Start PRINCE2 Practices PracticeWho is responsible for maintaining the Business Case throughout the project?
Explanation: The Project Manager is responsible for maintaining the Business Case throughout the project. This includes updating it with actual progress, costs, and benefits, and ensuring it remains viable. The Executive owns the Business Case and is accountable for it, but the day-to-day maintenance is delegated to the Project Manager.
Which TWO of the following are valid tolerances in PRINCE2?
Explanation: In PRINCE2, the six standard tolerances are Time, Cost, Quality, Scope, Risk, and Benefit. Among the given options, Benefit and Time are two valid tolerances. Resource and Budget are not formal tolerances; they are management levers or plan components. Note that Cost is also a valid tolerance, but the question specifically expects Benefit and Time as the correct pair.
Who is responsible for maintaining the Business Case throughout the project?
Explanation: In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project, including developing and updating it as needed. The Executive (Senior Responsible Owner) owns the Business Case and approves it, but the day-to-day maintenance is the Project Manager's responsibility.
Which of the following is a risk response for an opportunity?
Explanation: In PRINCE2, risk responses for opportunities (positive risks) include Enhance, Exploit, and Share. Enhance is the correct response because it involves proactively increasing the probability and/or impact of an opportunity to maximize its potential benefits. Transfer and Avoid are responses for threats (negative risks), while Fallback is a response for a threat when the primary response fails.
What is the purpose of the Quality Review technique?
Explanation: The Quality Review technique in PRINCE2 is a structured assessment of a product's fitness for purpose. Its primary purpose is to assess the quality of a product and identify any defects, ensuring that the product meets its agreed quality criteria before it is approved. This is a key part of the 'Manage Product Delivery' and 'Quality Management' processes.
+15 more PRINCE2 Practices questions available
Practice all PRINCE2 Practices questions1. Baseline your knowledge
Start with 10 questions to gauge your current understanding of PRINCE2 Practices. This tells you whether you need a concept refresher or just practice.
2. Review every explanation
For each question — right or wrong — read the full explanation. Understanding why an answer is correct is more valuable than knowing the answer itself.
3. Focus on exam traps
PRINCE2 Practices questions on the PRINCE2F frequently use trap wording. Look for subtle differences in answers that test your precision, not just general knowledge.
4. Reach 80% consistently
Do repeated sessions until you score 80%+ three times in a row. Then move to mixed-mode practice to test cross-topic recall under realistic conditions.
The exact number varies per candidate. PRINCE2 Practices is tested as part of the PRINCE2 Foundation blueprint. Practicing with targeted PRINCE2 Practices questions ensures you can handle any format or difficulty that appears.
Yes. Courseiva provides free PRINCE2F practice questions across all exam topics and domains. The platform includes topic-based practice, mock exams, missed-question review, bookmarked questions, and readiness tracking — no account required.
Difficulty is subjective, but PRINCE2 Practices is a high-priority exam concept tested in multiple ways — direct recall, scenario analysis, and command-output interpretation. Consistent practice is the best way to build confidence.
Launch a full PRINCE2 Practices practice session with instant scoring and detailed explanations.
Start PRINCE2 Practices Practice →