Correct answer & explanation
✓
Checkpoint Report
The Checkpoint Report is a progress report from the Team Manager to the Project Manager, typically produced at a frequency defined in the Work Package. Highlight Reports go from PM to Project Board. Exception Reports are for tolerance breaches. End Stage Reports are at stage end.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Highlight Report
Why it's wrong here
Highlight Reports are from the Project Manager to the Project Board.
- ✓
Checkpoint Report
Why this is correct
Checkpoint Reports are from the Team Manager to the Project Manager, detailing progress on a Work Package.
- ✗
Exception Report
Why it's wrong here
Exception Reports are triggered by tolerance breaches, not routine progress.
- ✗
End Stage Report
Why it's wrong here
End Stage Reports are produced at the end of a stage by the Project Manager.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which report is produced by the Team Manager to inform the Project Manager about progress against a Work Package?
medium- ✓ A.Checkpoint Report
- B.End Stage Report
- C.Exception Report
- D.Highlight Report
Why A: A Checkpoint Report is produced by the Team Manager to provide the Project Manager with progress details on a Work Package at regular intervals.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.