PRINCE2F PRINCE2 Practices Practice Question
Which THREE of the following are responsibilities of the Executive?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Ensure the Business Case remains viable
The Executive is accountable for the Business Case, appoints the Project Manager, and chairs the Project Board. Providing customer assurance is the Senior User's role; producing Highlight Reports is the Project Manager's role.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Produce Highlight Reports
Why it's wrong here
Highlight Reports are produced by the Project Manager.
- ✗
Provide customer assurance
Why it's wrong here
Customer assurance is provided by the Senior User.
- ✓
Ensure the Business Case remains viable
Why this is correct
The Executive owns the Business Case and ensures its viability.
- ✓
Chair the Project Board
Why this is correct
The Executive chairs the Project Board.
- ✓
Appoint the Project Manager
Why this is correct
The Executive appoints the Project Manager.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.