Correct answer & explanation
✓
To prepare the Stage Plan for the next stage and update the Business Case
The purpose is to provide the Project Board with information to assess the viability of the project and authorize the next stage.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
To prepare the Stage Plan for the next stage and update the Business Case
Why this is correct
Managing a Stage Boundary produces the next Stage Plan and updates the Business Case for Board approval.
- ✗
To control the work of the current stage
Why it's wrong here
Controlling a Stage is the process for ongoing management.
- ✗
To close the project
Why it's wrong here
Closing a Project is a separate process.
- ✗
To authorize work on the current stage
Why it's wrong here
That is done in Directing a Project.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.