The Project Board is considering whether to authorize the next stage. The current stage has used all its cost tolerance. What should the Project Board do?

⚠ Common exam trap

Many exam-takers assume the board can simply adjust tolerances or proceed as normal, failing to recognize that PRINCE2 mandates an Exception Plan when a stage exceeds its tolerance, not just a simple revision of the budget.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request an Exception Plan before authorizing the next stage

According to PRINCE2, if a stage has exceeded its cost tolerance, the Project Board cannot authorize the next stage without first assessing the situation. The correct action is to request an Exception Plan, which details how to recover from the deviation and bring the project back within tolerance. This ensures the board has a revised forecast and recovery strategy before committing to further expenditure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request an Exception Plan before authorizing the next stage

    Why this is correct

    To address the tolerance breach, the Board should request an Exception Plan to adjust future plans.

  • Revise the project's cost tolerance

    Why it's wrong here

    The Board could revise project-level tolerance, but this is not the immediate step; an Exception Plan addresses the stage breach.

  • Close the project immediately

    Why it's wrong here

    Closing may be an option but is not the only action; the Board should first consider an Exception Plan.

  • Authorize the next stage as planned

    Why it's wrong here

    The tolerance has been fully used; continuing without change risks exceeding overall budget.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.