A project is forecast to exceed its cost tolerance. What should the Project Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Raise an Exception Report to the Project Board
When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Option B is correct.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Close the project immediately
Why it's wrong here
The Project Board decides whether to close.
- ✓
Raise an Exception Report to the Project Board
Why this is correct
This is management by exception.
- ✗
Report in the next Highlight Report
Why it's wrong here
An Exception Report is needed immediately, not deferred.
- ✗
Increase the project budget and continue
Why it's wrong here
The Project Manager cannot unilaterally increase the budget.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.