PRINCE2F PRINCE2 Practices Practice Question
In the PRINCE2 risk management procedure, which step involves deciding whether to respond to a risk and selecting the appropriate response?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Plan
The 'Plan' step is where risk responses are developed and selected. The 'Assess' step evaluates probability and impact, but the decision on how to respond is part of planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Identify
Why it's wrong here
Identify is about finding risks, not deciding responses.
- ✗
Implement
Why it's wrong here
Implement executes the chosen response, not selects it.
- ✗
Assess
Why it's wrong here
Assess evaluates risks but does not select responses.
- ✓
Plan
Why this is correct
Correct. In the Plan step, the risk response is planned and selected.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.