Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which report is produced by the Team Manager to inform the Project Manager about progress on a Work Package?

⚠ Common exam trap

PRINCE2F often tests the specific roles and responsibilities for reports, causing candidates to confuse who produces which report and for whom.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Checkpoint Report

In PRINCE2, the Team Manager produces a Checkpoint Report to inform the Project Manager about the status of a Work Package, including progress, issues, and next steps. This report is provided at frequency defined in the Work Package and feeds into the Highlight Report. The Checkpoint Report is specifically designed for progress monitoring within a stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Highlight Report

    Why it's wrong here

    Highlight Reports flow from the Project Manager to the Project Board at stage boundaries, not from the Team Manager about a Work Package. Checkpoint Reports serve that Team Manager to Project Manager progress communication; Highlight Reports suit board-level stage progress.

  • ✓

    Checkpoint Report

    Why this is correct

    The Team Manager produces Checkpoint Reports at agreed intervals to update the Project Manager on Work Package progress, covering status, issues and next actions. This satisfies the stem's requirement for the specific report flowing from Team Manager to Project Manager within PRINCE2's controlling a stage cycle.

  • ✗

    Exception Report

    Why it's wrong here

    An Exception Report is raised by the Project Manager to the Project Board when tolerances are forecast to be exceeded, not by the Team Manager. Checkpoint Reports carry Work Package progress; Exception Reports suit board-level escalation of deviations.

  • ✗

    End Stage Report

    Why it's wrong here

    An End Stage Report is produced by the Project Manager for the Project Board at the end of a stage, summarising performance. It is not a Team Manager's Work Package progress update; Checkpoint Reports fill that role during delivery.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which report is produced by the Team Manager to inform the Project Manager about progress against a Work Package?

medium
  • ✓ A.Checkpoint Report
  • B.End Stage Report
  • C.Exception Report
  • D.Highlight Report

Why A: A Checkpoint Report is produced by the Team Manager and given to the Project Manager at the frequency defined in the Work Package. It reports progress, status, and any issues against the Work Package, enabling the Project Manager to monitor the stage. It is the standard mechanism for Team Manager-to-Project Manager progress communication.

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.