PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are responsibilities of the Senior User role?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Ensuring the solution will meet the users' needs
The Senior User specifies user needs, ensures the solution meets them, and is responsible for realizing benefits. The Senior User does not own the Business Case (Executive does) and does not manage risks day-to-day (Project Manager does).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Ensuring the solution will meet the users' needs
Why this is correct
The Senior User ensures the project delivers what users need.
- ✗
Owning the Business Case
Why it's wrong here
The Executive owns the Business Case.
- ✗
Managing project risks on a daily basis
Why it's wrong here
Risk management is the Project Manager's responsibility.
- ✗
Approving the Project Plan
Why it's wrong here
The Project Board as a whole approves plans.
- ✓
Specifying the user requirements
Why this is correct
The Senior User is responsible for defining user needs.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.