PRINCE2F PRINCE2 Practices Practice Question
Which THREE of the following are responsibilities of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Making decisions on exception situations
The Project Board is accountable for the project's success, approves stage plans, and provides direction. The PM manages day-to-day, and assurance is delegated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Performing project assurance activities
Why it's wrong here
Assurance is delegated to Project Assurance roles.
- ✓
Making decisions on exception situations
Why this is correct
The Board decides on exceptions.
- ✓
Approving stage plans
Why this is correct
The Project Board approves Stage Plans.
- ✗
Managing day-to-day activities
Why it's wrong here
That is the responsibility of the Project Manager.
- ✓
Providing overall direction and control
Why this is correct
The Board provides direction and control.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.