Courseiva

CCNA Prince2 Practices Questions

75 of 596 questions · Page 7/8 · Prince2 Practices topic · Answers revealed

451
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To update the Business Case based on the latest stage performance
B.To enable the Project Board to review the current stage, approve the next stage plan, and confirm continued business justification
C.To plan the next stage and update the Project Plan
D.To produce the End Project Report
AnswerB

This is the correct definition of the purpose of Managing a Stage Boundary.

Why this answer

The purpose of the Managing a Stage Boundary process is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification. Option A is wrong because the Business Case is reviewed, not updated, during this process. Option C is wrong because the next stage plan is created in this process, not merely planned.

Option D is wrong because the End Project Report is produced in the Closing a Project process, not here.

452
Multi-Selectmedium

Which TWO of the following are typical responsibilities of the Project Board?

Select 2 answers
A.Authorizing the start of each stage
B.Defining the project's acceptance criteria
C.Providing day-to-day management of the project
D.Approving the Project Plan
E.Providing independent assurance
AnswersA, D

The Project Board authorizes stage starts based on stage plans.

Why this answer

The Project Board is responsible for authorizing the start of each stage, including the initiation stage, by approving the Stage Plan and committing the required resources. This ensures that management stage boundaries are formally controlled and that the project remains aligned with the business case. Option D is correct because the Project Board approves the Project Plan (the overall plan for the project) to confirm that it is viable and consistent with the business case before the project proceeds.

Exam trap

PRINCE2 often tests the distinction between 'defining' and 'approving' acceptance criteria, and between 'providing assurance' and 'being the board' — candidates mistakenly assign definition and assurance tasks to the Project Board when they actually belong to the Senior User and Project Assurance, respectively.

453
MCQmedium

Which document is produced during the Initiating a Project process and provides a baseline against which the project's progress can be measured?

A.The Project Plan
B.The Project Brief
C.The Business Case
D.The Project Initiation Documentation (PID)
AnswerD

The PID is the comprehensive baseline document created during Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process and serves as the baseline for the project.

454
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
B.Raise an Exception Report to the Project Board and await their direction before proceeding
C.Close the project immediately as the Business Case is no longer viable
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerB

When a tolerance is forecast to be exceeded, the PM must escalate via an Exception Report.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is the principle of management by exception.

455
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Design the Risk Management Approach
B.Produce Highlight Reports
C.Approve Stage Plans
D.Provide assurance
E.Manage Work Packages
AnswersC, D

The Project Board approves Stage Plans.

Why this answer

The Project Board is responsible for approving Stage Plans (Option C) because it provides the necessary authority for the Project Manager to proceed with the next stage of work. This approval ensures that the project remains aligned with the business case and tolerances set by the board. The board also has a key responsibility to provide assurance (Option D) that the project is being managed correctly and that risks are being controlled, which is a core governance function in PRINCE2.

Exam trap

PRINCE2 often tests the distinction between approval and execution responsibilities, so candidates mistakenly assign operational tasks like producing reports or managing work packages to the Project Board instead of the Project Manager or Team Manager.

456
MCQhard

A project manager is creating the project product description. Which practice does this document belong to?

A.Business Case practice
B.Plans practice
C.Risk practice
D.Quality practice
AnswerD

This is correct. The project product description defines the product's quality criteria, acceptance methods, and quality expectations, which are core elements of the Quality practice.

Why this answer

The project product description belongs to the Quality practice because it defines the product's quality criteria, quality tolerances, acceptance methods, and quality responsibilities. It is used to ensure that the project's outputs meet the required quality standards and is a key input to the quality management approach.

Exam trap

PeopleCert often tests the distinction between the project product description and the quality management approach, leading candidates to incorrectly associate it with the Quality practice instead of the Business Case practice.

How to eliminate wrong answers

Option B (Plans practice) is wrong because the project product description is not a plan; it describes the final product, whereas the Plans practice focuses on defining how and when the project's objectives will be achieved through management and delivery plans. Option C (Risk practice) is wrong because the project product description does not address risk identification, assessment, or response planning; those are handled in the risk register and risk management approach. Option D (Quality practice) is wrong because while the project product description includes quality expectations and acceptance criteria, it is not a quality management document itself; the Quality practice is governed by the quality management approach and quality register.

457
MCQhard

Which of the following is NOT an opportunity response in PRINCE2?

A.Enhance
B.Exploit
C.Avoid
D.Share
AnswerC

Avoid is a threat response.

Why this answer

Avoid is a threat response, not an opportunity response. The opportunity responses are exploit, enhance, share, and reject.

458
MCQmedium

In the product-based planning approach, what is the purpose of the Product Breakdown Structure (PBS)?

A.To define the quality criteria for each product
B.To show the order in which products will be created
C.To provide the cost estimate for each product
D.To identify all the products needed for the project
AnswerD

The PBS provides a complete list of all deliverables in a hierarchical structure.

Why this answer

The PBS is a hierarchical decomposition of all products to be created. It helps identify all deliverables. The Product Flow Diagram shows dependencies, and Product Descriptions define quality criteria.

The Project Plan is not a direct output of the PBS.

459
MCQmedium

Which PRINCE2 management product is used to capture lessons throughout the project?

A.End Project Report
B.Quality Register
C.Lessons Log
D.Lessons Report
AnswerC

The Lessons Log captures lessons continuously.

Why this answer

The Lessons Log is the PRINCE2 management product specifically designed to capture lessons as they occur throughout the project lifecycle. It is a dynamic repository where the project team records both positive and negative experiences, ensuring that lessons are not lost and can be reviewed at key points, such as stage boundaries and project closure.

Exam trap

The trap here is that candidates often confuse the Lessons Log (the ongoing capture tool) with the Lessons Report (the formal summary), leading them to select the Lessons Report as the product used throughout the project.

How to eliminate wrong answers

Option A is wrong because the End Project Report is produced at project closure to summarize performance and provide a final assessment, not to capture lessons continuously during the project. Option B is wrong because the Quality Register records quality activities and results, such as inspections and audits, not lessons learned. Option D is wrong because the Lessons Report is a formal document created at the end of a stage or the project, summarizing key lessons from the Lessons Log, but it is not the product used for ongoing capture.

460
MCQeasy

In PRINCE2, who is responsible for the Business Case?

A.The Senior Supplier
B.The Project Manager
C.The Senior User
D.The Executive
AnswerD

The Executive owns the Business Case in PRINCE2, as defined by the management-by-stage principle and the business justification theme. This satisfies the constraint that the Business Case must have a single, accountable owner who is ultimately responsible for ensuring the project remains viable and aligned with corporate objectives.

Why this answer

The Executive is the single individual responsible for the Business Case in PRINCE2. They own the project's justification and ensure it remains viable throughout the project lifecycle, approving any changes that affect its viability. The Business Case is the Executive's primary accountability, as defined in the PRINCE2 manual.

Exam trap

The trap here is that candidates often confuse the Project Manager's role in maintaining the Business Case with ownership, but PRINCE2 explicitly assigns accountability to the Executive, not the manager who writes or updates it.

How to eliminate wrong answers

Option A is wrong because the Senior Supplier represents the supplier's interests and is responsible for the quality of products, not the Business Case. Option B is wrong because the Project Manager manages the day-to-day creation and maintenance of the Business Case document but does not own it; accountability rests with the Executive. Option C is wrong because the Senior User represents the users' needs and is responsible for specifying benefits, but the overall Business Case ownership belongs to the Executive.

461
MCQmedium

Which risk response is appropriate for a threat that the project team decides to proactively manage by reducing the probability or impact?

A.Reduce
B.Avoid
C.Transfer
D.Accept
AnswerA

Reduce means taking action to lower probability or impact.

Why this answer

Reduce is the correct risk response because it involves implementing actions to lower the probability or impact of a threat while still accepting that the risk may occur. In PRINCE2, this is a proactive response where the project team actively manages the risk by, for example, adding redundancy or conducting more frequent testing to decrease the likelihood of failure. The key is that the risk is not eliminated entirely but its effects are mitigated.

Exam trap

In PRINCE2, the Reduce response is proactive but does not eliminate the risk, whereas Avoid eliminates the threat entirely. Candidates often confuse 'proactive management' with 'avoidance,' but Avoid means changing the plan to remove the risk source, not just reducing it.

How to eliminate wrong answers

Option B is wrong because Avoid is a risk response that involves changing the project plan to eliminate the threat entirely, such as by removing a high-risk feature, not by reducing its probability or impact. Option C is wrong because Transfer shifts the financial impact of a threat to a third party (e.g., through insurance or a fixed-price contract), but does not reduce the probability or impact of the risk itself. Option D is wrong because Accept means the project team acknowledges the threat and takes no proactive action, either because the risk is low or because the cost of mitigation is too high, which contradicts the proactive reduction described in the question.

462
MCQmedium

Which risk response is appropriate for a threat that can be mitigated by transferring the financial impact to a third party?

A.Avoid
B.Reduce
C.Transfer
D.Accept
AnswerC

Correct. Transfer shifts the financial impact.

Why this answer

Transfer involves shifting the financial impact of a risk to a third party, e.g., through insurance or contract.

463
MCQhard

Which of the following describes the relationship between Project Assurance and Project Support?

A.Project Assurance is independent; Project Support provides admin services
B.Project Assurance reports to the Project Manager; Project Support reports to the Project Board
C.Project Assurance and Project Support are the same role
D.Project Assurance is part of Project Support
AnswerA

Correct. Assurance is independent from management; support is administrative.

Why this answer

Project Assurance is an independent role that provides objective oversight to ensure the project remains viable and compliant with PRINCE2 principles, while Project Support is an administrative role that handles tasks like planning tools, filing, and configuration management. The independence of Project Assurance from the Project Manager is critical to avoid conflicts of interest, whereas Project Support serves the Project Manager and the team. This separation ensures that assurance activities are unbiased and that support services are efficient.

Exam trap

The trap here is that candidates confuse the reporting lines and independence of Project Assurance, mistakenly thinking it reports to the Project Manager or is part of Project Support, when in fact PRINCE2 mandates that Project Assurance must be independent and report to the Project Board.

How to eliminate wrong answers

Option B is wrong because Project Assurance reports to the Project Board, not the Project Manager, and Project Support reports to the Project Manager, not the Project Board. Option C is wrong because Project Assurance and Project Support are distinct roles with different objectives: assurance provides independent oversight, while support provides administrative services. Option D is wrong because Project Assurance is not a subset of Project Support; they are separate functions, and combining them would compromise the independence required for assurance.

464
MCQeasy

According to PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.The Executive
B.The Project Manager
C.The Project Assurance
D.The Senior User
AnswerB

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case (keeping it up to date), while the Executive owns it and is accountable for its justification.

465
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Executive
C.Project Manager
D.Senior User
AnswerC

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, monitor progress against the Business Case, and update it as necessary to reflect changes in costs, benefits, and risks. PRINCE2 assigns this responsibility to the Project Manager to ensure the Business Case remains viable and aligned with project objectives at all times.

Exam trap

The trap here is confusing the Executive's ownership and accountability for the Business Case with the Project Manager's responsibility for its ongoing maintenance and updates.

How to eliminate wrong answers

Option A is wrong because Project Assurance is an independent check function that reviews the Business Case for compliance and viability, but does not maintain it. Option B is wrong because the Executive owns the Business Case and is accountable for its approval and sign-off, but the day-to-day maintenance is delegated to the Project Manager. Option D is wrong because the Senior User represents the users' interests and specifies benefits, but does not maintain the Business Case document.

466
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.An RFC is raised by the Project Board, while an Off-specification is raised by the Project Manager.
B.An RFC is always approved by the Change Authority, while an Off-specification is approved by the Project Board.
C.An RFC is a change to an approved baseline, while an Off-specification is a deviation from a requirement.
D.An Off-specification can be resolved by concession, while an RFC cannot.
AnswerC

An RFC proposes a change to an approved baseline; an Off-specification is a failure to meet a specified requirement.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify an approved baseline (e.g., a product description, plan, or schedule), whereas an Off-specification is a formal notification that a product or component does not meet its specified requirements or quality criteria. The core distinction lies in the nature of the issue: an RFC seeks to change what was agreed, while an Off-specification reports a failure to deliver what was agreed.

Exam trap

PeopleCert often tests the confusion between 'change to a baseline' (RFC) and 'failure to meet a requirement' (Off-specification), trapping candidates who focus on who raises or approves the issue rather than the fundamental nature of the problem.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specifications can be raised by anyone with a justified need, not exclusively by the Project Board or Project Manager; the Project Board typically approves major changes, but the raising of these issues is not restricted by role. Option B is wrong because the approval authority for an RFC depends on its impact and the delegated Change Authority, not a blanket rule that all RFCs are approved by the Change Authority; similarly, Off-specifications are not always approved by the Project Board—they may be resolved by concession or corrective action without Board involvement. Option D is wrong because an Off-specification can indeed be resolved by concession (accepting the deviation as is), but an RFC can also be resolved by concession if the change is accepted without full implementation; both can be closed via concession under appropriate circumstances.

467
Multi-Selectmedium

Which TWO of the following are valid tolerances in PRINCE2?

Select 2 answers
A.Customer satisfaction
B.Risk
C.Innovation
D.Quality
E.Resources
AnswersB, D

Yes, risk tolerance is defined.

Why this answer

In PRINCE2, tolerances are predefined limits for deviations in plan performance, and the six standard tolerances are Time, Cost, Quality, Scope, Risk, and Benefit. Option B (Risk) is correct because risk tolerance defines the acceptable level of risk exposure for a project, allowing the project manager to manage within that threshold without escalating. Option D (Quality) is correct because quality tolerance sets the acceptable deviation from specified quality criteria, ensuring deliverables meet agreed standards.

Exam trap

The trap here is that candidates confuse 'resources' (a common project management term) with a PRINCE2 tolerance, but PRINCE2 explicitly defines only six tolerances, and resources are managed under Cost and Scope, not as a separate tolerance.

468
MCQmedium

Which report is prepared by the Team Manager and sent to the Project Manager at regular intervals?

A.End Stage Report
B.Exception Report
C.Highlight Report
D.Checkpoint Report
AnswerD

The Checkpoint Report provides progress information from the Team Manager to the Project Manager.

Why this answer

The Checkpoint Report is a progress report prepared by the Team Manager and sent to the Project Manager at regular intervals. Option A is incorrect because the End Stage Report is prepared by the Project Manager for the Project Board at the end of each stage. Option B is incorrect because the Exception Report is prepared by the Project Manager when tolerances are forecast to be exceeded.

Option C is incorrect because the Highlight Report is prepared by the Project Manager for the Project Board at regular intervals.

469
MCQmedium

Who receives Highlight Reports?

A.Project Board
B.Senior Supplier
C.Project Support
D.Team Manager
AnswerA

The Project Board receives Highlight Reports from the Project Manager.

Why this answer

Highlight Reports are prepared by the Project Manager and sent to the Project Board (and possibly stakeholders) at regular intervals.

470
Multi-Selecthard

Which THREE of the following are components of a Product Description?

Select 3 answers
A.Purpose
B.Derivation
C.Quality criteria
D.Benefits
E.Cost
AnswersA, B, C

Purpose is a component of a Product Description.

Why this answer

'Purpose' is a mandatory component of a Product Description in PRINCE2. It describes what the product is intended to do and why it is needed, providing clarity on its role within the project's output. This aligns with the PRINCE2 principle of continued business justification, ensuring every product has a defined reason for existence.

Exam trap

PRINCE2 often tests the misconception that 'Benefits' or 'Cost' are part of a Product Description, confusing it with the Business Case or Project Plan, but PRINCE2 strictly separates product specification from financial justification and benefits realization.

471
MCQmedium

Which document defines the quality criteria and acceptance methods for a project's products?

A.Product Description
B.Quality Management Approach
C.Business Case
D.Project Plan
AnswerA

Product Descriptions define quality criteria, acceptance methods, and other product-specific details.

Why this answer

The Product Description defines the quality criteria, acceptance methods, and other details for each product. The Quality Management Approach defines the overall quality strategy, not the specific criteria for individual products.

472
MCQmedium

The project's risk appetite has been defined as 'cautious'. A high-impact opportunity with low probability is identified. What is the most likely response?

A.Enhance
B.Share
C.Reject
D.Exploit
AnswerC

Reject is appropriate for cautious appetite when opportunity risk is not acceptable.

Why this answer

A cautious appetite means risk-averse; even low probability opportunities may be rejected if they carry risk.

473
MCQmedium

In PRINCE2, who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Project Manager
C.Project Board
D.Project Assurance
AnswerD

Project Assurance is a defined PRINCE2 role, separate from the Project Manager and the Project Board, specifically tasked with providing independent assurance that the project remains aligned with its business justification and is conducted properly according to PRINCE2 principles and tolerances. This satisfies the stem’s requirement for a role explicitly responsible for monitoring compliance and governance, not for managing or directing the project.

Why this answer

Project Assurance is an independent role that ensures the project remains aligned with business, user, and supplier interests.

474
MCQhard

In the risk management procedure, what is the difference between a risk owner and a risk actionee?

A.Risk owner identifies risks; risk actionee assesses them
B.Risk owner manages the risk overall; risk actionee performs specific actions
C.Risk owner is the same as risk actionee in PRINCE2
D.Risk owner is on the Project Board; risk actionee is a team member
AnswerB

Correct. The owner has overall accountability; the actionee executes tasks.

Why this answer

In PRINCE2's risk management procedure, the risk owner is responsible for managing, monitoring, and controlling all aspects of a risk, including ensuring that appropriate responses are implemented. The risk actionee, on the other hand, is assigned to carry out specific risk response actions. Option B correctly captures this distinction: the risk owner manages the risk overall, while the risk actionee performs specific actions.

Exam trap

The trap here is that candidates often confuse the risk owner with the risk actionee, assuming they are interchangeable or that the risk owner must be a senior stakeholder like a Project Board member, when in fact PRINCE2 explicitly separates these roles to clarify accountability and execution responsibilities.

How to eliminate wrong answers

Option A is wrong because the risk owner does not solely identify risks; risk identification is a shared activity involving the project manager and team, and the risk actionee does not assess risks—assessment is done by the risk owner with support from the project manager. Option C is wrong because the risk owner and risk actionee are distinct roles in PRINCE2; they are not the same, as the risk owner has overall accountability while the risk actionee executes specific tasks. Option D is wrong because the risk owner is not necessarily on the Project Board; the risk owner can be any competent individual (e.g., a team member or subject matter expert), and the risk actionee is not limited to being a team member—they could be external specialists or suppliers.

475
MCQmedium

What is the difference between a Highlight Report and a Checkpoint Report?

A.The Highlight Report is used to escalate exceptions, while the Checkpoint Report is for routine communication
B.The Highlight Report is produced only at stage boundaries, while the Checkpoint Report is produced weekly
C.The Highlight Report is from the Project Manager to the Project Board, while the Checkpoint Report is from the Team Manager to the Project Manager
D.The Highlight Report focuses on risks and issues, while the Checkpoint Report focuses on product quality
AnswerC

This correctly identifies the reporting hierarchy.

Why this answer

In PRINCE2, the Highlight Report is produced by the Project Manager and sent to the Project Board to provide a summary of stage progress, while the Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report on work package progress. Option A is wrong because the Exception Report (not Highlight Report) is used to escalate exceptions. Option B is wrong because the Highlight Report is typically produced at regular intervals during a stage (e.g., weekly), not only at stage boundaries.

Option D is wrong because both reports cover progress, risks, and issues; the focus difference is on audience and level of detail.

476
MCQeasy

In PRINCE2, who is responsible for project assurance?

A.The Project Manager
B.The Senior Supplier
C.The Project Support
D.The Project Board
AnswerD

Correct. The Project Board is responsible for assurance.

Why this answer

Project assurance is the responsibility of the Project Board, which provides independent assurance.

477
Multi-Selectmedium

Which TWO of the following are components of a Business Case?

Select 2 answers
A.Major risks
B.Project organization structure
C.Work Breakdown Structure
D.Expected benefits
E.Quality criteria
AnswersA, D

Risks are included.

Why this answer

A Business Case in PRINCE2 must include the justification for the project, which requires an assessment of the major risks that could affect the viability of the project. Expected benefits are also a core component, as they define the measurable improvements that the project is expected to deliver, forming the basis for the cost-benefit analysis.

Exam trap

The trap here is that candidates often confuse the components of the Business Case with elements from other PRINCE2 themes, such as the Project Organization structure (Organization theme) or Quality criteria (Quality theme), leading them to select incorrect options like B or E.

478
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are the same thing
B.An RFC is raised by the Project Manager; an Off-specification is raised by the Team Manager
C.An RFC requires a change budget; an Off-specification does not
D.An RFC concerns a desired change to an approved specification; an Off-specification is a product that does not meet its specification
AnswerD

This is the correct distinction.

Why this answer

A Request for Change (RFC) is a formal proposal to modify an approved baseline product or process, while an Off-specification is a product that has been identified as not meeting its agreed specification. The key distinction is that an RFC seeks to change the specification itself, whereas an Off-specification indicates a deviation from an already-approved specification that must be resolved.

Exam trap

The trap here is that candidates confuse the purpose of an RFC (changing the specification) with an Off-specification (product not meeting the specification), often assuming they are interchangeable or that only certain roles can raise them.

How to eliminate wrong answers

Option A is wrong because an RFC and an Off-specification are fundamentally different concepts: one is a proposal for change, the other is a product defect. Option B is wrong because both an RFC and an Off-specification can be raised by any project role (e.g., Project Manager, Team Manager, or even a Senior User) depending on the issue; PRINCE2 does not restrict raising to a specific role. Option C is wrong because an Off-specification may also require a change budget if the resolution involves a change to the specification or additional work, and an RFC does not always require a change budget if it is within the project's existing tolerances.

479
MCQhard

A risk has been identified that could cause a delay to the project. The project team decides to purchase insurance to cover the financial impact. Which risk response type is this?

A.Transfer
B.Avoid
C.Accept
D.Reduce
AnswerA

Insurance transfers the financial impact to an insurer.

Why this answer

Transferring the financial impact to a third party (insurance) is a 'transfer' response. 'Reduce' would involve actions to lower probability or impact. 'Accept' would be to take the risk without action.

480
Multi-Selectmedium

Which TWO of the following are steps in the PRINCE2 risk management procedure?

Select 2 answers
A.Monitor
B.Implement
C.Assess
D.Control
E.Allocate
AnswersB, C

Implement is a correct step; it involves executing the planned risk responses.

Why this answer

Options B and C are correct. The PRINCE2 risk management procedure consists of five steps: Identify, Assess, Plan, Implement, and Communicate. 'Assess' involves evaluating the probability and impact of risks, while 'Implement' involves executing the planned risk responses. 'Monitor' and 'Control' are not separate steps in the procedure; they are activities that occur within the 'Communicate' and 'Implement' steps, respectively.

481
MCQhard

A project is using the PRINCE2 product-based planning technique. Which of the following describes the correct sequence of activities?

A.Create Product Breakdown Structure, then Product Flow Diagram, then Product Descriptions
B.Create Product Flow Diagram, then Product Descriptions, then Product Breakdown Structure
C.Write Project Product Description, create Product Descriptions, then Product Breakdown Structure
D.Write Project Product Description, create Product Breakdown Structure, create Product Flow Diagram, then produce Product Descriptions
AnswerD

This is the correct order per PRINCE2.

Why this answer

The PRINCE2 product-based planning technique starts with the Project Product Description, which defines the final product. Next, you create the Product Breakdown Structure (PBS) to decompose the project product into its component products. Then, you develop the Product Flow Diagram (PFD) to show the order of creation and dependencies.

Finally, you produce Product Descriptions for each component product to detail their purpose, composition, and quality criteria. Option D correctly follows this sequence.

Exam trap

The trap here is that candidates often confuse the order of the Product Breakdown Structure and Product Flow Diagram, mistakenly thinking the flow diagram comes first because it resembles a process map, whereas PRINCE2 requires the product hierarchy to be defined before the flow.

How to eliminate wrong answers

Option A is wrong because it omits the initial step of writing the Project Product Description, which is the foundation for all subsequent product planning. Option B is wrong because it starts with the Product Flow Diagram before defining the product hierarchy via the PBS, which violates the logical top-down decomposition. Option C is wrong because it skips the Product Flow Diagram, which is essential for understanding the sequence and dependencies between products before writing their descriptions.

482
MCQhard

During the Managing a Stage Boundary process, the Project Manager reviews the Business Case and finds that the expected benefits are no longer achievable. What should the Project Manager do?

A.Create an Exception Plan to revise the benefits
B.Continue with the next stage as planned and report the issue in the End Project Report
C.Recommend to the Project Board that the project should be closed as the Business Case is no longer viable
D.Close the project immediately without consulting the Project Board
AnswerC

The Project Manager should escalate to the Project Board, which may decide to close the project.

Why this answer

If the Business Case is no longer viable, the Project Manager should recommend to the Project Board that the project should be closed. The Project Board makes the final decision, not the Project Manager. Option A is incorrect because an Exception Plan is for handling tolerance deviations, not for a failed Business Case.

Option B is incorrect because continuing as planned would ignore the loss of viability. Option D is incorrect because the Project Manager cannot unilaterally close the project; the Board must decide.

483
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue with the current plan and report the cost overrun in the next Highlight Report
B.Raise an Exception Report to the Project Board and await their direction
C.Increase the project budget to absorb the additional cost and continue with the current plan
D.Close the project immediately as the Business Case is no longer viable
AnswerB

This is the correct escalation procedure.

Why this answer

In PRINCE2, when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits; exceeding them requires board-level decision-making. Option B correctly follows the PRINCE2 exception management process, ensuring the board can assess the impact on the Business Case and authorize corrective action.

Exam trap

PRINCE2 often tests the misconception that the Project Manager can handle tolerance breaches independently or defer reporting, but PRINCE2 mandates immediate escalation to the Project Board via an Exception Report when tolerances are forecast to be exceeded.

How to eliminate wrong answers

Option A is wrong because continuing with the current plan and reporting the cost overrun in the next Highlight Report violates the PRINCE2 principle of management by exception—tolerance breaches must be escalated immediately, not deferred. Option C is wrong because the Project Manager cannot unilaterally increase the project budget; budget authority rests with the Project Board, and doing so would bypass governance controls. Option D is wrong because closing the project immediately is premature; the Business Case may still be viable if the board approves a revised budget or scope, and the decision to close is a board responsibility, not the Project Manager's.

484
Multi-Selectmedium

Which THREE of the following are typical response strategies for a threat (negative risk) in PRINCE2?

Select 3 answers
A.Share
B.Avoid
C.Reduce
D.Transfer
E.Exploit
AnswersA, B, C

Correct. Share is a valid threat response where responsibility is shared with another party.

Why this answer

In PRINCE2, the typical response strategies for a threat (negative risk) include Avoid, Reduce, Transfer, and Share. Option A (Share) is correct as it involves collaborating with another party to manage the threat. Option B (Avoid) is correct by eliminating the threat.

Option C (Reduce) is correct by lowering probability or impact. Option D (Transfer) is also a threat response, but since the question asks for THREE, the set of A, B, C is correct. Share is often confused as only an opportunity response, but in PRINCE2, it can be used for threats as well.

Exam trap

A common trap is assuming Share is only for opportunities. In PRINCE2, Share can also be used for threats, especially when collaborating with a third party.

485
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
D.Close the project immediately as the Business Case is no longer viable
AnswerA

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally exceed tolerances (C), continue without escalation (B), or close the project without Board decision (D).

486
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board?

Select 3 answers
A.Providing overall direction and control
B.Managing risks on a daily basis
C.Approving the Project Plan
D.Producing Highlight Reports
E.Ensuring project assurance is carried out
AnswersA, C, E

The Project Board provides overall direction.

Why this answer

The Project Board is responsible for providing overall direction and control of the project, ensuring it remains aligned with business objectives and governance requirements. This includes making key decisions, approving major deliverables, and authorizing stage transitions as defined in PRINCE2's management by stages principle.

Exam trap

PRINCE2 often tests the distinction between strategic oversight (Project Board) and operational execution (Project Manager), leading candidates to mistakenly assign daily risk management or reporting duties to the Board.

487
MCQmedium

A project manager is reviewing the business case for a new product development project. The project board has expressed concern that the benefits may not be realized as planned. Which management product should the project manager update to address this concern?

A.Benefits Management Approach
B.Business Case
C.Project Plan
D.Risk Register
AnswerA

This approach defines how benefits will be measured and reviewed, addressing the board's concern.

Why this answer

The Benefits Management Approach defines how the project's benefits will be measured, tracked, and realized throughout the project and into operations. Since the project board is concerned about benefits realization, updating this approach with revised measurement criteria, review timing, or ownership details directly addresses their concern by providing a clear plan for ensuring benefits are achieved.

Exam trap

The trap here is that candidates often confuse the Business Case (which justifies the project) with the Benefits Management Approach (which manages how benefits are tracked and realized), leading them to incorrectly select the Business Case when the question specifically asks about addressing realization concerns.

How to eliminate wrong answers

Option B is wrong because the Business Case documents the justification for the project, including costs, benefits, and risks, but it does not detail the ongoing management and measurement of benefits realization; updating it would not provide the specific tracking plan needed. Option C is wrong because the Project Plan focuses on the schedule, resources, and activities to deliver the project's products, not on how benefits will be realized after delivery. Option D is wrong because the Risk Register captures individual risks and their responses, but benefits realization is a broader management concern that requires a dedicated approach document, not just a risk entry.

488
Multi-Selecthard

Which THREE of the following are types of issue defined in PRINCE2?

Select 3 answers
A.Request for Change
B.Problem/Concern
C.Risk
D.Off-specification
E.Change request
AnswersA, B, D

An RFC is a formal proposal for a change.

Why this answer

PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. Therefore, options A, B, and D are correct. Option C is a risk, not an issue, and option E is effectively the same as option A but under a different name; PRINCE2 uses the term 'Request for Change' specifically, so 'Change request' is not a recognized issue type.

489
MCQmedium

Based on the exhibit, what is the current risk exposure of risk R1?

A.Low
B.Very High
C.Medium
D.High
AnswerC

(Medium) is correct because the product of Medium probability (0.5) and Medium impact (0.5) is 0.25, which according to the PRINCE2 risk matrix corresponds to Medium exposure.

Why this answer

Risk exposure is calculated as the product of probability and impact. In the exhibit, risk R1 has a probability of 'Medium' (0.3–0.7) and an impact of 'Medium' (0.3–0.7). Multiplying the midpoints (0.5 × 0.5 = 0.25) or using the ranges, the resulting exposure falls within the 'Medium' category on the PRINCE2 risk matrix.

Therefore, the current risk exposure is correctly identified as Medium.

Exam trap

The trap here is that candidates often confuse the individual probability or impact rating with the combined risk exposure, mistakenly selecting 'High' or 'Very High' when only one factor is elevated, or 'Low' when both are medium, instead of correctly calculating the product.

How to eliminate wrong answers

Option A is wrong because 'Low' would require both probability and impact to be low (e.g., 0.1–0.3 each), but R1 has medium probability and medium impact. Option B is wrong because 'Very High' requires both probability and impact to be very high (e.g., 0.9–1.0 each), which is not the case for R1. Option D is wrong because 'High' would require at least one factor to be high (e.g., 0.7–0.9) and the other medium or high, but R1 has both factors at medium, yielding a medium exposure.

490
Multi-Selecthard

Which THREE of the following are valid threat responses in PRINCE2?

Select 3 answers
A.Enhance
B.Exploit
C.Reduce
D.Avoid
E.Transfer
AnswersC, D, E

Reduce is a threat response to lower the probability or impact.

Why this answer

In PRINCE2, threat responses are actions taken to address negative risks. 'Reduce' (also called 'Mitigate') is a valid response that aims to lower the probability and/or impact of a threat to an acceptable level. This is one of the five standard threat response categories defined in the PRINCE2 risk management practice.

Exam trap

PeopleCert often tests the confusion between threat and opportunity responses, where candidates mistakenly select 'Enhance' or 'Exploit' as valid threat responses because they sound like proactive actions, but PRINCE2 strictly reserves them for positive risks.

491
Multi-Selecteasy

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Project Plan
B.Expected benefits
C.Product Breakdown Structure
D.Quality Register
E.Major risks
AnswersB, E

Benefits are a key component.

Why this answer

The Business Case includes expected benefits, costs, timescales, major risks, etc. Options, investment appraisal, and dis-benefits are also components.

492
MCQmedium

What is the purpose of a Checkpoint Report?

A.To document lessons learned
B.To report progress of a Work Package from the Team Manager to the Project Manager
C.To inform the Project Board of stage progress
D.To escalate issues to the Project Board
AnswerB

Checkpoint Reports are team-level reports from Team Manager to PM.

Why this answer

The Checkpoint Report is a PRINCE2 management product used by the Team Manager to report progress of a Work Package to the Project Manager. Its purpose is to provide regular, detailed progress updates on the work being performed by the team, ensuring the Project Manager can monitor delivery against the Work Package plan. This is distinct from higher-level reports like the End Stage Report or Highlight Report.

Exam trap

PeopleCert often tests the distinction between reports directed at different management levels; the trap here is confusing the Checkpoint Report (team-level to Project Manager) with the Highlight Report (Project Manager to Project Board).

How to eliminate wrong answers

Option A is wrong because lessons learned are formally captured in the Lessons Log and Lessons Report, not in a Checkpoint Report. Option C is wrong because informing the Project Board of stage progress is the purpose of the Highlight Report (or End Stage Report), not the Checkpoint Report. Option D is wrong because escalating issues to the Project Board is done via an Exception Report or Issue Report, not the Checkpoint Report.

493
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Configuration item records
B.Quality criteria
C.Investment appraisal
D.Product descriptions
E.Expected benefits
AnswersC, E

Why this answer

The Business Case includes expected benefits, costs, and investment appraisal, among others. Options and risks are also components.

494
MCQmedium

Which PRINCE2 principle is being applied when the Project Manager escalates a tolerance deviation to the Project Board?

A.Continued Business Justification
B.Manage by Exception
C.Learn from Experience
D.Focus on Products
AnswerB

Correct. Escalation of tolerance deviations is management by exception.

Why this answer

The 'Manage by Exception' principle is applied when the Project Manager escalates a tolerance deviation to the Project Board. This principle delegates decision-making authority to the Project Manager within defined tolerances (e.g., time, cost, quality, scope, risk, and benefit). When a forecast indicates that a tolerance will be exceeded, the Project Manager must escalate the issue to the Project Board, which then decides on corrective action.

This ensures that the Project Board only becomes involved when a deviation threatens the project's agreed limits, embodying the 'manage by exception' approach.

Exam trap

Candidates often confuse 'Manage by Exception' with 'Continued Business Justification' — the escalation of a tolerance breach is about exceeding delegated limits, not about the project's ongoing viability.

How to eliminate wrong answers

Option A is wrong because Continued Business Justification ensures the project remains viable and aligned with business objectives throughout its lifecycle, but it does not directly address the escalation of tolerance deviations; that is the role of Manage by Exception. Option C is wrong because Learn from Experience involves capturing and applying lessons learned from previous projects or phases to improve current and future work, not the escalation of tolerance breaches. Option D is wrong because Focus on Products emphasizes defining and delivering the project's products (outputs) with agreed quality criteria, not the mechanism for handling deviations from tolerances.

495
MCQhard

Who is responsible for performing Project Assurance?

A.Project Support
B.Project Manager
C.Team Managers
D.Project Board members (or their delegates)
AnswerD

Correct. Assurance is independent and typically delegated by the Board.

Why this answer

Project Assurance is a PRINCE2 responsibility that provides an independent check on the project's progress, compliance, and viability. The Project Board members (or their delegates) are accountable for this function because they represent the business, user, and supplier interests, ensuring objective oversight separate from day-to-day management.

Exam trap

The trap here is that candidates often confuse Project Assurance with Project Support or assume the Project Manager can handle it, but PRINCE2 explicitly separates the assurance role from management to maintain independence and objectivity.

How to eliminate wrong answers

Option A is wrong because Project Support provides administrative and clerical services (e.g., planning tools, filing), not independent oversight. Option B is wrong because the Project Manager is responsible for day-to-day management and cannot provide independent assurance of their own work. Option C is wrong because Team Managers are focused on delivering specific work packages and lack the authority or independence to perform Project Assurance across the entire project.

496
MCQmedium

Which risk response is appropriate for a threat that the project team decides to actively reduce the probability or impact of?

A.Avoid
B.Accept
C.Reduce
D.Transfer
AnswerC

Reduce involves actions to lower probability or impact.

Why this answer

The 'Reduce' response involves proactive actions to lower the probability and/or impact of a threat.

497
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is documented in the Issue Register, while an Off-specification is documented in the Quality Register
B.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
C.There is no difference; they are the same thing
D.A Request for Change is a proposal to change an agreed baseline, while an Off-specification is a deviation from a baseline
AnswerD

RFC proposes a change; Off-spec identifies a deviation that already exists.

Why this answer

A Request for Change (RFC) is a formal proposal to modify an approved baseline (e.g., a product description, plan, or scope), while an Off-specification (Off-spec) is a deviation from a baseline that has been identified—meaning something that should be there is missing or something that should not be there is present. In PRINCE2, both are types of issues recorded in the Issue Register, but they serve distinct purposes: RFCs seek authorized changes, whereas Off-specs report non-compliance with agreed baselines.

Exam trap

The trap here is that candidates confuse the documentation location (Issue Register vs. Quality Register) or assume that only certain roles can raise these issues, whereas PRINCE2 allows any stakeholder to raise any type of issue, and the key differentiator is the baseline relationship—proposal to change vs. deviation from baseline.

How to eliminate wrong answers

Option A is wrong because both a Request for Change and an Off-specification are documented in the Issue Register, not the Quality Register (the Quality Register records planned quality activities and results). Option B is wrong because either can be raised by any project stakeholder (e.g., team member, supplier, Project Manager), not exclusively by the Project Board (RFCs) or Project Manager (Off-specs); the Project Board approves RFCs, but does not necessarily raise them. Option C is wrong because they are fundamentally different: an RFC proposes a change to an agreed baseline, while an Off-specification reports a deviation from a baseline that already exists.

498
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Executive
D.Senior Supplier
AnswerC

The Executive is the owner of the Business Case and is responsible for ensuring it remains viable throughout the project.

Why this answer

The Executive owns the Business Case and is accountable for its viability throughout the project. Option A is incorrect because the Senior User represents the users' needs, not the Business Case. Option B is incorrect because the Project Manager maintains the Business Case on a day-to-day basis but does not own it.

Option D is incorrect because the Senior Supplier provides resources and expertise, not ownership of the Business Case.

499
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is for changes to the project plan; an Off-specification is for changes to products
B.A Request for Change is raised by the team; an Off-specification is raised by the project manager
C.A Request for Change requires an issue report; an Off-specification does not
D.A Request for Change is a proposal to change a baselined product; an Off-specification is a product that does not meet its specification
AnswerD

This correctly distinguishes the two types of issue.

Why this answer

A Request for Change is a proposed change to a product that has been defined and possibly baselined. An Off-specification is something that is missing from a product or does not meet specifications. Both are types of issue, but the key difference is that a RFC is a change to the specification, while an Off-spec is a failure to meet it.

500
MCQeasy

Which document records the project's planned costs, timescales, and products?

A.Business Case
B.Stage Plan
C.Project Plan
D.Highlight Report
AnswerC

Correct.

Why this answer

The Project Plan is the high-level plan covering the entire project.

501
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Project Assurance
C.Senior User
D.Executive
AnswerA

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive owns it and approves changes.

502
MCQmedium

A project has identified a risk that the key supplier may go out of business. The Project Manager decides to source a backup supplier. Which risk response is being applied?

A.Avoid
B.Transfer
C.Accept
D.Fallback
AnswerD

Fallback involves having a contingency plan to implement if the risk occurs.

Why this answer

Fallback is a threat response that involves preparing a contingency plan to be implemented if the risk occurs. Sourcing a backup supplier is an example of a fallback, as it provides an alternative if the primary supplier fails. Option A is wrong because Avoid would mean taking action to eliminate the risk entirely, such as finding a different supplier altogether.

Option B is wrong because Transfer would involve shifting the risk to a third party, such as through insurance or a contract. Option C is wrong because Accept would mean taking no proactive action and simply acknowledging the risk.

503
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To manage the work of the current stage
B.To create the Project Initiation Documentation
C.To close the project and produce the End Project Report
D.To plan the next stage in detail and request authorization from the Project Board
AnswerD

Correct description of the process purpose.

Why this answer

The purpose is to enable the Project Board to review the current stage's performance and approve the next stage plan.

504
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Senior User
C.Executive
D.Project Manager
AnswerD

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager maintains the Business Case under the direction of the Executive. The Executive owns it, but the PM does the updates.

505
MCQhard

In PRINCE2, which role is responsible for maintaining the risk register?

A.The Senior User
B.The Risk Owner
C.The Project Assurance
D.The Project Manager
AnswerD

The Project Manager maintains the risk register.

Why this answer

The Project Manager is responsible for maintaining the risk register as part of the 'Manage Risk' practice. This includes ensuring that risks are recorded, updated, and reviewed throughout the project, and that the register reflects the current risk status. The Project Manager does not own individual risks but manages the register as a key project document.

Exam trap

The trap here is that candidates confuse the 'Risk Owner' (who manages a specific risk) with the role responsible for maintaining the entire risk register, leading them to select Option B instead of the correct Project Manager.

How to eliminate wrong answers

Option A is wrong because the Senior User specifies the user needs and benefits, but does not maintain the risk register; their role is to represent the users and ensure the project delivers the required outcomes. Option B is wrong because the Risk Owner is responsible for managing a specific risk and implementing responses, not for maintaining the overall risk register; the register is a project-level document. Option C is wrong because Project Assurance provides independent oversight and checks that the risk register is being properly maintained, but does not perform the maintenance itself.

506
MCQmedium

In the PRINCE2 risk management procedure, which step involves deciding whether to respond to a risk and selecting the appropriate response?

A.Identify
B.Implement
C.Assess
D.Plan
AnswerD

Correct. In the Plan step, the risk response is planned and selected.

Why this answer

The 'Plan' step is where risk responses are developed and selected. The 'Assess' step evaluates probability and impact, but the decision on how to respond is part of planning.

507
MCQeasy

Which role is responsible for managing the project on a day-to-day basis?

A.Executive
B.Senior User
C.Project Manager
D.Senior Supplier
AnswerC

The Project Manager is responsible for day-to-day management.

Why this answer

The Project Manager is delegated by the Project Board to manage the project on a day-to-day basis within agreed tolerances.

508
MCQeasy

What is the definition of quality in PRINCE2?

A.Conformance to ISO standards
B.Fit for purpose
C.Customer satisfaction
D.Zero defects
AnswerB

Quality in PRINCE2 is 'fit for purpose'.

Why this answer

In PRINCE2, quality is defined as 'fit for purpose,' meaning the product meets the stated requirements and is suitable for its intended use. This definition emphasizes that quality is about satisfying the agreed-upon specifications and user needs, not about achieving an abstract standard like zero defects or ISO compliance.

Exam trap

The trap here is that candidates often confuse quality with customer satisfaction or zero defects, but PRINCE2 specifically defines quality as 'fit for purpose' to emphasize meeting requirements over perfection or external standards.

How to eliminate wrong answers

Option A is wrong because conformance to ISO standards is a specific external benchmark, not the PRINCE2 definition of quality; PRINCE2 focuses on meeting agreed requirements rather than any particular standard. Option C is wrong because customer satisfaction is a broader outcome that can result from quality, but it is not the definition of quality itself in PRINCE2. Option D is wrong because zero defects is a manufacturing-oriented concept that does not align with PRINCE2's pragmatic approach, where quality is about fitness for purpose, not perfection.

509
Multi-Selecthard

Which THREE of the following are risk responses for threats?

Select 3 answers
A.Enhance
B.Reduce
C.Avoid
D.Exploit
E.Transfer
AnswersB, C, E

Why this answer

In PRINCE2, risk responses for threats are designed to reduce the probability or impact of a negative risk. 'Reduce' (Option B) is a correct threat response because it involves taking action to lower the probability or impact of a threat, such as implementing additional testing to reduce the risk of software failure. 'Avoid' (Option C) is correct because it involves changing the project plan to eliminate the threat entirely, for example, by choosing a different technology stack to avoid a known security vulnerability. 'Transfer' (Option E) is correct because it shifts the financial impact of a threat to a third party, such as purchasing insurance or outsourcing a high-risk component to a specialist vendor.

Exam trap

PeopleCert often tests the confusion between threat and opportunity responses, specifically that 'Enhance' and 'Exploit' are only for opportunities, not threats, leading candidates to incorrectly select them as valid threat responses.

510
Multi-Selectmedium

Which THREE of the following are typical elements of a Product Description?

Select 3 answers
A.Project budget
B.Purpose of the product
C.Quality criteria
D.Product composition
E.Risk register
AnswersB, C, D

The product's purpose is included.

Why this answer

The Purpose of the product is a mandatory element in a PRINCE2 Product Description. It defines why the product is needed and how it contributes to the project's objectives, ensuring all stakeholders understand its role before development begins.

Exam trap

The trap here is that candidates confuse management products (like the Project budget or Risk register) with the elements of a Product Description, which are strictly focused on the product's definition and quality requirements.

511
MCQhard

A project is in the Managing a Stage Boundary process. The Project Manager discovers that a key team member has left the project and a replacement will cost more than planned. What should the Project Manager do?

A.Include the issue in the End Stage Report and propose a revised Plan for the next stage
B.Hire a replacement and absorb the cost without escalation
C.Report the issue in the next Highlight Report
D.Raise an Exception Report immediately
AnswerA

Correct action in Managing a Stage Boundary.

Why this answer

During Managing a Stage Boundary, the PM prepares the End Stage Report and next Stage Plan. The issue should be documented with a recommendation for the Project Board to decide.

512
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Configuration item records
B.Product Description
C.Major risks
D.Expected benefits
E.Project Plan
AnswersC, D

Major risks to the business justification are included.

Why this answer

The Business Case in PRINCE2 justifies the project's initiation and continued viability. It must include the expected benefits (tangible and intangible) that the project aims to deliver, as well as the major risks that could affect those benefits. Therefore, options C and D are correct components.

Exam trap

PRINCE2 exams often test the distinction between the Business Case and the Project Plan, as candidates may mistakenly think the Project Plan is part of the Business Case, when in fact the Business Case is the justification document and the Project Plan is the delivery schedule.

513
MCQmedium

Which document defines the quality criteria for a product and is used during quality control?

A.Product Description
B.Project Product Description
C.Quality Management Approach
D.Quality Register
AnswerA

Each product has a Product Description detailing its quality criteria.

Why this answer

The Product Description includes quality criteria and is used to verify that the product meets requirements.

514
MCQmedium

Which of the following best describes the 'risk owner'?

A.The person who monitors the risk budget
B.The person who carries out the risk response actions
C.The person who identifies the risk
D.The person responsible for managing the risk and implementing responses
AnswerD

This is the definition of risk owner.

Why this answer

The PRINCE2 definition of a risk owner is the person who is responsible for managing all aspects of a specific risk, including monitoring the risk, implementing the planned response actions, and ensuring the risk is effectively controlled. This role is accountable for the risk throughout its lifecycle, not just for executing a single task.

Exam trap

The trap here is that candidates often confuse the 'risk owner' with the 'risk actionee' (the person who performs the response actions), leading them to incorrectly select Option B, but PRINCE2 explicitly separates accountability from execution.

How to eliminate wrong answers

Option A is wrong because monitoring the risk budget is the responsibility of the project manager or the person managing the project budget, not the risk owner. Option B is wrong because carrying out the risk response actions is typically the role of the 'risk actionee' (or risk response owner), who is assigned by the risk owner to perform specific tasks; the risk owner retains overall accountability. Option C is wrong because identifying the risk is a task that can be performed by any stakeholder or team member, and it does not automatically make that person the risk owner; the risk owner is formally assigned later during the risk management process.

515
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable.
B.Raise an Exception Report to the Project Board and await their direction before proceeding.
C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan.
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report.
AnswerB

When a stage tolerance is forecast to be exceeded, the PM must escalate immediately via an Exception Report. This is management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception. The PM cannot increase the budget or continue without escalation.

516
MCQhard

During a project, a Team Manager reports that a product will be delivered two weeks later than planned. The tolerance for the Work Package is one week. What should the Team Manager do?

A.Update the Project Plan to reflect the delay
B.Request a change to the Project Plan directly from the Project Board
C.Issue an Exception Report to the Project Manager
D.Continue with the work and inform the Project Manager in the next Checkpoint Report
AnswerC

This is the correct escalation per PRINCE2.

Why this answer

When a Work Package tolerance is forecast to be exceeded, the Team Manager must escalate to the Project Manager via an Exception Report. The Project Manager can then negotiate corrective actions.

517
MCQeasy

Which document describes the quality methods and responsibilities for the project?

A.Quality Register
B.Product Description
C.Project Plan
D.Quality Management Approach
AnswerD

Correct.

Why this answer

The Quality Management Approach defines how quality will be managed, including methods, responsibilities, and tools.

518
MCQmedium

Which practice is responsible for defining the project's approach to identifying, assessing, and controlling uncertainty?

A.Risk
B.Quality
C.Progress
D.Change
AnswerA

Correct.

Why this answer

The Risk practice covers the systematic management of threats and opportunities.

519
MCQmedium

In product-based planning, what is the purpose of a Product Flow Diagram?

A.To show the order in which products are created and their dependencies
B.To show the timeline and resource allocation for product creation
C.To describe the quality criteria for a product
D.To break down the final product into its component products
AnswerA

The Product Flow Diagram illustrates the sequence and dependencies of products.

Why this answer

A Product Flow Diagram shows the sequence in which products are created and the dependencies between them. Option B is incorrect because it describes a Gantt chart or timeline, not a Product Flow Diagram. Option C is incorrect because it describes a Product Description, which defines quality criteria.

Option D is incorrect because it describes a Product Breakdown Structure (PBS), which decomposes the final product into components.

520
MCQeasy

What is the key output of the Initiating a Project process?

A.Project Initiation Documentation (PID)
B.Project Brief
C.End Project Report
D.Stage Plan
AnswerA

The PID is the key deliverable of Initiating a Project.

Why this answer

The key output of the Initiating a Project process is the Project Initiation Documentation (PID). The PID consolidates all baseline information needed to justify proceeding with the project, including the Business Case, project scope, and management strategies. It serves as the foundation for decision-making by the Project Board and is formally approved before moving to the next stage.

Exam trap

PRINCE2 often tests the distinction between the Project Brief (created in Starting Up a Project) and the PID (created in Initiating a Project), leading candidates to confuse the two outputs.

How to eliminate wrong answers

Option B is wrong because the Project Brief is created during the Starting Up a Project process, not the Initiating a Project process; it provides initial context but lacks the detailed plans and strategies required for full authorization. Option C is wrong because the End Project Report is produced during the Closing a Project process to summarize performance against the PID, not during initiation. Option D is wrong because a Stage Plan is created for each management stage during the Controlling a Stage process, not as the key output of Initiating a Project.

521
MCQmedium

The Project Board is considering whether to authorize the next stage. The current stage has used all its cost tolerance. What should the Project Board do?

A.Request an Exception Plan before authorizing the next stage
B.Revise the project's cost tolerance
C.Close the project immediately
D.Authorize the next stage as planned
AnswerA

To address the tolerance breach, the Board should request an Exception Plan to adjust future plans.

Why this answer

According to PRINCE2, if a stage has exceeded its cost tolerance, the Project Board cannot authorize the next stage without first assessing the situation. The correct action is to request an Exception Plan, which details how to recover from the deviation and bring the project back within tolerance. This ensures the board has a revised forecast and recovery strategy before committing to further expenditure.

Exam trap

The trap here is that candidates may assume the board can simply adjust tolerances or proceed as normal, failing to recognize that PRINCE2 mandates an Exception Plan when a stage exceeds its tolerance, not just a simple revision of the budget.

How to eliminate wrong answers

Option B is wrong because revising the project's cost tolerance would be an inappropriate response to a stage-level deviation; tolerances are set at project level and should not be changed simply because a stage has overspent. Option C is wrong because closing the project immediately is too drastic and not mandated by PRINCE2; the board should first investigate the cause and consider recovery options. Option D is wrong because authorizing the next stage as planned ignores the fact that the current stage has breached its cost tolerance, which requires corrective action before proceeding.

522
Multi-Selecthard

Which THREE of the following are responsibilities of the Executive?

Select 3 answers
A.Produce Highlight Reports
B.Provide customer assurance
C.Ensure the Business Case remains viable
D.Chair the Project Board
E.Appoint the Project Manager
AnswersC, D, E

The Executive owns the Business Case and ensures its viability.

Why this answer

The Executive is accountable for the Business Case, appoints the Project Manager, and chairs the Project Board. Providing customer assurance is the Senior User's role; producing Highlight Reports is the Project Manager's role.

523
Multi-Selecthard

Which THREE of the following are examples of threat responses in the Risk practice?

Select 3 answers
A.Enhance
B.Reduce
C.Exploit
D.Transfer
E.Avoid
AnswersB, D, E

Correct threat response.

Why this answer

Avoid, reduce, and transfer are threat responses. Exploit and enhance are opportunity responses.

524
MCQeasy

Which PRINCE2 document contains the cost and time tolerances for the project?

A.Business Case
B.Project Plan
C.Project Brief
D.Project Initiation Documentation
AnswerB

The Project Plan defines project-level tolerances for time, cost, scope, quality, risk, and benefits.

Why this answer

The Project Plan contains the project-level tolerances, including cost and time.

525
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Configuration item records
B.Expected benefits
C.Work package descriptions
D.Quality criteria
E.Major risks
AnswersB, E

Expected benefits are a key component of the Business Case.

Why this answer

The Business Case in PRINCE2 is the key document that justifies the project's initiation and continued viability. It must include the expected benefits (B) to demonstrate the positive outcomes the project aims to achieve, and it must identify major risks (E) to provide a balanced view of the potential downsides and uncertainties. These two components are explicitly required by the PRINCE2 Business Case theme.

Exam trap

The trap here is that candidates often confuse the contents of the Business Case with other management products, such as the Project Plan (which includes work packages) or the Quality Register (which includes quality criteria), leading them to select options that belong to those other documents.

← PreviousPage 7 of 8 · 596 questions totalNext →

Ready to test yourself?

Try a timed practice session using only Prince2 Practices questions.