PRINCE2F PRINCE2 Practices Practice Question
The Project Manager is reviewing an issue that affects a product currently in development. The product does not meet a requirement defined in its Product Description. What type of issue is this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Off-specification
An Off-specification is something that should be provided but is not (or is provided but does not meet the specification).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Request for Change
Why it's wrong here
A Request for Change proposes a deliberate change to an agreed baseline.
- ✗
Risk
Why it's wrong here
A risk is an uncertain event, not a current issue.
- ✗
Problem/Concern
Why it's wrong here
A Problem/Concern is an issue that is neither a change nor an off-specification.
- ✓
Off-specification
Why this is correct
A product not meeting its specification is an Off-specification.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.