Which THREE of the following are responsibilities of the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Making decisions on exception situations

The Project Board is accountable for the project's success, approves stage plans, and provides direction. The PM manages day-to-day, and assurance is delegated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Performing project assurance activities

    Why it's wrong here

    Assurance is delegated to Project Assurance roles.

  • Making decisions on exception situations

    Why this is correct

    The Board decides on exceptions.

  • Approving stage plans

    Why this is correct

    The Project Board approves Stage Plans.

  • Managing day-to-day activities

    Why it's wrong here

    That is the responsibility of the Project Manager.

  • Providing overall direction and control

    Why this is correct

    The Board provides direction and control.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.