Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

In a project using PRINCE2, the project board is reviewing the End Stage Report. They notice that the actual costs are significantly lower than planned, but the scope is complete. What should the project board do?

⚠ Common exam trap

PeopleCert often tests the misconception that being under budget automatically triggers an exception plan or immediate stage authorization, but PRINCE2 requires the project board to formally review the End Stage Report and make a deliberate decision based on continued business justification, not just cost performance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the End Stage Report and decide whether to authorize the next stage

The project board's primary responsibility is to review the End Stage Report and decide whether to authorize the next stage based on continued business justification, not solely on cost performance. Being under budget with scope complete does not automatically trigger an exception plan or immediate authorization; the board must assess the overall viability, risks, and lessons learned before proceeding. Option D correctly reflects the PRINCE2 principle of continued business justification and the board's decision-making authority at stage boundaries.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request an exception plan to reallocate the surplus

    Why it's wrong here

    An exception plan is only needed if tolerance is exceeded; here, costs are under tolerance.

  • Immediately authorize the next stage as the project is under budget

    Why it's wrong here

    The board should first understand the reasons for the under-run before authorizing.

  • Ask the project manager to revise the project plan to increase costs

    Why it's wrong here

    There is no reason to increase costs; the board should understand the variance first.

  • Review the End Stage Report and decide whether to authorize the next stage

    Why this is correct

    The board uses the End Stage Report to review performance and make a decision on the next stage.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.