CCNA Prince2 Practices Questions

75 of 674 questions · Page 8/9 · Prince2 Practices topic · Answers revealed

526
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.An RFC is raised by the Project Board, while an Off-specification is raised by the Project Manager.
B.An RFC is always approved by the Change Authority, while an Off-specification is approved by the Project Board.
C.An RFC is a change to an approved baseline, while an Off-specification is a deviation from a requirement.
D.An Off-specification can be resolved by concession, while an RFC cannot.
AnswerC

An RFC proposes a change to an approved baseline; an Off-specification is a failure to meet a specified requirement.

Why this answer

An RFC is a proposal for a change that would deliver something not originally specified. An Off-specification is something that should have been provided but was not, i.e., a failure to meet a requirement.

527
Multi-Selectmedium

Which TWO of the following are valid tolerances in PRINCE2?

Select 2 answers
A.Customer satisfaction
B.Risk
C.Innovation
D.Quality
E.Resources
AnswersB, D

Yes, risk tolerance is defined.

Why this answer

PRINCE2 defines tolerances for time, cost, scope, quality, risk, and benefits. Quality and risk are valid tolerances.

528
MCQmedium

Which report is prepared by the Team Manager and sent to the Project Manager at regular intervals?

A.End Stage Report
B.Exception Report
C.Highlight Report
D.Checkpoint Report
AnswerD

The Checkpoint Report provides progress information from the Team Manager to the Project Manager.

Why this answer

Option A is correct. The Checkpoint Report is a progress report prepared by the Team Manager and sent to the Project Manager. Option B is incorrect because the Highlight Report is prepared by the Project Manager for the Project Board.

Option C is incorrect because the Exception Report is prepared by the Project Manager when tolerances are forecast to be exceeded. Option D is incorrect because the End Stage Report is prepared by the Project Manager at stage boundaries.

529
MCQmedium

What is the purpose of the Quality Review technique?

A.To approve the project's quality management approach
B.To update the quality register
C.To assess the quality of a product and identify defects
D.To define quality criteria for products
AnswerC

The Quality Review technique is used to review products against their quality criteria.

Why this answer

The Quality Review technique is used to assess the quality of a product and identify defects. It is a form of quality control.

530
MCQmedium

Who receives Highlight Reports?

A.Project Board
B.Senior Supplier
C.Project Support
D.Team Manager
AnswerA

The Project Board receives Highlight Reports from the Project Manager.

Why this answer

Highlight Reports are prepared by the Project Manager and sent to the Project Board (and possibly stakeholders) at regular intervals.

531
Multi-Selecthard

Which THREE of the following are components of a Product Description?

Select 3 answers
A.Purpose
B.Derivation
C.Quality criteria
D.Benefits
E.Cost
AnswersA, B, C

Purpose is a component of a Product Description.

Why this answer

A Product Description includes purpose, composition, derivation, format, quality criteria, quality method, and quality tolerance. Cost and benefits are not part of a Product Description; they are in the Business Case.

532
MCQmedium

Which document defines the quality criteria and acceptance methods for a project's products?

A.Product Description
B.Quality Management Approach
C.Business Case
D.Project Plan
AnswerA

Product Descriptions define quality criteria, acceptance methods, and other product-specific details.

Why this answer

Option C is correct. Product Descriptions define the quality criteria, acceptance methods, and other details for each product. The Quality Management Approach defines the overall quality strategy.

533
MCQmedium

The project's risk appetite has been defined as 'cautious'. A high-impact opportunity with low probability is identified. What is the most likely response?

A.Enhance
B.Share
C.Reject
D.Exploit
AnswerC

Reject is appropriate for cautious appetite when opportunity risk is not acceptable.

Why this answer

A cautious appetite means risk-averse; even low probability opportunities may be rejected if they carry risk.

534
Multi-Selectmedium

Which TWO of the following are types of issues in PRINCE2?

Select 2 answers
A.Request for Change
B.Change
C.Risk
D.Off-specification
E.Opportunity
AnswersA, D

An RFC is a type of issue.

Why this answer

PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. Risk and change are not types of issues.

535
MCQmedium

In PRINCE2, who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Project Manager
C.Project Board
D.Project Assurance
AnswerD

Project Assurance is independent and reports to the Project Board.

Why this answer

Project Assurance is an independent role that ensures the project remains aligned with business, user, and supplier interests.

536
MCQhard

In the risk management procedure, what is the difference between a risk owner and a risk actionee?

A.Risk owner identifies risks; risk actionee assesses them
B.Risk owner manages the risk overall; risk actionee performs specific actions
C.Risk owner is the same as risk actionee in PRINCE2
D.Risk owner is on the Project Board; risk actionee is a team member
AnswerB

Correct. The owner has overall accountability; the actionee executes tasks.

Why this answer

The risk owner is responsible for managing the risk and ensuring appropriate responses are implemented; the risk actionee is the person who carries out specific risk response actions.

537
MCQmedium

What is the difference between a Highlight Report and a Checkpoint Report?

A.The Highlight Report is used to escalate exceptions, while the Checkpoint Report is for routine communication
B.The Highlight Report is produced only at stage boundaries, while the Checkpoint Report is produced weekly
C.The Highlight Report is from the Project Manager to the Project Board, while the Checkpoint Report is from the Team Manager to the Project Manager
D.The Highlight Report focuses on risks and issues, while the Checkpoint Report focuses on product quality
AnswerC

This correctly identifies the reporting hierarchy.

Why this answer

Option A is correct. The Highlight Report is sent by the Project Manager to the Project Board, while the Checkpoint Report is sent by the Team Manager to the Project Manager. Option B is wrong because both reports are regular.

Option C is wrong because both reports focus on progress. Option D is wrong because the Highlight Report is not a response to exceptions.

538
MCQeasy

In PRINCE2, who is responsible for project assurance?

A.The Project Manager
B.The Senior Supplier
C.The Project Support
D.The Project Board
AnswerD

Correct. The Project Board is responsible for assurance.

Why this answer

Project assurance is the responsibility of the Project Board, which provides independent assurance.

539
Multi-Selectmedium

Which TWO of the following are components of a Business Case?

Select 2 answers
A.Major risks
B.Project organization structure
C.Work Breakdown Structure
D.Expected benefits
E.Quality criteria
AnswersA, D

Risks are included.

Why this answer

Expected benefits and major risks are key components of a Business Case in PRINCE2.

540
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are the same thing
B.An RFC is raised by the Project Manager; an Off-specification is raised by the Team Manager
C.An RFC requires a change budget; an Off-specification does not
D.An RFC concerns a desired change to an approved specification; an Off-specification is a product that does not meet its specification
AnswerD

This is the correct distinction.

Why this answer

An RFC is a proposal for a modification to a product that has been baselined, while an Off-specification is a product that should be produced but is not meeting specifications.

541
MCQhard

A risk has been identified that could cause a delay to the project. The project team decides to purchase insurance to cover the financial impact. Which risk response type is this?

A.Transfer
B.Avoid
C.Accept
D.Reduce
AnswerA

Insurance transfers the financial impact to an insurer.

Why this answer

Transferring the financial impact to a third party (insurance) is a 'transfer' response. 'Reduce' would involve actions to lower probability or impact. 'Accept' would be to take the risk without action.

542
Multi-Selectmedium

Which TWO of the following are steps in the PRINCE2 risk management procedure?

Select 2 answers
A.Monitor
B.Implement
C.Assess
D.Control
E.Allocate
AnswersB, C

Implement involves executing the planned risk responses.

Why this answer

Options B and D are correct. The recommended risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. 'Assess' includes both probability and impact evaluation. 'Implement' involves executing the planned responses. 'Monitor' and 'Control' are not separate steps; they are part of Implement and Communicate.

543
MCQhard

A project is using the PRINCE2 product-based planning technique. Which of the following describes the correct sequence of activities?

A.Create Product Breakdown Structure, then Product Flow Diagram, then Product Descriptions
B.Create Product Flow Diagram, then Product Descriptions, then Product Breakdown Structure
C.Write Project Product Description, create Product Descriptions, then Product Breakdown Structure
D.Write Project Product Description, create Product Breakdown Structure, create Product Flow Diagram, then produce Product Descriptions
AnswerD

This is the correct order per PRINCE2.

Why this answer

Product-based planning follows: write Project Product Description, create Product Breakdown Structure, create Product Flow Diagram, then produce Product Descriptions for each product.

544
MCQhard

During the Managing a Stage Boundary process, the Project Manager reviews the Business Case and finds that the expected benefits are no longer achievable. What should the Project Manager do?

A.Create an Exception Plan to revise the benefits
B.Continue with the next stage as planned and report the issue in the End Project Report
C.Recommend to the Project Board that the project should be closed as the Business Case is no longer viable
D.Close the project immediately without consulting the Project Board
AnswerC

The Project Manager should escalate to the Project Board, which may decide to close the project.

Why this answer

If the Business Case is no longer viable, the Project Manager should recommend to the Project Board that the project is not worthwhile. The Board decides whether to continue or close. Option A is wrong because continuing without addressing the issue is not acceptable.

Option C is wrong because the PM does not unilaterally close the project. Option D is wrong because an Exception Plan is for tolerance deviations, not for a failed Business Case.

545
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue with the current plan and report the cost overrun in the next Highlight Report
B.Raise an Exception Report to the Project Board and await their direction
C.Increase the project budget to absorb the additional cost and continue with the current plan
D.Close the project immediately as the Business Case is no longer viable
AnswerB

This is the correct escalation procedure.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

546
Multi-Selectmedium

Which THREE of the following are typical response strategies for a threat (negative risk) in PRINCE2?

Select 3 answers
A.Share
B.Avoid
C.Reduce
D.Transfer
E.Exploit
AnswersB, C, D

Avoid is a valid threat response.

Why this answer

Threat response strategies include Avoid, Reduce (Mitigate), Fallback, Transfer, Accept, and Share. Exploit is an opportunity response, not a threat response.

547
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
D.Close the project immediately as the Business Case is no longer viable
AnswerA

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

Option C is correct. When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally exceed tolerances (A), continue without escalation (B), or close the project without Board decision (D).

548
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board?

Select 3 answers
A.Providing overall direction and control
B.Managing risks on a daily basis
C.Approving the Project Plan
D.Producing Highlight Reports
E.Ensuring project assurance is carried out
AnswersA, C, E

The Project Board provides overall direction.

Why this answer

The Project Board is responsible for providing overall direction, approving plans, and ensuring assurance. Producing Highlight Reports is the PM's responsibility; managing risks on a daily basis is the PM's role.

549
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Senior User
B.There is no difference; they are alternative terms for the same thing
C.A Request for Change seeks to modify a baselined product; an Off-specification identifies a failure to meet a specification
D.A Request for Change always requires a change budget; an Off-specification does not
AnswerC

Correct. RFC proposes a change to an agreed baseline; Off-specification is a deviation from the agreed specification.

Why this answer

A Request for Change is a proposal for a modification to a product that has been baselined, while an Off-specification is something that should be provided but is not (or is forecast not to be). The key difference is that RFC is about changing what was agreed, whereas Off-spec is about failing to deliver what was agreed.

550
MCQmedium

A project manager is reviewing the business case for a new product development project. The project board has expressed concern that the benefits may not be realized as planned. Which management product should the project manager update to address this concern?

A.Benefits Management Approach
B.Business Case
C.Project Plan
D.Risk Register
AnswerA

This approach defines how benefits will be measured and reviewed, addressing the board's concern.

Why this answer

The Benefits Management Approach defines how the project's benefits will be measured, tracked, and realized throughout the project and into operations. Since the project board is concerned about benefits realization, updating this approach with revised measurement criteria, review timing, or ownership details directly addresses their concern by providing a clear plan for ensuring benefits are achieved.

Exam trap

The trap here is that candidates often confuse the Business Case (which justifies the project) with the Benefits Management Approach (which manages how benefits are tracked and realized), leading them to incorrectly select the Business Case when the question specifically asks about addressing realization concerns.

How to eliminate wrong answers

Option B is wrong because the Business Case documents the justification for the project, including costs, benefits, and risks, but it does not detail the ongoing management and measurement of benefits realization; updating it would not provide the specific tracking plan needed. Option C is wrong because the Project Plan focuses on the schedule, resources, and activities to deliver the project's products, not on how benefits will be realized after delivery. Option D is wrong because the Risk Register captures individual risks and their responses, but benefits realization is a broader management concern that requires a dedicated approach document, not just a risk entry.

551
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is only used during delivery; an Off-specification is only used during closure
B.A Request for Change is proposed by the Project Board; an Off-specification is proposed by the Project Manager
C.A Request for Change seeks to modify a baselined product; an Off-specification identifies a product that does not meet its specification
D.There is no difference; the terms are interchangeable
AnswerC

Correct. RFC: change to specification; Off-spec: failure to meet specification.

Why this answer

A Request for Change is a proposal for a change, while an Off-specification is something that should be there but isn't.

552
Multi-Selecthard

Which THREE of the following are types of issue defined in PRINCE2?

Select 3 answers
A.Request for Change
B.Problem/Concern
C.Risk
D.Off-specification
E.Change request
AnswersA, B, D

An RFC is a formal proposal for a change.

Why this answer

PRINCE2 defines three issue types: Request for Change, Off-specification, and Problem/Concern. Options A, B, and D are correct. Options C and E are not issue types.

553
Multi-Selecthard

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Risk Register
B.Project Plan
C.Lessons Log
D.Work Package
E.Business Case
AnswersA, B, E

Correct. The Risk Register is part of the PID.

Why this answer

The PID includes the Business Case, Project Plan, and Risk Register. The Lessons Log is separate; the Work Package is created later.

554
MCQmedium

Based on the exhibit, what is the current risk exposure of risk R1?

A.Low
B.Very High
C.Medium
D.High
AnswerC

Low probability combined with High impact typically gives a Medium risk exposure.

Why this answer

Risk exposure is calculated as the product of probability and impact. In the exhibit, risk R1 has a probability of 'Medium' (0.3–0.7) and an impact of 'Medium' (0.3–0.7). Multiplying the midpoints (0.5 × 0.5 = 0.25) or using the ranges, the resulting exposure falls within the 'Medium' category on the PRINCE2 risk matrix.

Therefore, the current risk exposure is correctly identified as Medium.

Exam trap

The trap here is that candidates often confuse the individual probability or impact rating with the combined risk exposure, mistakenly selecting 'High' or 'Very High' when only one factor is elevated, or 'Low' when both are medium, instead of correctly calculating the product.

How to eliminate wrong answers

Option A is wrong because 'Low' would require both probability and impact to be low (e.g., 0.1–0.3 each), but R1 has medium probability and medium impact. Option B is wrong because 'Very High' requires both probability and impact to be very high (e.g., 0.9–1.0 each), which is not the case for R1. Option D is wrong because 'High' would require at least one factor to be high (e.g., 0.7–0.9) and the other medium or high, but R1 has both factors at medium, yielding a medium exposure.

555
Multi-Selecthard

Which THREE of the following are valid threat responses in PRINCE2?

Select 3 answers
A.Enhance
B.Exploit
C.Reduce
D.Avoid
E.Transfer
AnswersC, D, E

Reduce is a threat response to lower the probability or impact.

Why this answer

In PRINCE2, threat responses are actions taken to address negative risks. 'Reduce' (also called 'Mitigate') is a valid response that aims to lower the probability and/or impact of a threat to an acceptable level. This is one of the five standard threat response categories defined in the PRINCE2 risk management practice.

Exam trap

PeopleCert often tests the confusion between threat and opportunity responses, where candidates mistakenly select 'Enhance' or 'Exploit' as valid threat responses because they sound like proactive actions, but PRINCE2 strictly reserves them for positive risks.

556
Multi-Selectmedium

Which TWO of the following are components of a Business Case?

Select 2 answers
A.Product Description
B.Risk Register
C.Expected benefits
D.Configuration Item Records
E.Investment appraisal
AnswersC, E

Benefits are a key component justifying the project.

Why this answer

The Business Case includes expected benefits and costs (investment appraisal). Options A and B are correct. Options C, D, and E are not standard components.

557
Multi-Selecteasy

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Project Plan
B.Expected benefits
C.Product Breakdown Structure
D.Quality Register
E.Major risks
AnswersB, E

Benefits are a key component.

Why this answer

The Business Case includes expected benefits, costs, timescales, major risks, etc. Options, investment appraisal, and dis-benefits are also components.

558
MCQmedium

What is the purpose of a Checkpoint Report?

A.To document lessons learned
B.To report progress of a Work Package from the Team Manager to the Project Manager
C.To inform the Project Board of stage progress
D.To escalate issues to the Project Board
AnswerB

Checkpoint Reports are team-level reports from Team Manager to PM.

Why this answer

The Checkpoint Report is a PRINCE2 management product used by the Team Manager to report progress of a Work Package to the Project Manager. Its purpose is to provide regular, detailed progress updates on the work being performed by the team, ensuring the Project Manager can monitor delivery against the Work Package plan. This is distinct from higher-level reports like the End Stage Report or Highlight Report.

Exam trap

PeopleCert often tests the distinction between reports directed at different management levels; the trap here is confusing the Checkpoint Report (team-level to Project Manager) with the Highlight Report (Project Manager to Project Board).

How to eliminate wrong answers

Option A is wrong because lessons learned are formally captured in the Lessons Log and Lessons Report, not in a Checkpoint Report. Option C is wrong because informing the Project Board of stage progress is the purpose of the Highlight Report (or End Stage Report), not the Checkpoint Report. Option D is wrong because escalating issues to the Project Board is done via an Exception Report or Issue Report, not the Checkpoint Report.

559
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Configuration item records
B.Quality criteria
C.Investment appraisal
D.Product descriptions
E.Expected benefits
AnswersC, E

Why this answer

The Business Case includes expected benefits, costs, and investment appraisal, among others. Options and risks are also components.

560
MCQmedium

Which PRINCE2 principle is being applied when the Project Manager escalates a tolerance deviation to the Project Board?

A.Continued Business Justification
B.Manage by Exception
C.Learn from Experience
D.Focus on Products
AnswerB

Correct. Escalation of tolerance deviations is management by exception.

Why this answer

Management by Exception is the principle of delegating authority within tolerances and escalating deviations.

561
MCQhard

Who is responsible for performing Project Assurance?

A.Project Support
B.Project Manager
C.Team Managers
D.Project Board members (or their delegates)
AnswerD

Correct. Assurance is independent and typically delegated by the Board.

Why this answer

Project Assurance is performed by individuals independent of the Project Manager, typically from the Project Board roles.

562
MCQmedium

Which risk response is appropriate for a threat that the project team decides to actively reduce the probability or impact of?

A.Avoid
B.Accept
C.Reduce
D.Transfer
AnswerC

Reduce involves actions to lower probability or impact.

Why this answer

The 'Reduce' response involves proactive actions to lower the probability and/or impact of a threat.

563
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is documented in the Issue Register, while an Off-specification is documented in the Quality Register
B.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
C.There is no difference; they are the same thing
D.A Request for Change is a proposal to change an agreed baseline, while an Off-specification is a deviation from a baseline
AnswerD

RFC proposes a change; Off-spec identifies a deviation that already exists.

Why this answer

A Request for Change proposes a modification to an agreed baseline; an Off-specification is something that should be there but is not, or is wrong.

564
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Executive
D.Senior Supplier
AnswerC

The Executive is the owner of the Business Case and is responsible for ensuring it remains viable throughout the project.

Why this answer

Option B is correct. The Executive (Senior Responsible Owner) owns the Business Case and is accountable for its viability. The Project Manager maintains it on a day-to-day basis, but the Executive retains ultimate responsibility.

Option A is incorrect because the Project Manager maintains the Business Case but does not own it. Option C is incorrect because the Senior User represents the users, not the Business Case. Option D is incorrect because the Senior Supplier provides resources and expertise, not ownership of the Business Case.

565
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is for changes to the project plan; an Off-specification is for changes to products
B.A Request for Change is raised by the team; an Off-specification is raised by the project manager
C.A Request for Change requires an issue report; an Off-specification does not
D.A Request for Change is a proposal to change a baselined product; an Off-specification is a product that does not meet its specification
AnswerD

This correctly distinguishes the two types of issue.

Why this answer

A Request for Change is a proposed change to a product that has been defined and possibly baselined. An Off-specification is something that is missing from a product or does not meet specifications. Both are types of issue, but the key difference is that a RFC is a change to the specification, while an Off-spec is a failure to meet it.

566
MCQeasy

Which document records the project's planned costs, timescales, and products?

A.Business Case
B.Stage Plan
C.Project Plan
D.Highlight Report
AnswerC

Correct.

Why this answer

The Project Plan is the high-level plan covering the entire project.

567
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Project Assurance
C.Senior User
D.Executive
AnswerA

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive owns it and approves changes.

568
MCQmedium

A project has identified a risk that the key supplier may go out of business. The Project Manager decides to source a backup supplier. Which risk response is being applied?

A.Avoid
B.Transfer
C.Accept
D.Fallback
AnswerD

Fallback involves having a contingency plan to implement if the risk occurs.

Why this answer

Option C is correct. Fallback is a threat response that involves having a contingency plan if the risk occurs. Sourcing a backup supplier is a fallback.

Option A is wrong because avoid would mean finding a way to eliminate the risk entirely. Option B is wrong because transfer would involve shifting the risk to a third party. Option D is wrong because accept would mean taking no action.

569
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To manage the work of the current stage
B.To create the Project Initiation Documentation
C.To close the project and produce the End Project Report
D.To plan the next stage in detail and request authorization from the Project Board
AnswerD

Correct description of the process purpose.

Why this answer

The purpose is to enable the Project Board to review the current stage's performance and approve the next stage plan.

570
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Senior User
C.Executive
D.Project Manager
AnswerD

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager maintains the Business Case under the direction of the Executive. The Executive owns it, but the PM does the updates.

571
MCQhard

In PRINCE2, which role is responsible for maintaining the risk register?

A.The Senior User
B.The Risk Owner
C.The Project Assurance
D.The Project Manager
AnswerD

The Project Manager maintains the risk register.

Why this answer

The Project Manager is responsible for maintaining the risk register as part of the 'Manage Risk' practice. This includes ensuring that risks are recorded, updated, and reviewed throughout the project, and that the register reflects the current risk status. The Project Manager does not own individual risks but manages the register as a key project document.

Exam trap

The trap here is that candidates confuse the 'Risk Owner' (who manages a specific risk) with the role responsible for maintaining the entire risk register, leading them to select Option B instead of the correct Project Manager.

How to eliminate wrong answers

Option A is wrong because the Senior User specifies the user needs and benefits, but does not maintain the risk register; their role is to represent the users and ensure the project delivers the required outcomes. Option B is wrong because the Risk Owner is responsible for managing a specific risk and implementing responses, not for maintaining the overall risk register; the register is a project-level document. Option C is wrong because Project Assurance provides independent oversight and checks that the risk register is being properly maintained, but does not perform the maintenance itself.

572
MCQmedium

In the PRINCE2 risk management procedure, which step involves deciding whether to respond to a risk and selecting the appropriate response?

A.Identify
B.Implement
C.Assess
D.Plan
AnswerD

Correct. In the Plan step, the risk response is planned and selected.

Why this answer

The 'Plan' step is where risk responses are developed and selected. The 'Assess' step evaluates probability and impact, but the decision on how to respond is part of planning.

573
MCQeasy

Which role is responsible for managing the project on a day-to-day basis?

A.Executive
B.Senior User
C.Project Manager
D.Senior Supplier
AnswerC

The Project Manager is responsible for day-to-day management.

Why this answer

The Project Manager is delegated by the Project Board to manage the project on a day-to-day basis within agreed tolerances.

574
MCQeasy

What is the definition of quality in PRINCE2?

A.Conformance to ISO standards
B.Fit for purpose
C.Customer satisfaction
D.Zero defects
AnswerB

Quality in PRINCE2 is 'fit for purpose'.

Why this answer

In PRINCE2, quality is defined as 'fit for purpose,' meaning the product meets the stated requirements and is suitable for its intended use. This definition emphasizes that quality is about satisfying the agreed-upon specifications and user needs, not about achieving an abstract standard like zero defects or ISO compliance.

Exam trap

The trap here is that candidates often confuse quality with customer satisfaction or zero defects, but PRINCE2 specifically defines quality as 'fit for purpose' to emphasize meeting requirements over perfection or external standards.

How to eliminate wrong answers

Option A is wrong because conformance to ISO standards is a specific external benchmark, not the PRINCE2 definition of quality; PRINCE2 focuses on meeting agreed requirements rather than any particular standard. Option C is wrong because customer satisfaction is a broader outcome that can result from quality, but it is not the definition of quality itself in PRINCE2. Option D is wrong because zero defects is a manufacturing-oriented concept that does not align with PRINCE2's pragmatic approach, where quality is about fitness for purpose, not perfection.

575
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is an issue that cannot be resolved, whereas an Off-specification is a problem that can be resolved
B.A Request for Change is a product that does not meet its specification, whereas an Off-specification is a proposal for a change
C.A Request for Change is a proposal for a modification, whereas an Off-specification is a product that does not meet its specification
D.A Request for Change is a proposal for a change, whereas an Off-specification is a product that should have been produced but was not
AnswerC

Correct distinction.

Why this answer

A Request for Change is a proposal for a modification, while an Off-specification is a product that does not meet its specification.

576
Multi-Selecthard

Which THREE of the following are risk responses for threats?

Select 3 answers
A.Enhance
B.Reduce
C.Avoid
D.Exploit
E.Transfer
AnswersB, C, E

Why this answer

In PRINCE2, risk responses for threats are designed to reduce the probability or impact of a negative risk. 'Reduce' (Option B) is a correct threat response because it involves taking action to lower the probability or impact of a threat, such as implementing additional testing to reduce the risk of software failure. 'Avoid' (Option C) is correct because it involves changing the project plan to eliminate the threat entirely, for example, by choosing a different technology stack to avoid a known security vulnerability. 'Transfer' (Option E) is correct because it shifts the financial impact of a threat to a third party, such as purchasing insurance or outsourcing a high-risk component to a specialist vendor.

Exam trap

PeopleCert often tests the confusion between threat and opportunity responses, specifically that 'Enhance' and 'Exploit' are only for opportunities, not threats, leading candidates to incorrectly select them as valid threat responses.

577
Multi-Selectmedium

Which THREE of the following are typical elements of a Product Description?

Select 3 answers
A.Project budget
B.Purpose of the product
C.Quality criteria
D.Product composition
E.Risk register
AnswersB, C, D

The product's purpose is included.

Why this answer

A Product Description includes purpose, composition, and quality criteria, among others.

578
MCQhard

A project is in the Managing a Stage Boundary process. The Project Manager discovers that a key team member has left the project and a replacement will cost more than planned. What should the Project Manager do?

A.Include the issue in the End Stage Report and propose a revised Plan for the next stage
B.Hire a replacement and absorb the cost without escalation
C.Report the issue in the next Highlight Report
D.Raise an Exception Report immediately
AnswerA

Correct action in Managing a Stage Boundary.

Why this answer

During Managing a Stage Boundary, the PM prepares the End Stage Report and next Stage Plan. The issue should be documented with a recommendation for the Project Board to decide.

579
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Configuration item records
B.Product Description
C.Major risks
D.Expected benefits
E.Project Plan
AnswersC, D

Major risks to the business justification are included.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Expected benefits and major risks are correct.

580
MCQmedium

Which document defines the quality criteria for a product and is used during quality control?

A.Product Description
B.Project Product Description
C.Quality Management Approach
D.Quality Register
AnswerA

Each product has a Product Description detailing its quality criteria.

Why this answer

The Product Description includes quality criteria and is used to verify that the product meets requirements.

581
MCQmedium

Which of the following best describes the 'risk owner'?

A.The person who monitors the risk budget
B.The person who carries out the risk response actions
C.The person who identifies the risk
D.The person responsible for managing the risk and implementing responses
AnswerD

This is the definition of risk owner.

Why this answer

The risk owner is responsible for managing the risk and implementing responses. The risk actionee carries out specific actions. The owner may delegate tasks but retains overall accountability.

582
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable.
B.Raise an Exception Report to the Project Board and await their direction before proceeding.
C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan.
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report.
AnswerB

When a stage tolerance is forecast to be exceeded, the PM must escalate immediately via an Exception Report. This is management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception. The PM cannot increase the budget or continue without escalation.

583
MCQhard

During a project, a Team Manager reports that a product will be delivered two weeks later than planned. The tolerance for the Work Package is one week. What should the Team Manager do?

A.Update the Project Plan to reflect the delay
B.Request a change to the Project Plan directly from the Project Board
C.Issue an Exception Report to the Project Manager
D.Continue with the work and inform the Project Manager in the next Checkpoint Report
AnswerC

This is the correct escalation per PRINCE2.

Why this answer

When a Work Package tolerance is forecast to be exceeded, the Team Manager must escalate to the Project Manager via an Exception Report. The Project Manager can then negotiate corrective actions.

584
MCQeasy

Which document describes the quality methods and responsibilities for the project?

A.Quality Register
B.Product Description
C.Project Plan
D.Quality Management Approach
AnswerD

Correct.

Why this answer

The Quality Management Approach defines how quality will be managed, including methods, responsibilities, and tools.

585
MCQmedium

Which practice is responsible for defining the project's approach to identifying, assessing, and controlling uncertainty?

A.Risk
B.Quality
C.Progress
D.Change
AnswerA

Correct.

Why this answer

The Risk practice covers the systematic management of threats and opportunities.

586
MCQmedium

In product-based planning, what is the purpose of a Product Flow Diagram?

A.To show the order in which products are created and their dependencies
B.To show the timeline and resource allocation for product creation
C.To describe the quality criteria for a product
D.To break down the final product into its component products
AnswerA

The Product Flow Diagram illustrates the sequence and dependencies of products.

Why this answer

Option C is correct. A Product Flow Diagram shows the sequence of product creation and the dependencies between products. Option A is incorrect because it describes the Product Breakdown Structure.

Option B is incorrect because it describes a Product Description. Option D is incorrect because it describes the Project Plan schedule.

587
MCQeasy

What is the key output of the Initiating a Project process?

A.Project Initiation Documentation (PID)
B.Project Brief
C.End Project Report
D.Stage Plan
AnswerA

The PID is the key deliverable of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It forms the basis for management decision-making.

588
MCQmedium

The Project Board is considering whether to authorize the next stage. The current stage has used all its cost tolerance. What should the Project Board do?

A.Request an Exception Plan before authorizing the next stage
B.Revise the project's cost tolerance
C.Close the project immediately
D.Authorize the next stage as planned
AnswerA

To address the tolerance breach, the Board should request an Exception Plan to adjust future plans.

Why this answer

If a stage is within its tolerances, the Project Board authorizes the next stage. If tolerance is exceeded, an Exception Plan should be requested or the project may be closed.

589
Multi-Selecthard

Which THREE of the following are responsibilities of the Executive?

Select 3 answers
A.Produce Highlight Reports
B.Provide customer assurance
C.Ensure the Business Case remains viable
D.Chair the Project Board
E.Appoint the Project Manager
AnswersC, D, E

The Executive owns the Business Case and ensures its viability.

Why this answer

The Executive is accountable for the Business Case, appoints the Project Manager, and chairs the Project Board. Providing customer assurance is the Senior User's role; producing Highlight Reports is the Project Manager's role.

590
Multi-Selecthard

Which THREE of the following are examples of threat responses in the Risk practice?

Select 3 answers
A.Enhance
B.Reduce
C.Exploit
D.Transfer
E.Avoid
AnswersB, D, E

Correct threat response.

Why this answer

Avoid, reduce, and transfer are threat responses. Exploit and enhance are opportunity responses.

591
MCQmedium

What is the definition of quality in PRINCE2?

A.Conformance to specification
B.Fit for purpose
C.Zero defects
D.As described in the Quality Register
AnswerB

Correct: PRINCE2 defines quality as fit for purpose.

Why this answer

PRINCE2 defines quality as 'fit for purpose', meaning the product meets its stated requirements and user expectations.

592
MCQeasy

Which PRINCE2 document contains the cost and time tolerances for the project?

A.Business Case
B.Project Plan
C.Project Brief
D.Project Initiation Documentation
AnswerB

The Project Plan defines project-level tolerances for time, cost, scope, quality, risk, and benefits.

Why this answer

The Project Plan contains the project-level tolerances, including cost and time.

593
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Configuration item records
B.Expected benefits
C.Work package descriptions
D.Quality criteria
E.Major risks
AnswersB, E

Expected benefits are a key component of the Business Case.

Why this answer

Expected benefits and major risks are key components of the Business Case. Options B and D are correct.

594
Multi-Selecthard

Which TWO of the following are responsibilities of the Senior User role?

Select 2 answers
A.Ensuring the solution will meet the users' needs
B.Owning the Business Case
C.Managing project risks on a daily basis
D.Approving the Project Plan
E.Specifying the user requirements
AnswersA, E

The Senior User ensures the project delivers what users need.

Why this answer

The Senior User specifies user needs, ensures the solution meets them, and is responsible for realizing benefits. The Senior User does not own the Business Case (Executive does) and does not manage risks day-to-day (Project Manager does).

595
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Plan
B.Project Brief
C.Business Case
D.Project Initiation Documentation
AnswerD

The PID is the key output that defines the project in detail.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing a foundation for project execution.

596
Multi-Selectmedium

Which TWO of the following documents are produced by the Project Manager and reviewed by the Project Board?

Select 3 answers
A.Checkpoint Report
B.Highlight Report
C.Exception Report
D.End Stage Report
E.End Project Report
AnswersB, C, D

The Highlight Report is from Project Manager to Project Board.

Why this answer

Highlight Reports and End Stage Reports are produced by the Project Manager for the Project Board. Checkpoint Reports are for Team Managers; the End Project Report is produced at the end.

597
MCQmedium

During which process is the Benefits Review Plan first created?

A.Closing a Project
B.Initiating a Project
C.Managing a Stage Boundary
D.Starting up a Project
AnswerB

Correct.

Why this answer

The Benefits Review Plan is created during the Initiating a Project process.

598
MCQhard

In PRINCE2, which two responsibilities are separated to ensure independent assurance?

A.Project Management and Project Assurance
B.Senior User and Senior Supplier
C.Project Support and Project Assurance
D.Project Board and Project Manager
AnswerA

Correct: management (delivery) is separated from assurance (independent checking).

Why this answer

PRINCE2 separates the management and assurance functions to maintain objectivity.

599
MCQmedium

Which of the following is a threat response in PRINCE2?

A.Enhance
B.Exploit
C.Share
D.Reject
AnswerC

Share is a threat response (and also used for opportunities).

Why this answer

PRINCE2 lists avoid, reduce, fallback, transfer, accept, and share as threat responses. Exploit is an opportunity response.

600
MCQmedium

During the Controlling a Stage process, the Team Manager completes a work package and delivers the products. What report does the Team Manager provide to the Project Manager?

A.Highlight Report
B.Exception Report
C.End Stage Report
D.Checkpoint Report
AnswerD

Checkpoint Reports are from Team Manager to Project Manager.

Why this answer

The Team Manager provides Checkpoint Reports at regular intervals. The Project Manager uses these to compile Highlight Reports for the Project Board.

← PreviousPage 8 of 9 · 674 questions totalNext →

Ready to test yourself?

Try a timed practice session using only Prince2 Practices questions.