Boundary process with the Controlling a Stage process, as both involve stage-level activities, but only Managing a Stage Boundary handles the formal end-of-stage review and authorization of the next stage.

How to eliminate wrong answers

Option A is wrong because closing the project is the purpose of the Closing a Project process, not Managing a Stage Boundary. Option C is wrong because controlling the work of the current stage is the purpose of the Controlling a Stage process, which handles day-to-day management and issue resolution. Option D is wrong because planning the entire project is done during the Initiating a Project process, which creates the Project Plan; Managing a Stage Boundary only produces Stage Plans for the next stage.

328
MCQmedium

In PRINCE2, what is the definition of quality?

A.Customer satisfaction
B.Fit for purpose
C.Conformance to specification
D.Zero defects
AnswerB

This is the correct PRINCE2 definition.

Why this answer

In PRINCE2, quality is defined as 'fit for purpose,' meaning the product meets the stated requirements and is suitable for its intended use. This definition aligns with the PRINCE2 principle of continued business justification, ensuring the product delivers value to the stakeholders. It is not merely about conformance to specification or zero defects, but about satisfying the user's needs in the operational environment.

Exam trap

The trap here is that candidates often confuse 'conformance to specification' (a traditional manufacturing view) with PRINCE2's broader 'fit for purpose' definition, which includes the requirement that the specification itself must be appropriate for the user's needs and the business case.

How to eliminate wrong answers

Option A is wrong because 'customer satisfaction' is a broader outcome of quality but not the PRINCE2 definition; PRINCE2 focuses on the product's fitness for its stated purpose, not just subjective satisfaction. Option C is wrong because 'conformance to specification' is a narrower, manufacturing-focused view that ignores whether the specification itself is correct for the user's needs; PRINCE2 emphasizes that the product must be suitable for its intended use, which may require adapting specifications. Option D is wrong because 'zero defects' is an idealistic goal from total quality management, not PRINCE2's definition; PRINCE2 accepts that some defects may be tolerable if the product remains fit for purpose, and it manages quality through tolerances and acceptance criteria.

329
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Support
C.Project Manager
D.Executive (Senior Responsible Owner)
AnswerC

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

According to PRINCE2, the Project Manager is responsible for maintaining the Business Case, while the Executive (Senior Responsible Owner) owns it and is accountable for its justification.

330
MCQmedium

What document is a key output of the Initiating a Project process?

A.Project Brief
B.Project Plan
C.Business Case
D.Project Initiation Documentation
AnswerD

The PID is the main output of Initiating a Project, containing the Business Case, Project Plan, and other baselines.

Why this answer

The Project Initiation Documentation (PID) is the definitive output of the Initiating a Project process. It consolidates the Project Brief, Business Case, and Project Plan into a single, controlled document that defines the project's scope, objectives, and governance. PRINCE2 mandates that the PID is created and approved during this process to provide a firm foundation for the project.

Exam trap

PRINCE2 often tests the distinction between inputs and outputs of processes; the trap here is confusing the Project Brief (an input) or the Business Case (a component) with the PID, which is the comprehensive output that bundles them together.

How to eliminate wrong answers

Option A is wrong because the Project Brief is created during the Starting Up a Project process, not the Initiating a Project process; it serves as input to the latter. Option B is wrong because the Project Plan is a component within the PID, but the PID itself is the key output, not the plan alone. Option C is wrong because the Business Case is also a component of the PID; while it may be refined during Initiating a Project, the PID is the overarching deliverable.

331
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Initiation Documentation
C.Project Plan
D.Stage Plan
AnswerB

The PID is the comprehensive set of documents that form the project baseline.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, containing the business case, project plan, and other baselines.

332
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is a proposal to modify a baseline; an Off-specification is a failure to meet the baseline
B.A Request for Change is raised by the Project Manager; an Off-specification is raised by the team
C.A Request for Change is always urgent; an Off-specification is not
D.There is no difference; they are the same thing
AnswerA

This is the correct distinction.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify a product baseline (e.g., a specification or plan), while an Off-specification is a notification that a product has failed to meet its agreed baseline (e.g., a defect or missing requirement). Option A correctly captures this fundamental distinction: RFCs propose changes to baselines, whereas Off-specifications report deviations from baselines.

Exam trap

In PRINCE2, candidates often confuse the roles responsible for raising issues (Option B) or assume urgency (Option C), but PRINCE2 explicitly defines RFCs and Off-specifications by their relationship to baselines, not by who raises them or their urgency.

How to eliminate wrong answers

Option B is wrong because both RFCs and Off-specifications can be raised by any project role (e.g., Project Manager, team members, or stakeholders), not exclusively by the Project Manager or team. Option C is wrong because neither RFCs nor Off-specifications are inherently urgent; urgency is determined by impact analysis, not by the type of issue. Option D is wrong because RFCs and Off-specifications are distinct concepts with different purposes and triggers in PRINCE2's change control process.

333
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is submitted by the Project Board, whereas an Off-specification is submitted by the Project Manager
B.A Request for Change is a type of risk, whereas an Off-specification is a type of issue
C.A Request for Change requires a change budget, whereas an Off-specification does not
D.A Request for Change proposes a modification to an approved baseline, whereas an Off-specification occurs when a product does not meet its specification
AnswerD

This correctly distinguishes the two issue types.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify an approved baseline (e.g., a product description or project plan), while an Off-specification (Off-spec) is an issue that arises when a product does not meet its agreed specification or quality criteria. The RFC seeks to change the baseline, whereas the Off-spec identifies a deviation from the existing baseline. This distinction is fundamental to PRINCE2's issue management and change control processes.

Exam trap

The trap here is confusing the source or budget implications of issues; candidates often assume RFCs always need a change budget or that Off-specs are only raised by the Project Manager, but PRINCE2 defines them strictly by their relationship to baselines and specifications.

How to eliminate wrong answers

Option A is wrong because both a Request for Change and an Off-specification can be submitted by any stakeholder, not exclusively by the Project Board or Project Manager; the Project Manager typically logs all issues, but the source can be anyone. Option B is wrong because a Request for Change is a type of issue (not a risk), and an Off-specification is also a type of issue; PRINCE2 classifies issues into three types: Request for Change, Off-specification, and Problem/Concern. Option C is wrong because both a Request for Change and an Off-specification may require a change budget if the resolution involves additional cost; the need for a change budget depends on the impact and the stage, not on the issue type itself.

334
MCQmedium

Who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Project Manager
C.Project Board
D.Team Manager
AnswerC

The Project Board is responsible for project assurance, ensuring the project is conducted properly.

Why this answer

In PRINCE2, the Project Board is responsible for providing assurance that the project is being conducted properly. This includes ensuring that the project remains viable, that risks are managed, and that the business case is still valid. The Project Board delegates day-to-day management to the Project Manager but retains overall accountability and oversight through assurance activities.

Exam trap

PRINCE2 often tests the distinction between the Project Manager's role (managing the project) and the Project Board's role (providing assurance and making key decisions), leading candidates to mistakenly select the Project Manager as the assurance provider.

How to eliminate wrong answers

Option A is wrong because Project Support provides administrative and clerical services, such as maintaining files and producing reports, but does not have the authority to provide independent assurance. Option B is wrong because the Project Manager is responsible for the day-to-day management of the project and is the recipient of assurance, not the provider; they cannot assure their own work. Option D is wrong because the Team Manager is responsible for delivering the work within a work package and reports to the Project Manager, not for providing assurance on the project as a whole.

335
MCQeasy

In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.The Project Manager
B.The Project Support
C.The Executive
D.The Senior User
AnswerA

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Project Manager maintains the Business Case, but the Executive (SRO) owns it and is ultimately responsible for ensuring business justification.

336
MCQeasy

What is the definition of quality in PRINCE2?

A.Fit for purpose
B.Zero defects
C.Customer satisfaction
D.Conformance to specification
AnswerA

Correct.

Why this answer

PRINCE2 defines quality as 'fit for purpose' — meaning the product meets its stated requirements and satisfies customer needs.

337
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change can only be raised by the Project Board, while an Off-specification can be raised by anyone.
B.There is no difference; they are the same thing with different names.
C.A Request for Change is raised for any deviation, while an Off-specification is only for threats.
D.A Request for Change proposes a modification to an agreed baseline, while an Off-specification identifies a product that does not meet its specification.
AnswerD

Correct distinction: RFC proposes a change; Off-specification identifies a failure to meet the specification.

Why this answer

A Request for Change proposes a modification to an agreed baseline, while an Off-specification is something that should be provided but is not (or is forecast not to be).

338
MCQmedium

In PRINCE2, what is the purpose of the Quality Review Technique?

A.To define quality criteria for products
B.To approve the Project Plan
C.To assess the project's overall quality management approach
D.To review a product's fitness for purpose against its quality criteria
AnswerD

Correct purpose.

Why this answer

The Quality Review Technique is a structured method for assessing whether a product meets its quality criteria, involving a presenter, reviewers, and a chair.

339
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board?

Select 3 answers
A.Performing project assurance activities
B.Making decisions on exception situations
C.Approving stage plans
D.Managing day-to-day activities
E.Providing overall direction and control
AnswersB, C, E

The Board decides on exceptions.

Why this answer

The Project Board is accountable for the project's success, approves stage plans, and provides direction. The PM manages day-to-day, and assurance is delegated.

340
MCQmedium

In the PRINCE2 risk management procedure, what is the immediate next step after assessing a risk?

A.Plan
B.Implement
C.Communicate
D.Identify
AnswerA

Plan comes after Assess in the recommended risk management procedure.

Why this answer

In the PRINCE2 risk management procedure, after assessing a risk (which includes evaluating its probability and impact), the immediate next step is to plan risk responses. This step involves identifying and selecting appropriate responses to address the risk, such as avoid, reduce, transfer, or accept. Option A is correct because planning directly follows assessment to determine how to manage the risk before any implementation or communication occurs.

Exam trap

Candidates often mistakenly think that 'Communicate' is a separate step after assessment, but in PRINCE2, communication is integrated throughout the risk management procedure.

How to eliminate wrong answers

Option B is wrong because 'Implement' is the step that comes after planning, where the planned risk responses are actually executed. Option C is wrong because 'Communicate' is a continuous activity throughout the risk management procedure, not a sequential step after assessment. Option D is wrong because 'Identify' is the step that precedes assessment, where risks are first identified and described.

341
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To prepare the Stage Plan for the next stage and update the Business Case
B.To control the work of the current stage
C.To close the project
D.To authorize work on the current stage
AnswerA

Managing a Stage Boundary produces the next Stage Plan and updates the Business Case for Board approval.

Why this answer

The purpose is to provide the Project Board with information to assess the viability of the project and authorize the next stage.

342
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Executive
B.Senior User
C.Project Manager
D.Project Board
AnswerC

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 assigns this role to the Project Manager as part of the 'Managing a Stage Boundary' and 'Directing a Project' processes. The Project Manager ensures the Business Case remains viable by updating it with actual costs, benefits, and risks, and by presenting it to the Project Board for approval at key decision points. This is distinct from the Executive, who owns the Business Case but delegates its day-to-day maintenance to the Project Manager.

Exam trap

The trap here is that candidates often confuse the Executive's ownership of the Business Case with the responsibility for its maintenance, leading them to incorrectly select the Executive instead of the Project Manager.

How to eliminate wrong answers

Option A is wrong because the Executive is the owner of the Business Case and is responsible for its creation and ultimate approval, but not for its ongoing maintenance; the Executive relies on the Project Manager to keep it updated. Option B is wrong because the Senior User is responsible for specifying the benefits and ensuring the project delivers them, but does not maintain the Business Case document itself. Option D is wrong because the Project Board is responsible for making key decisions and approving changes to the Business Case, but the actual maintenance and update of the document is a Project Manager responsibility.

343
MCQmedium

Which component of the Business Case describes the expected measurable improvements resulting from the project?

A.Reasons
B.Major risks
C.Dis-benefits
D.Expected benefits
AnswerD

Correct. Expected benefits are the measurable improvements resulting from the project.

Why this answer

The 'Expected benefits' component of the Business Case in PRINCE2 specifically quantifies the measurable improvements that the project will deliver, such as increased revenue, reduced costs, or improved efficiency. These benefits must be defined in measurable terms to enable post-project evaluation against the Business Case. The other options describe different aspects: Reasons justify the project, Major risks identify uncertainties, and Dis-benefits document negative outcomes.

Exam trap

The trap here is that candidates often confuse 'Reasons' (the justification) with 'Expected benefits' (the measurable outcomes), but PRINCE2 explicitly separates these components to ensure benefits are quantifiable and trackable.

How to eliminate wrong answers

Option A is wrong because 'Reasons' explain the justification for undertaking the project, not the measurable improvements. Option B is wrong because 'Major risks' are uncertainties that could affect the project's outcome, not the expected benefits. Option C is wrong because 'Dis-benefits' are negative consequences or outcomes that may arise from the project, which are distinct from the positive measurable improvements.

344
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To manage the day-to-day activities of the stage
B.To close the project
C.To plan the project at a high level
D.To enable the Project Board to review the current stage and approve the next
AnswerD

This is the correct purpose.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and update the project plan and business case. It ensures that the project remains viable before committing resources to the next stage, making D the correct answer.

Exam trap

Candidates often mistakenly think Managing a Stage Boundary is about day-to-day management (which is Controlling a Stage) or about closing the project. The key distinction is that this process provides a review and approval point for the Project Board before committing resources to the next stage.

How to eliminate wrong answers

Option A is wrong because managing day-to-day activities is the purpose of the Controlling a Stage process, not Managing a Stage Boundary. Option B is wrong because closing the project is the purpose of the Closing a Project process, which occurs after the final stage. Option C is wrong because high-level project planning is done during the Initiating a Project process, not during stage boundary management.

345
MCQmedium

Which document describes the quality criteria for a product and is used during quality inspection?

A.Project Product Description
B.Quality Register
C.Quality Management Strategy
D.Product Description
AnswerD

The Product Description includes quality criteria and is used for quality inspection.

Why this answer

A Product Description contains the quality criteria and is used as the basis for quality inspection.

346
MCQmedium

During the Managing Product Delivery process, a Team Manager identifies a defect in a product that is currently being developed. The defect means the product will not meet its agreed quality criteria. What should the Team Manager do?

A.Stop work on the product and wait for instructions
B.Raise an Issue to the Project Manager
C.Correct the defect immediately and report it in the next Checkpoint Report
D.Record the defect in the Quality Register only
AnswerB

Correct. The Team Manager raises an Issue so the Project Manager can assess the impact and decide on corrective action.

Why this answer

The correct action is to raise an Issue. In PRINCE2, any problem, including a defect, is logged as an Issue. The Project Manager then decides if it is an Off-specification, Request for Change, or Problem/Concern.

347
MCQmedium

Which of the following is NOT a component of the Business Case?

A.Major risks
B.Investment appraisal
C.Expected benefits
D.Project Plan
AnswerD

The Project Plan is a separate management product, not a component of the Business Case, so this is correct.

Why this answer

The Business Case in PRINCE2 includes reasons, options, benefits, dis-benefits, costs, timescale, investment appraisal, and major risks. The Project Plan is not a component of the Business Case; it is a separate management product that describes how and when the project's objectives are to be achieved.

348
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately
B.Raise an Exception Report to the Project Board
C.Report in the next Highlight Report
D.Increase the project budget and continue
AnswerB

This is management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Option B is correct.

349
MCQmedium

A team manager reports that a work package is complete. What should the Project Manager do to verify this?

A.Review the Team Plan to confirm all products are delivered and accepted
B.Log the completion in the Issue Register
C.Instruct the team to report directly to the Project Board
D.Check the product against its Product Description
AnswerA

The Team Plan shows what was agreed; the Project Manager reviews completion against it.

Why this answer

Reviewing the Team Plan is the correct action because the Team Plan documents all products to be delivered and their acceptance criteria. The Project Manager verifies completion by checking the Team Plan against actual achievements, ensuring all products are delivered and accepted. Option B is incorrect because the Issue Register is for recording issues, not work package completion.

Option C is incorrect because the team manager reports to the Project Manager, not directly to the Project Board. Option D is incorrect because checking the product against its Product Description is a quality inspection step, not the primary verification of work package completion.

350
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Brief
B.Risk Register
C.Business Case
D.Project Initiation Documentation
AnswerD

The PID is the key output of Initiating a Project, containing the project plan, business case, and other management documents.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project, providing a foundation for the project. Option A is wrong because the Project Brief is created during Starting Up a Project. Option B is wrong because the Risk Register is created during Initiating a Project but is not the key output; the PID is the primary document.

Option C is wrong because the Business Case is created in the Starting Up a Project process and refined during Initiating a Project.

351
MCQhard

What is the difference between a Risk Owner and a Risk Actionee?

A.Risk Owner is accountable for the risk; Risk Actionee performs the response actions
B.Risk Owner identifies the risk; Risk Actionee records it
C.There is no difference; they are interchangeable terms
D.Risk Owner is on the Project Board; Risk Actionee is on the team
AnswerA

Correct distinction per PRINCE2.

Why this answer

The Risk Owner is accountable for the overall management of the risk, including ensuring that appropriate responses are implemented. The Risk Actionee is assigned to carry out specific response actions to address the risk. Options B, C, and D are incorrect because they misstate the roles or claim they are interchangeable.

352
MCQeasy

What is the purpose of the Quality Register?

A.To list product descriptions
B.To record lessons learned
C.To record all quality activities and their results
D.To define the quality management approach
AnswerC

Correct.

Why this answer

The Quality Register records all planned and performed quality activities, providing a log for tracking quality events.

353
MCQmedium

Which report is produced by the Team Manager to inform the Project Manager about progress on a Work Package?

A.Highlight Report
B.Checkpoint Report
C.Exception Report
D.End Stage Report
AnswerB

Checkpoint Reports are from the Team Manager to the Project Manager, detailing progress on a Work Package.

Why this answer

The Checkpoint Report is a progress report from the Team Manager to the Project Manager, typically produced at a frequency defined in the Work Package. Highlight Reports go from PM to Project Board. Exception Reports are for tolerance breaches.

End Stage Reports are at stage end.

354
MCQhard

The Project Manager is reviewing an issue that affects a product currently in development. The product does not meet a requirement defined in its Product Description. What type of issue is this?

A.Request for Change
B.Risk
C.Problem/Concern
D.Off-specification
AnswerD

A product not meeting its specification is an Off-specification.

Why this answer

An Off-specification is something that should be provided but is not (or is provided but does not meet the specification).

355
MCQmedium

In a project using PRINCE2, the project board is reviewing the End Stage Report. They notice that the actual costs are significantly lower than planned, but the scope is complete. What should the project board do?

A.Request an exception plan to reallocate the surplus
B.Immediately authorize the next stage as the project is under budget
C.Ask the project manager to revise the project plan to increase costs
D.Review the End Stage Report and decide whether to authorize the next stage
AnswerD

The board uses the End Stage Report to review performance and make a decision on the next stage.

Why this answer

The project board's primary responsibility is to review the End Stage Report and decide whether to authorize the next stage based on continued business justification, not solely on cost performance. Being under budget with scope complete does not automatically trigger an exception plan or immediate authorization; the board must assess the overall viability, risks, and lessons learned before proceeding. Option D correctly reflects the PRINCE2 principle of continued business justification and the board's decision-making authority at stage boundaries.

Exam trap

PeopleCert often tests the misconception that being under budget automatically triggers an exception plan or immediate stage authorization, but PRINCE2 requires the project board to formally review the End Stage Report and make a deliberate decision based on continued business justification, not just cost performance.

How to eliminate wrong answers

Option A is wrong because an exception plan is only required when a stage is forecast to exceed tolerance levels (cost or time), not when actual costs are lower than planned; a surplus does not constitute a deviation requiring exception management. Option B is wrong because the project board cannot immediately authorize the next stage without reviewing the End Stage Report and confirming that the project remains viable; authorization is a formal decision based on the report's full content, not just cost performance. Option C is wrong because asking the project manager to revise the project plan to increase costs would violate the principle of continued business justification and is not a valid PRINCE2 action; the project should not artificially inflate costs.

356
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To provide the Project Board with information to approve the next stage
B.To plan the project as a whole
C.To close the project
D.To control the work of the current stage on a day-to-day basis
AnswerA

Managing a Stage Boundary provides the Project Board with the necessary information to approve the next stage.

Why this answer

The purpose of Managing a Stage Boundary is to enable the Project Board to review the current stage's performance, approve the next stage plan, and confirm continued business justification.

357
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.Project Brief
C.Project Plan
D.Business Case
AnswerA

The PID is the aggregation of all management products created during Initiating a Project.

Why this answer

The Initiating a Project process is where the project's foundations are solidified, and its key output is the Project Initiation Documentation (PID). The PID compiles the Project Brief, Business Case, Project Plan, and other management strategies into a single, consolidated document that defines what, why, who, when, and how of the project, forming the basis for management control and decision-making.

Exam trap

PeopleCert often tests the distinction between inputs and outputs of the Initiating a Project process, trapping candidates who confuse the Project Brief (an input) or individual components like the Project Plan or Business Case (which are parts of the PID) with the PID itself as the key output.

How to eliminate wrong answers

Option B (Project Brief) is wrong because the Project Brief is an input to the Initiating a Project process, not its output; it is created during the Starting Up a Project process. Option C (Project Plan) is wrong because while the Project Plan is a component of the PID, it is not the key output itself; the PID is the overarching document that contains the plan. Option D (Business Case) is wrong because the Business Case is also a component within the PID, but the PID as a whole is the definitive output that formalizes the project's justification and approach.

358
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change seeks to alter a product; an Off-specification is a failure to meet a requirement
B.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
C.A Request for Change is always approved; an Off-specification is always rejected
D.There is no difference; they are synonyms
AnswerA

Correct. RFC proposes a change; Off-specification indicates something is missing or wrong.

Why this answer

A Request for Change (RFC) is a formal proposal to modify a product, baseline, or configuration item, while an Off-specification (Off-spec) is a formal notification that a product does not meet its agreed specification or requirement. In PRINCE2, the RFC seeks to change what is specified, whereas the Off-spec identifies a failure to deliver what was specified. This distinction is fundamental to the Change Control approach within the PRINCE2 Practice of Change.

Exam trap

The trap here is confusing the direction of the change: candidates often think an Off-spec is a type of RFC, but PRINCE2 treats them as distinct issue types — one for proposing a change (RFC) and one for reporting a failure to meet requirements (Off-spec).

How to eliminate wrong answers

Option B is wrong because both a Request for Change and an Off-specification can be raised by anyone (e.g., Project Manager, team members, suppliers), not exclusively by the Project Board or Project Manager; the Project Board only approves or rejects them. Option C is wrong because neither is always approved or always rejected; each is evaluated on its merits and may be accepted, rejected, or deferred. Option D is wrong because they are not synonyms; an RFC proposes a change to an agreed specification, while an Off-spec reports a deviation from that specification.

359
MCQmedium

A team member reports a problem that could impact the next stage. What should the Team Manager do?

A.Immediately raise an Exception Report to the Project Board.
B.Log the issue in the Risk Register and continue.
C.Update the Stage Plan to address the problem.
D.Raise the issue in the next Checkpoint Report to the Project Manager.
AnswerD

The Team Manager communicates issues to the PM via Checkpoint Reports.

Why this answer

The Team Manager's first responsibility is to escalate the problem to the Project Manager via the next Checkpoint Report, which is the formal reporting mechanism for issues within the team. The Project Manager then decides if the issue requires an Exception Report to the Project Board. This aligns with PRINCE2's management by exception principle, where the Team Manager does not bypass the Project Manager unless the issue is outside delegated tolerances.

Exam trap

PRINCE2 candidates often mistakenly think that any problem impacting a stage must immediately go to the Project Board via an Exception Report, but the correct escalation path is first through the Checkpoint Report to the Project Manager, who then decides on escalation based on tolerance thresholds.

How to eliminate wrong answers

Option A is wrong because the Team Manager cannot directly raise an Exception Report to the Project Board; that is the Project Manager's responsibility after assessing if the issue exceeds stage tolerances. Option B is wrong because the issue should be logged in the Issue Register, not the Risk Register, as it is a current problem, not a future uncertainty. Option C is wrong because the Team Manager cannot unilaterally update the Stage Plan; only the Project Manager can authorize changes to the plan after evaluating the impact.

360
MCQmedium

Who is responsible for producing a Checkpoint Report?

A.Senior User
B.Project Manager
C.Team Manager
D.Project Support
AnswerC

Team Managers report to the Project Manager via Checkpoint Reports.

Why this answer

The Checkpoint Report is a progress report on the work performed within a Work Package, and it is produced by the Team Manager (or the team member responsible for the work package) to provide the Project Manager with a summary of progress at a frequency defined in the Work Package. This is because the Team Manager is the role that manages the day-to-day work of the team and is best positioned to report on actual progress against the plan.

Exam trap

The trap here is that candidates often confuse the Checkpoint Report (produced by the Team Manager) with the Highlight Report (produced by the Project Manager), leading them to incorrectly select the Project Manager as the responsible role.

How to eliminate wrong answers

Option A is wrong because the Senior User is responsible for specifying the user requirements and benefits, not for producing operational progress reports like the Checkpoint Report. Option B is wrong because the Project Manager is responsible for producing the Highlight Report (for the Project Board) and managing the overall project, not the Checkpoint Report which is a team-level report. Option D is wrong because Project Support provides administrative and advisory services (e.g., maintaining files, tools, or configuration management) but does not produce the Checkpoint Report; that is a management responsibility of the Team Manager.

361
MCQhard

What is the difference between a Highlight Report and a Checkpoint Report?

A.Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
B.They are the same but with different names
C.Highlight Reports are written by the team; Checkpoint Reports are written by the PM
D.Highlight Reports are for stakeholders; Checkpoint Reports are for the Project Board
AnswerA

Correct.

Why this answer

Highlight Reports are from PM to Project Board; Checkpoint Reports are from Team Manager to PM.

362
Multi-Selectmedium

Which TWO of the following are elements of the Business Case?

Select 2 answers
A.Project Plan
B.Expected benefits
C.Major risks
D.Quality Register
E.Risk Register
AnswersB, C

Expected benefits are a required component of the Business Case.

Why this answer

Expected benefits and major risks are key components of a Business Case in PRINCE2.

363
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Plan
B.Project Initiation Documentation (PID)
C.Business Case
D.Stage Plan
AnswerB

The PID is the comprehensive document produced during the Initiating a Project process.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, as it defines the project and serves as the foundation for its management.

364
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Executive
D.Project Support
AnswerB

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive (Senior Responsible Owner) owns it and is accountable for its viability.

365
MCQmedium

During which process does the Project Board make a decision on the next stage after reviewing the End Stage Report?

A.Initiating a Project
B.Managing a Stage Boundary
C.Directing a Project
D.Controlling a Stage
AnswerB

During this process, the Project Board reviews the End Stage Report and approves the next Stage Plan.

Why this answer

Managing a Stage Boundary process includes the Project Board reviewing the End Stage Report and deciding whether to approve the next Stage Plan. Directing a Project is the process where the Board makes high-level decisions, but the formal review and approval of the next stage occurs during Managing a Stage Boundary.

366
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is a proposal; an Off-specification is a failure to meet a specification
B.A Request for Change is for scope changes; an Off-specification is for quality changes
C.An Off-specification is always a threat; a Request for Change is always an opportunity
D.They are the same thing
AnswerA

Correct distinction.

Why this answer

A Request for Change proposes a modification; an Off-specification is a product that does not meet its specification.

367
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Management by Exception
B.Product-based Planning
C.Risk-based Planning
D.Focus on Products
E.Manage by Stages
AnswersA, D

Correct. 'Management by Exception' is a recognized PRINCE2 principle, referring to the practice of delegating authority and escalating issues when tolerances are exceeded.

Why this answer

PRINCE2 has seven principles: Continued Business Justification, Learn from Experience, Defined Roles and Responsibilities, Manage by Stages, Manage by Exception, Focus on Products, and Tailor to Suit the Project Environment. 'Management by Exception' (A) is a principle despite the slight wording difference, 'Focus on Products' (D) is a principle, and 'Manage by Stages' (E) is also a principle. However, the question asks for TWO principles, so options A and D are selected as correct. 'Product-based Planning' (B) is a technique, not a principle, and 'Risk-based Planning' (C) is not a PRINCE2 principle.

368
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.An RFC is a request for a new feature, while an Off-specification is a report of a defect
B.An RFC seeks to change an approved baseline, while an Off-specification reports a failure to meet a specified requirement
C.An RFC is used for threats, while an Off-specification is used for opportunities
D.An RFC is raised by the Project Board, while an Off-specification is raised by the Project Manager
AnswerB

This is the correct distinction.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify an approved baseline (e.g., a product description, plan, or scope), while an Off-specification is a notification that a product has failed to meet a specified requirement or acceptance criterion. The RFC seeks to change the baseline itself, whereas the Off-specification reports a deviation from the agreed specification that must be resolved, often via a concession or corrective action.

Exam trap

The trap here is that candidates confuse the 'defect' nature of an Off-specification with a simple bug report, when in PRINCE2 it is a formal issue that reports any failure to meet a specified requirement, and an RFC is not just for new features but for any change to an approved baseline.

How to eliminate wrong answers

Option A is wrong because an RFC is not limited to new features; it can request any change to an approved baseline, including modifications to existing functionality, while an Off-specification is not merely a 'defect' but any failure to meet a specified requirement, which could include missing documentation or performance criteria. Option C is wrong because both RFCs and Off-specifications are used for issues (unplanned events requiring management action), not specifically for threats or opportunities; threats and opportunities are managed via the risk register, not via change control. Option D is wrong because both RFCs and Off-specifications can be raised by any stakeholder, not exclusively by the Project Board or Project Manager; the Project Board authorizes changes, but the raising of these documents is not restricted to specific roles.

369
MCQhard

The Managing a Stage Boundary process includes which of the following activities?

A.Authorising a Work Package
B.Producing an Exception Plan
C.Producing an End Stage Report and a Stage Plan for the next stage
D.Updating the Business Case
AnswerC

These are key outputs of Managing a Stage Boundary.

Why this answer

Managing a Stage Boundary includes producing an End Stage Report and preparing a Stage Plan for the next stage.

370
MCQhard

In the PRINCE2 risk management procedure, which step follows 'Assess'?

A.Implement
B.Communicate
C.Identify
D.Plan
AnswerD

Plan follows Assess in the procedure.

Why this answer

The procedure steps are: Identify, Assess, Plan, Implement, Communicate. 'Plan' comes after 'Assess'.

371
MCQeasy

What is the difference between a Checkpoint Report and a Highlight Report?

A.Checkpoint Reports are from Team Manager to Project Manager; Highlight Reports are from Project Manager to Project Board
B.Checkpoint Reports are produced by the Project Manager; Highlight Reports by the Team Manager
C.Checkpoint Reports are only produced at stage boundaries; Highlight Reports are produced weekly
D.Checkpoint Reports are sent to the Project Board; Highlight Reports are sent to the Project Manager
AnswerA

Correct: Checkpoint Reports are for team delivery status; Highlight Reports give the Board an overview.

Why this answer

Checkpoint Reports are from Team Managers to the Project Manager, while Highlight Reports are from the Project Manager to the Project Board.

372
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Raise an Exception Report to the Project Board and await directions
B.Increase the stage budget by using the project's change budget
C.Continue with the current plan and report the overrun in the next Highlight Report
D.Close the project as the Business Case is no longer viable
AnswerA

When stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report to the Project Board, which will decide on corrective action.

Why this answer

According to PRINCE2's management by exception principle, if a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The PM cannot exceed tolerance without authorization.

373
MCQmedium

Which process does the Project Board use to make key decisions and commit resources?

A.Managing a Stage Boundary
B.Controlling a Stage
C.Directing a Project
D.Managing Product Delivery
AnswerC

This is the process for the Project Board to make high-level decisions and commit resources.

Why this answer

Directing a Project. This process is used by the Project Board to make key decisions, such as authorizing initiation, stage plans, and project closure. Option A (Managing a Stage Boundary) is performed by the Project Manager.

Option B (Controlling a Stage) is also a Project Manager process. Option D (Managing Product Delivery) is a Team Manager process.

374
MCQeasy

Which role is responsible for providing assurance that the project is being conducted properly?

A.Project Manager
B.Project Support
C.Project Assurance
D.Senior User
AnswerC

Project Assurance provides independent oversight.

Why this answer

Project Assurance is responsible for independent oversight of the project, separate from management and delivery.

375
Multi-Selecthard

Which THREE elements are part of the PRINCE2 Quality practice?

Select 3 answers
A.Customer's quality expectations
B.Project product description
C.Quality control
D.Acceptance criteria
E.Quality register
AnswersA, C, D

These are defined in the project product description and are part of the Quality practice.

Why this answer

The Customer's quality expectations are a key input to the PRINCE2 Quality practice, defining the criteria that the project's products must meet from the customer's perspective. These expectations are documented in the Project Product Description and used to derive acceptance criteria and quality control activities.

Exam trap

PeopleCert often tests the distinction between management products (like the Project Product Description and Quality Register) and the core elements of a practice, leading candidates to mistakenly select the Project Product Description as an element of the Quality practice when it is actually a container for those elements.

← PreviousPage 5 of 8 · 596 questions totalNext →

Ready to test yourself?

Try a timed practice session using only Prince2 Practices questions.