CCNA Prince2 Practices Questions

75 of 674 questions · Page 5/9 · Prince2 Practices topic · Answers revealed

301
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Revise the Project Plan to reduce costs in later stages
B.Issue a Highlight Report noting the overrun
C.Raise an Exception Report to the Project Board
D.Request additional funds from the Executive informally
AnswerC

Correct action when tolerance is forecast to be exceeded.

Why this answer

When a stage-level tolerance is forecast to be exceeded, the Project Manager must escalate via an Exception Report. This is management by exception.

302
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue with the current plan and adjust the budget in the next stage
B.Close the project immediately
C.Issue an Exception Report to the Project Board
D.Reduce the scope to stay within budget without informing the Board
AnswerC

An Exception Report is the correct mechanism to escalate the forecast deviation.

Why this answer

Management by exception dictates that when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Continuing without escalation is not allowed.

303
MCQeasy

Which practice describes the project management team structure and defines roles and responsibilities?

A.Plans
B.Business Case
C.Organising
D.Progress
AnswerC

Correct. Organising defines the team structure and responsibilities.

Why this answer

The Organising practice defines the project management team structure and assigns roles and responsibilities. It includes the Project Board, Project Manager, Team Managers, and other roles.

304
MCQmedium

Which of the following best describes the purpose of the Directing a Project process?

A.To enable the Project Board to make key decisions and exercise overall control
B.To coordinate the work of the team
C.To produce the Project Plan
D.To manage the day-to-day activities of the project
AnswerA

Correct purpose.

Why this answer

The Directing a Project process is designed to enable the Project Board to make key decisions and exercise overall control over the project. It covers the board's responsibilities from project initiation through closure, including authorizing stages, reviewing progress, and providing strategic direction.

Exam trap

PeopleCert often tests the distinction between the Project Board's strategic oversight (Directing a Project) and the Project Manager's operational management (Controlling a Stage), leading candidates to confuse the two.

How to eliminate wrong answers

Option B is wrong because coordinating the work of the team is the purpose of the Managing Product Delivery process, not Directing a Project. Option C is wrong because producing the Project Plan is an activity within the Initiating a Project process, not a purpose of Directing a Project. Option D is wrong because managing day-to-day activities is the responsibility of the Project Manager via the Controlling a Stage process, not the Directing a Project process.

305
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Project Plan
B.The Business Case
C.The Project Brief
D.The Project Initiation Documentation
AnswerD

The PID is the key output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing a comprehensive basis for the project.

306
MCQmedium

Which role is responsible for providing assurance that the project is being managed correctly in terms of business, user, and supplier interests?

A.Project Support
B.Project Manager
C.Team Manager
D.Project Assurance
AnswerD

Project Assurance provides independent oversight of the project's management.

Why this answer

Option C is correct. Project Assurance is an independent role that provides assurance to the Project Board on all three interests. Option A is incorrect because Project Support provides administrative support, not independent assurance.

Option B is incorrect because the Project Manager is responsible for day-to-day management, not independent assurance. Option D is incorrect because the Team Manager is responsible for delivering work packages.

307
Multi-Selecthard

Which TWO of the following are opportunity responses in PRINCE2?

Select 2 answers
A.Share
B.Transfer
C.Reduce
D.Enhance
E.Avoid
AnswersA, D

Share is an opportunity response to allocate ownership to a third party best able to realize it.

Why this answer

PRINCE2 defines opportunity responses: exploit, enhance, share, and reject. Avoid and transfer are threat responses.

308
Multi-Selectmedium

Which TWO of the following are correct statements about tolerance in PRINCE2?

Select 2 answers
A.The Project Board sets stage tolerances for the Project Manager
B.If a stage tolerance is exceeded, the Project Manager must escalate
C.Tolerances apply only to time and cost
D.The Project Manager can never change tolerances without Board approval
E.Tolerances are set only at project level
AnswersA, B

The Board delegates authority via stage tolerances.

Why this answer

Tolerances are set for each management level; the Project Board sets stage tolerances. The Project Manager can reallocate tolerance within a stage if the total is not exceeded.

309
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Supplier
B.Project Manager
C.Senior User
D.Executive
AnswerD

The Executive is the single point of accountability for the business justification and owns the Business Case.

Why this answer

The Executive is the single person ultimately accountable for the project's Business Case and its continued viability. PRINCE2 assigns responsibility for maintaining the Business Case to the Executive because they own the project's justification and must ensure it remains aligned with organizational objectives throughout the project lifecycle.

Exam trap

PeopleCert often tests the distinction between 'ownership' and 'management' of the Business Case, trapping candidates who confuse the Project Manager's role in drafting the document with the Executive's accountability for its content and viability.

How to eliminate wrong answers

Option A is wrong because the Senior Supplier represents the interests of those providing the project's products and is responsible for the quality of deliverables, not for maintaining the Business Case. Option B is wrong because the Project Manager manages the day-to-day creation of the Business Case but does not own it; the Project Manager's role is to develop and update the document under the Executive's authority. Option C is wrong because the Senior User represents the users' needs and ensures the final product meets requirements, but they do not hold accountability for the Business Case's ongoing justification.

310
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Project Manager
B.The Project Assurance
C.The Executive
D.The Senior Supplier
AnswerA

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 assigns the day-to-day management of the Business Case to the Project Manager, who must ensure it remains viable and aligned with project progress. The Project Manager updates the Business Case with actual costs, benefits, and risks, and presents it to the Project Board for approval at key decision points. This is defined in PRINCE2's Business Case management process, where the Project Manager owns the document's maintenance, not its approval.

Exam trap

PeopleCert often tests the distinction between ownership (Executive) and maintenance (Project Manager), causing candidates to incorrectly select the Executive because they confuse ultimate accountability with operational responsibility.

How to eliminate wrong answers

Option B is wrong because Project Assurance is an independent oversight role that reviews and verifies the Business Case's integrity, but does not maintain or update it. Option C is wrong because the Executive is the ultimate owner of the Business Case and is responsible for its approval and justification, but the day-to-day maintenance is delegated to the Project Manager. Option D is wrong because the Senior Supplier provides supplier-side expertise and resources, but has no direct responsibility for maintaining the Business Case, which is a management product owned by the Project Manager.

311
MCQmedium

In the Progress practice, what is 'management by exception'?

A.The Project Manager must report all decisions to the Project Board
B.Management is only involved when tolerances are forecast to be exceeded
C.The Project Board manages the project on a daily basis
D.All deviations from the plan must be approved by the Project Board
AnswerB

This is the definition of management by exception.

Why this answer

Management by exception means that the Project Manager is allowed to manage within agreed tolerances; if a tolerance is forecast to be exceeded, the matter is escalated to the Project Board.

312
MCQeasy

Which role is accountable for the project's success and chairs the Project Board?

A.Senior User
B.Executive
C.Project Manager
D.Senior Supplier
AnswerB

The Executive chairs the Project Board and is accountable for the project.

Why this answer

The Executive is the single individual accountable for the project's success and chairs the Project Board in PRINCE2. This role provides the business justification, secures funding, and makes key strategic decisions, ensuring the project remains viable and aligned with organizational objectives.

Exam trap

The trap here is confusing accountability with responsibility, leading candidates to pick the Project Manager (who is responsible for delivery) instead of the Executive (who is accountable for success and chairs the Board).

How to eliminate wrong answers

Option A is wrong because the Senior User represents the interests of those who will use the project's outputs, but they are not accountable for overall project success nor do they chair the Project Board. Option C is wrong because the Project Manager is responsible for day-to-day management and delivery within constraints set by the Board, but accountability and chairing authority rest with the Executive. Option D is wrong because the Senior Supplier represents the interests of those providing the project's products and resources, but they do not hold ultimate accountability or chair the Board.

313
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To plan the next stage and provide information for the Project Board to decide on continuation
C.To initiate the project
D.To manage the work of the current stage
AnswerB

Correct.

Why this answer

The purpose is to provide the Project Board with information to approve the next stage and review the current stage's performance.

314
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To control the work of the current stage
B.To close the project
C.To initiate the project
D.To plan the next stage and provide an End Stage Report to the Project Board
AnswerD

The process produces an End Stage Report and a next Stage Plan for approval.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and decide whether to continue the project. It produces an End Stage Report summarizing the current stage's results and a Stage Plan for the next stage, enabling informed governance decisions.

Exam trap

PeopleCert often tests the confusion between 'controlling a stage' and 'managing a stage boundary'—candidates mistakenly think the boundary process handles day-to-day stage control, but it is specifically about stage-end review and next-stage planning.

How to eliminate wrong answers

Option A is wrong because controlling the work of the current stage is the purpose of the Controlling a Stage process, not Managing a Stage Boundary. Option B is wrong because closing the project is the purpose of the Closing a Project process, which occurs after the final stage. Option C is wrong because initiating the project is the purpose of the Initiating a Project process, which sets up the project management foundation before any delivery stages begin.

315
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change always requires a change budget; an Off-specification does not
B.A Request for Change proposes a modification to baselined products; an Off-specification identifies a failure to meet a specification
C.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
D.A Request for Change is recorded in the Risk Register; an Off-specification is recorded in the Issue Register
AnswerB

This is the correct distinction: RFC proposes a change, Off-specification identifies a deviation.

Why this answer

A Request for Change is a proposal for a change to a product that has been agreed or baselined. An Off-specification is something that should be provided but is not (or is forecast not to be) provided.

316
MCQmedium

What is the purpose of the Plans practice?

A.To define the project's quality criteria
B.To manage changes to project baselines
C.To define the roles and responsibilities of the project team
D.To facilitate communication and control by defining the means of delivering the products
AnswerD

This is the purpose of the Plans practice.

Why this answer

The Plans practice defines the means of delivering the products by establishing a structured approach to planning, including the creation of project and stage plans. This facilitates communication and control by providing a clear roadmap for stakeholders and enabling progress tracking against baselines. It is not about defining quality criteria, managing changes, or assigning roles, which are covered by other PRINCE2 practices.

Exam trap

The trap here is that candidates often confuse the Plans practice with the Quality practice, mistakenly thinking that plans define quality criteria, when in fact plans focus on the sequence and means of product delivery, not the quality standards.

How to eliminate wrong answers

Option A is wrong because defining the project's quality criteria is the purpose of the Quality practice, not the Plans practice. Option B is wrong because managing changes to project baselines is the purpose of the Change practice, which handles issue and change control. Option C is wrong because defining the roles and responsibilities of the project team is the purpose of the Organization practice, which establishes the project management team structure.

317
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Request for Change
B.Off-specification
C.Risk
D.Opportunity
E.Change budget
AnswersA, B

A Request for Change is a type of issue.

Why this answer

Request for Change and Off-specification are two types of issue. The third is Problem/Concern. All three are valid; the question asks for two of them.

318
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To enable the Project Board to review the current stage and approve the next stage plan
B.To accept Work Packages and deliver products
C.To provide overall direction and control to the project
D.To prepare the End Project Report and close the project
AnswerA

Managing a Stage Boundary prepares the information for the Project Board to decide on stage boundaries.

Why this answer

The Managing a Stage Boundary process provides the Project Board with information to review the current stage, approve the next stage plan, and update the project plan and Business Case. Option C correctly captures this. Option A is the purpose of Managing Product Delivery.

Option B is the purpose of Directing a Project. Option D is the purpose of Closing a Project.

319
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project as the Business Case is no longer viable.
B.Increase the project budget using the change budget.
C.Raise an Exception Report and await Project Board direction.
D.Continue with the plan and report the overrun in the next Highlight Report.
AnswerC

The Project Manager must escalate via an Exception Report.

Why this answer

C is correct because when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is a PRINCE2 management by exception principle: tolerances are delegated limits, and exceeding them requires board-level decision-making, not unilateral action by the Project Manager.

Exam trap

The trap here is that candidates confuse the Project Manager's authority to manage within tolerances with the ability to handle breaches, leading them to choose 'continue and report later' (D) or 'use change budget' (B), when PRINCE2 mandates immediate escalation via an Exception Report.

How to eliminate wrong answers

Option A is wrong because closing the project is a Project Board decision, not the Project Manager's, and exceeding cost tolerance does not automatically invalidate the Business Case—the board may approve a revised plan. Option B is wrong because the change budget is for authorized changes, not for covering forecast overruns; using it without board approval violates PRINCE2's change control approach. Option D is wrong because continuing the plan and reporting in the next Highlight Report ignores the escalation requirement; an Exception Report is mandatory when a tolerance is forecast to be breached.

320
Multi-Selectmedium

Which THREE of the following are roles on the Project Board?

Select 3 answers
A.Senior Supplier
B.Project Support
C.Senior User
D.Executive
E.Project Manager
AnswersA, C, D

The Senior Supplier represents those who provide resources and expertise.

Why this answer

The Project Board consists of Executive, Senior User, and Senior Supplier.

321
Drag & Dropmedium

Drag and drop the steps to create a PRINCE2 project plan into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Planning steps: design the plan, define products, identify activities, estimate, and schedule/document.

322
MCQeasy

Which process authorizes a work package?

A.Managing Product Delivery
B.Controlling a Stage
C.Starting Up a Project
D.Initiating a Project
AnswerB

The PM authorizes work packages during CS.

Why this answer

In Controlling a Stage, the Project Manager authorizes work packages to Team Managers. The Project Board authorizes stages, not work packages directly.

323
MCQmedium

What is the purpose of the Quality Review technique?

A.To approve the Project Plan
B.To establish the project's acceptance criteria
C.To assign risk owners to identified risks
D.To assess whether a product meets its quality criteria and identify errors
AnswerD

This is the purpose of the Quality Review technique.

Why this answer

The Quality Review technique is used to assess whether a product meets its quality criteria and to identify errors.

324
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a modification to a baseline, whereas an Off-specification identifies a failure to meet a baseline
B.There is no difference; they are the same thing
C.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
D.An Off-specification requires a change budget, while a Request for Change does not
AnswerA

Correct distinction.

Why this answer

A Request for Change is a proposal for a change to the project's baselines, while an Off-specification is something that should be provided but is not (or is forecast not to be).

325
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Raise an Exception Report to the Project Board
B.Close the project immediately
C.Continue with the current plan and report at the next Highlight Report
D.Increase the budget and inform the Project Board
AnswerA

Correct action when tolerance is forecast to be exceeded.

Why this answer

When a tolerance is forecast to be exceeded, the PM must escalate via an Exception Report to the Project Board. This is management by exception.

326
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is for any change, while an Off-specification is for a product that has not been approved
B.A Request for Change proposes a modification to an approved product, while an Off-specification identifies a product that does not meet its specification
C.A Request for Change is raised by the Project Manager, while an Off-specification is raised by the Team Manager
D.A Request for Change requires a change budget, while an Off-specification requires contingency
AnswerB

This is the correct distinction.

Why this answer

A Request for Change is a proposal for a modification to a product that has been approved, while an Off-specification is a product that does not meet its specification.

327
MCQmedium

In the Progress practice, who receives the Highlight Report?

A.Project Support
B.Senior User
C.Project Board
D.Team Manager
AnswerC

The Highlight Report is directed to the Project Board.

Why this answer

The Highlight Report is produced by the Project Manager and sent to the Project Board and stakeholders to provide a summary of progress.

328
Multi-Selecthard

Which THREE of the following are true about the PRINCE2 Quality Review technique?

Select 3 answers
A.It can include participants external to the project team
B.It requires the presence of a Project Assurance representative
C.It involves defined roles such as Chair, Presenter, and Reviewer
D.It is a method of testing the product against its specification
E.It is a systematic examination of a product to identify defects
AnswersA, C, E

External experts can be invited to provide independent review.

Why this answer

Options A, C, and D are correct. The Quality Review technique is a structured review with defined roles (chair, presenter, reviewer, administrator). It is a team-based inspection, not a test.

It may involve external experts. The goal is to assess whether the product meets its quality criteria. Options B and E are false: quality review is not a test (B), and the reviewer role is mandatory (E).

329
MCQmedium

Which risk response is appropriate for an opportunity that the project wants to make more likely to happen?

A.Reject
B.Exploit
C.Share
D.Enhance
AnswerB

Exploit aims to make the opportunity happen.

Why this answer

To increase the probability and/or impact of an opportunity, use the 'exploit' response.

330
MCQhard

An issue is raised stating that a product has been delivered but does not meet its agreed specification. What type of issue is this?

A.Request for Change
B.Risk
C.Problem/Concern
D.Off-specification
AnswerD

This describes a product not meeting its specification.

Why this answer

An Off-specification is an issue where a product should be provided but is not (or is forecast not to be) according to its specification. This includes a product delivered that does not meet its specification.

331
MCQeasy

What does the 'management by exception' principle in PRINCE2 mean?

A.The Project Board sets tolerances and only reviews the project if tolerances are forecast to be exceeded
B.The Project Manager must report all decisions to the Project Board immediately
C.The Project Board makes all decisions for the project
D.The Project Manager can ignore plans and work independently
AnswerA

This is the core of management by exception.

Why this answer

Option C is correct. Management by exception means that the Project Board sets tolerances and only gets involved if those tolerances are forecast to be exceeded. This empowers the Project Manager to manage within the tolerances without constant board oversight.

332
MCQmedium

Which document describes the quality expectations and acceptance criteria for a project's products?

A.Product Description
B.Quality Management Approach
C.Project Product Description
D.Quality Register
AnswerB

This document sets out the quality procedures, standards, and acceptance criteria for the project.

Why this answer

The Quality Management Approach defines how quality will be managed, including quality criteria and acceptance methods.

333
MCQmedium

Which PRINCE2 principle is being applied when a project uses management by exception?

A.Continued business justification
B.Manage by exception
C.Manage by stages
D.Focus on products
AnswerB

Correct principle.

Why this answer

Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.

334
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Plan
C.Project Brief
D.Project Initiation Documentation
AnswerD

The PID is the comprehensive document that consolidates all information required to start the project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It defines the project's scope, objectives, and approach.

335
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Exception Plan
B.Off-specification
C.Risk
D.Lessons Report
E.Request for Change
AnswersB, E

A product that does not meet its specification.

Why this answer

The three predefined issue types are Request for Change, Off-specification, and Problem/Concern. Risk is a different management product.

336
MCQhard

In the Risk management procedure, what is the difference between a Risk Owner and a Risk Actionee?

A.Risk Owner monitors the risk; Risk Actionee updates the Risk Register
B.Risk Owner is accountable for the risk; Risk Actionee is accountable for the response budget
C.Risk Owner manages the risk; Risk Actionee implements the response actions
D.Risk Owner identifies the risk; Risk Actionee evaluates it
AnswerC

This is the correct distinction.

Why this answer

The Risk Owner is responsible for managing the risk overall; the Risk Actionee is assigned to implement specific response actions.

337
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do first?

A.Close the project immediately
B.Issue an Exception Report to the Project Board
C.Increase the budget to cover the extra cost
D.Continue with the current plan and report at the end of the stage
AnswerB

The Project Manager must escalate via an Exception Report when tolerances are forecast to be exceeded.

Why this answer

According to the management by exception principle, when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

338
MCQhard

In product-based planning, what is the purpose of a Product Flow Diagram?

A.To show the hierarchical breakdown of products
B.To identify the resources needed for each product
C.To list the quality criteria for each product
D.To show the sequence and dependencies of product creation
AnswerD

The Product Flow Diagram maps the order and dependencies of product development.

Why this answer

A Product Flow Diagram shows the order in which products will be developed and the dependencies between them. It is a key input to the activity network.

339
MCQmedium

Which of the following is an opportunity response in PRINCE2?

A.Exploit
B.Accept
C.Transfer
D.Avoid
AnswerA

Exploit is an opportunity response.

Why this answer

PRINCE2 defines five threat responses and five opportunity responses; 'Exploit' is a response to an opportunity to ensure it happens.

340
Multi-Selectmedium

Which TWO of the following are threat response types in PRINCE2 risk management?

Select 2 answers
A.Exploit
B.Enhance
C.Share
D.Avoid
E.Reduce
AnswersD, E

Avoid is a threat response.

Why this answer

Avoid and Reduce are threat responses; Exploit and Enhance are opportunity responses.

341
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To manage the day-to-day activities of the team
B.To plan the next stage in detail and obtain Project Board approval
C.To close the project and produce the End Project Report
D.To initiate the project and create the PID
AnswerB

This is the core purpose of SB: to plan the next stage and seek approval.

Why this answer

Managing a Stage Boundary (SB) is designed to provide the Project Board with information to review the current stage's performance, approve the next stage plan, and update the Business Case and project plan.

342
Multi-Selecthard

Which TWO statements correctly describe the difference between the risk owner and the risk actionee?

Select 2 answers
A.There can be multiple risk actionees for a single risk; there is only one risk owner
B.The risk owner is always a member of the Project Board; the risk actionee is always a team member
C.The risk owner is responsible for updating the risk register; the risk actionee is not
D.The risk actionee is responsible for identifying new risks; the risk owner is responsible for implementing responses
E.The risk owner is accountable for the risk; the risk actionee carries out actions
AnswersA, E

This is correct.

Why this answer

The risk owner is responsible for managing the risk, while the risk actionee performs specific actions.

343
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is a threat; an Off-spec is an opportunity
B.An RFC requires a change budget; an Off-spec does not
C.An RFC proposes a change to a baselined product; an Off-spec is a product that does not meet its specification
D.An RFC is raised by the Project Manager; an Off-spec is raised by the Project Board
AnswerC

This is the key distinction.

Why this answer

An RFC proposes a modification to a product that has been approved or baselined; an Off-spec is something that should be provided but is not (or will not be) as specified.

344
MCQmedium

In the Organising practice, what is the single point of accountability for the project's business justification?

A.The Project Manager
B.The Executive (Senior Responsible Owner)
C.The Senior User
D.The Project Board
AnswerB

The Executive is accountable for the Business Case and business justification.

Why this answer

The Executive (Senior Responsible Owner) is the single point of accountability for the business justification in PRINCE2.

345
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; the terms are interchangeable
B.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
C.A Request for Change seeks to change a product without a baseline; an Off-specification relates to a baselined product
D.An Off-specification is a failure to meet a specification; a Request for Change is a proposal to change a specification
AnswerD

Off-specification indicates non-conformance; Request for Change proposes a deliberate change.

Why this answer

An Off-specification is something that should be provided but is not (or is wrong). A Request for Change is a proposed modification to a baselined product.

346
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Providing overall direction and control of the project
B.Managing day-to-day activities of the project
C.Approving the Project Plan and any stage plans
D.Maintaining the Business Case
E.Producing Team Plans
AnswersA, C

The Project Board is accountable for the project's success and provides direction and control.

Why this answer

Options B and D are correct. The Project Board is responsible for approving plans and resources (B) and providing direction and control (D). Maintaining the Business Case is the PM's job; producing Team Plans is the Team Manager's; managing day-to-day activities is the PM's.

347
MCQmedium

Which of the following is NOT a component of the Business Case?

A.Expected benefits
B.Major risks
C.Product description
D.Investment appraisal
AnswerC

A product description is part of quality and plans, not the Business Case.

Why this answer

The Business Case components include reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. A product description is part of product-based planning, not the Business Case.

348
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Project Board
D.Senior Supplier
AnswerB

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Executive (SRO) owns the Business Case and is responsible for maintaining its viability. The Project Manager maintains it on a day-to-day basis.

349
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
B.Close the project immediately as the Business Case is no longer viable
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

Option C is correct. When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation.

Option A is wrong because the PM cannot increase the budget without Project Board approval. Option B is wrong because continuing without escalation violates management by exception. Option D is wrong because closing the project is not the appropriate response to a stage tolerance breach.

350
MCQeasy

Which of the following is NOT a component of the Business Case?

A.Investment appraisal
B.Risk Register
C.Major risks
D.Expected benefits
AnswerB

The Risk Register is a separate management product.

Why this answer

The Business Case includes reasons, options, benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. The Risk Register is separate.

351
MCQeasy

What is the purpose of the Highlight Report?

A.To detail the work packages for the next stage
B.To provide the Project Board with a summary of stage progress
C.To report issues to the Project Board
D.To report team progress to the Project Manager
AnswerB

This is the main purpose of the Highlight Report.

Why this answer

The Highlight Report is produced by the Project Manager and sent to the Project Board at regular intervals to provide a summary of progress during a stage.

352
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Investment appraisal
B.Configuration Item Records
C.Product Description
D.Risk Register
E.Expected benefits
AnswersA, E

Investment appraisal is a key component, showing the justification for the project.

Why this answer

The Business Case includes expected benefits, dis-benefits, costs, timescale, risks, and investment appraisal. Options B and E are correct; A, C, and D are not standard components.

353
Multi-Selectmedium

Which THREE of the following are components of the Business Case?

Select 3 answers
A.Major risks
B.Expected benefits
C.Project approach
D.Investment appraisal
E.Benefits review plan
AnswersA, B, D

Major risks are included.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Benefits review plan is part of the project plan, not the Business Case.

354
MCQeasy

According to PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior Supplier
C.Senior User
D.Project Board
AnswerA

Correct. The Project Manager maintains the Business Case.

Why this answer

In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains a living document that reflects the current justification for the project.

Exam trap

The trap here is that candidates often assume the Project Board, as the ultimate decision-making body, is responsible for maintaining the Business Case, but PRINCE2 explicitly assigns this maintenance role to the Project Manager.

How to eliminate wrong answers

Option B is wrong because the Senior Supplier is responsible for providing the necessary resources and expertise, not for maintaining the Business Case. Option C is wrong because the Senior User represents the users' interests and specifies the benefits, but does not maintain the Business Case document. Option D is wrong because the Project Board is responsible for approving the Business Case and making key decisions, but the day-to-day maintenance and monitoring of the Business Case is delegated to the Project Manager.

355
MCQmedium

During a project, a team manager reports that a work package is taking longer than expected. The project manager needs to assess the impact on the project schedule. Which practice should be used to evaluate the effect and determine whether to escalate?

A.Risk
B.Plans
C.Organizing
D.Progress
AnswerD

Progress practice covers monitoring, control, and escalations.

Why this answer

The Progress practice is used to monitor and compare actual achievements against planned performance, and to assess the impact of deviations. When a work package takes longer than expected, the project manager uses Progress to evaluate the effect on the schedule and decide whether to escalate to the project board. This aligns with PRINCE2's principle of managing by stages and using tolerances to control deviations.

Exam trap

PeopleCert often tests the distinction between 'Risk' (managing future uncertainties) and 'Progress' (monitoring actual performance against baselines), leading candidates to incorrectly select Risk when a delay is already occurring.

How to eliminate wrong answers

Option A is wrong because Risk practice focuses on identifying, assessing, and controlling uncertainties that could affect the project, not on evaluating schedule impact from a known delay. Option B is wrong because Plans practice is about defining how, when, and by whom the products are delivered, not about monitoring actual progress or assessing deviations. Option C is wrong because Organizing practice defines roles and responsibilities, not the mechanism for evaluating schedule impact or escalation decisions.

356
MCQeasy

What is the purpose of the Highlight Report?

A.To escalate exceptions
B.To report progress to the Project Board at regular intervals
C.To request changes
D.To report progress to the Team Manager
AnswerB

Correct.

Why this answer

The Highlight Report is produced by the Project Manager for the Project Board at regular intervals to summarize progress and issues.

357
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Project Initiation Documentation
B.The Business Case
C.The Risk Register
D.The Project Plan
AnswerA

The PID is the key output of Initiating a Project.

Why this answer

The Initiating a Project process is where the project's foundations are established, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—including the Business Case, Project Plan, and Risk Register—into a single, coherent document that defines what the project will deliver, why, how, and against what constraints. It serves as the baseline for decision-making and is formally approved before the project proceeds to the next stage.

Exam trap

PeopleCert often tests the distinction between the PID as the overarching output and its individual components (like the Business Case or Project Plan) to see if candidates understand that the PID is the consolidated deliverable, not any single part of it.

How to eliminate wrong answers

Option B is wrong because the Business Case is a component of the Project Initiation Documentation, not the key output of the Initiating a Project process; it is developed and refined during the Starting Up a Project process and updated in Initiating a Project. Option C is wrong because the Risk Register is a management product that is created and maintained throughout the project, but it is not the primary output of Initiating a Project; it is one of many components that feed into the PID. Option D is wrong because the Project Plan is also a component of the PID, not the key output itself; it is produced during the Initiating a Project process but is only one part of the comprehensive PID.

358
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
B.Close the project immediately as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerC

When a stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report. This is management by exception.

Why this answer

According to the management by exception principle, when a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The Project Manager cannot unilaterally increase the budget or ignore the breach.

359
MCQhard

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are synonyms in PRINCE2
B.An Off-specification is always raised by the Project Manager; an RFC is raised by the Project Board
C.An RFC only applies to project products; an Off-specification applies to the Business Case
D.An RFC is a proposal to change a baseline; an Off-specification is a failure to meet a baseline requirement
AnswerD

Correct. RFC proposes a change; Off-specification is a deviation from what was specified.

Why this answer

An Off-specification is something that should be provided but is not (a gap), whereas a Request for Change is a proposal for a change that, if implemented, would alter an approved baseline.

360
MCQeasy

Which role is responsible for ensuring that project assurance is carried out independently of the Project Manager?

A.Project Manager
B.Project Board
C.Team Manager
D.Project Support
AnswerB

Correct. The Project Board is accountable for project assurance and ensures it is independent.

Why this answer

The Project Board members (Executive, Senior User, Senior Supplier) are responsible for project assurance. They delegate assurance tasks but remain accountable. The Project Manager does not perform assurance; that would compromise independence.

361
MCQmedium

A project is experiencing many changes due to evolving requirements. Which document should the Project Manager use to track all requests for change?

A.Risk Register
B.Configuration Item Record
C.Issue Register
D.Quality Register
AnswerC

All issues, including requests for change, are logged in the Issue Register.

Why this answer

The Issue Register records all issues including requests for change, off-specifications, and problems/concerns. The Configuration Item Record tracks product versions, and the Quality Register tracks quality activities.

362
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; they are the same
B.Off-specification is raised by the Project Board; Request for Change by users
C.A Request for Change is always budgeted; Off-specification is not
D.A Request for Change proposes a modification; Off-specification identifies something that is missing or not working
AnswerD

Correct distinction per PRINCE2.

Why this answer

A Request for Change is a proposal for a modification, while an Off-specification is something that should have been provided but is missing or not working.

363
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Increase the project budget and continue
C.Close the project immediately
D.Raise an Exception Report to the Project Board
AnswerD

An Exception Report is raised to the Project Board to decide on corrective action.

Why this answer

Management by exception requires escalation via an Exception Report to the Project Board when a tolerance is forecast to be exceeded.

364
MCQmedium

Which role is responsible for providing independent assurance that the project is being managed correctly?

A.Project Support
B.Project Assurance
C.Team Manager
D.Project Manager
AnswerB

Project Assurance provides independent oversight.

Why this answer

Project Assurance is responsible for independent oversight, ensuring that the project adheres to standards and that the Project Board's interests are protected.

365
MCQmedium

A project is in the Initiating a Project process. The project manager is reviewing the Business Case and notes that the expected benefits are not clearly linked to the project's objectives. Which practice should the project manager use to address this issue?

A.Quality practice
B.Risk practice
C.Business Case practice
D.Plans practice
AnswerC

The Business Case practice ensures the project remains viable and benefits are defined and linked to objectives.

Why this answer

The Business Case practice is responsible for establishing and maintaining the justification for the project, including the link between objectives and expected benefits. During the Initiating a Project process, the Business Case must be refined to ensure that all benefits are clearly traceable to the project's objectives, as this alignment is critical for ongoing viability decisions. The project manager should use the Business Case practice to address this gap by updating the Business Case to explicitly map each benefit to a specific project objective.

Exam trap

PeopleCert often tests the distinction between the Business Case practice (which owns the justification and benefit-objective linkage) and the Plans practice (which owns the schedule and activities), leading candidates to incorrectly choose Plans when the issue is about benefit alignment rather than sequencing.

How to eliminate wrong answers

Option A is wrong because the Quality practice focuses on defining and verifying the quality criteria of products, not on linking benefits to objectives. Option B is wrong because the Risk practice deals with identifying, assessing, and controlling uncertainties that could affect the project, not with ensuring benefit-objective alignment. Option D is wrong because the Plans practice is concerned with defining the sequence of activities, resources, and schedules to deliver the project's products, not with the justification or benefit mapping in the Business Case.

366
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Senior User
B.The Project Assurance
C.The Project Manager
D.The Senior Supplier
AnswerC

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Executive (Senior Responsible Owner) is the owner of the Business Case. The Project Manager maintains (updates) the Business Case on behalf of the Executive.

367
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To plan the next stage and update the Project Plan and Business Case
B.To produce the Project Initiation Documentation
C.To manage the work of the current stage
D.To close the project
AnswerA

Correct. Managing a Stage Boundary produces the next stage plan and updates the PID.

Why this answer

The purpose is to provide the Project Board with sufficient information to review the current stage's performance and approve the next stage plan.

368
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To initiate the project and create the Project Plan
B.To plan the next stage in detail and obtain Project Board approval for the next stage
C.To manage the work of the current stage and report progress
D.To close the project and produce the End Project Report
AnswerB

This is the primary purpose of Managing a Stage Boundary.

Why this answer

The purpose of Managing a Stage Boundary is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification.

369
MCQeasy

Which management product defines the quality criteria and acceptance methods for a product?

A.The Business Case
B.The Project Plan
C.The Quality Register
D.The Product Description
AnswerD

The Product Description defines quality criteria and acceptance methods.

Why this answer

The Product Description defines quality criteria and acceptance methods. Option C is correct.

370
MCQmedium

Which document describes the quality criteria and quality methods to be applied during the project?

A.Quality Register
B.Product Description
C.Project Plan
D.Quality Management Approach
AnswerD

The Quality Management Approach defines the quality procedures, criteria, and methods for the project.

Why this answer

The Quality Management Approach defines the quality management system, including quality criteria and methods. The Product Description defines quality for a specific product. The Quality Register logs quality activities.

The Project Plan includes schedules.

371
MCQeasy

Which document is used to capture and track all identified risks throughout the project?

A.Quality Register
B.Risk Register
C.Configuration Item Record
D.Issue Register
AnswerB

The Risk Register captures and tracks all risks.

Why this answer

The Risk Register is the document used to record and track risks.

372
MCQeasy

Which risk response is appropriate for a threat that the project team decides to eliminate by changing the project approach?

A.Transfer
B.Accept
C.Reduce
D.Avoid
AnswerD

Avoid eliminates the threat by changing the plan.

Why this answer

Avoid is the response where action is taken to eliminate the threat by changing the plan or approach.

373
MCQmedium

During which process are team plans typically created?

A.Managing a Stage Boundary
B.Initiating a Project
C.Directing a Project
D.Managing Product Delivery
AnswerD

Correct. Team plans are created by the team manager in MP.

Why this answer

Team plans are created by the team manager during the Managing Product Delivery process.

374
MCQmedium

Which of the following is a risk response for an opportunity?

A.Transfer
B.Avoid
C.Fallback
D.Enhance
AnswerD

Enhance is a response for opportunities.

Why this answer

In PRINCE2, risk responses for opportunities include exploit, enhance, share, and reject. 'Enhance' is an appropriate response to maximize the probability or impact of an opportunity.

375
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To enable the Project Board to review the current stage and authorize the next
C.To control the work of the current stage
D.To plan the entire project
AnswerB

Correct. The process provides the basis for stage boundary decisions.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve its completion, and authorize the next stage plan. This ensures that the project remains viable and aligned with business justification before committing further resources.

Exam trap

The trap here is confusing the Managing a Stage Boundary process with the Controlling a Stage process, as both involve stage-level activities, but only Managing a Stage Boundary handles the formal end-of-stage review and authorization of the next stage.

How to eliminate wrong answers

Option A is wrong because closing the project is the purpose of the Closing a Project process, not Managing a Stage Boundary. Option C is wrong because controlling the work of the current stage is the purpose of the Controlling a Stage process, which handles day-to-day management and issue resolution. Option D is wrong because planning the entire project is done during the Initiating a Project process, which creates the Project Plan; Managing a Stage Boundary only produces Stage Plans for the next stage.

← PreviousPage 5 of 9 · 674 questions totalNext →

Ready to test yourself?

Try a timed practice session using only Prince2 Practices questions.