Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which report is produced by the Team Manager and sent to the Project Manager on a regular basis?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Checkpoint Report

The Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report progress at the work package level.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Checkpoint Report

    Why this is correct

    Correct. The Team Manager produces the Checkpoint Report for the Project Manager.

  • Highlight Report

    Why it's wrong here

    The Highlight Report is produced by the Project Manager for the Project Board.

  • End Stage Report

    Why it's wrong here

    The End Stage Report is produced by the Project Manager for the Project Board at stage end.

  • Exception Report

    Why it's wrong here

    The Exception Report is produced by the Project Manager to escalate to the Project Board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.