Courseiva
PRINCE2 PracticeshardMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which TWO statements about the Change Authority are true?

⚠ Common exam trap

Many candidates confuse the Change Authority with the Project Manager, assuming the Project Manager always has the authority to approve changes, but PeopleCert PRINCE2 explicitly separates the two roles to ensure appropriate governance and delegation of decision-making power.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

It has the authority to approve changes within a defined limit

The Change Authority is a role defined in PRINCE2 that is granted the authority to approve changes within a defined limit, such as a cost or time threshold. This limit is typically set by the Project Board in the Project Initiation Documentation, and the Change Authority can be an individual (e.g., a senior user) or a group (e.g., a change board). Option A is incorrect because the Change Authority is defined in the Change Control Approach, not the Configuration Management Approach. Option D is incorrect because the Change Authority is not always the Project Manager; it is a separate role with delegated authority. Option E is incorrect because maintaining Configuration Item Records is the responsibility of the Configuration Librarian, not the Change Authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • It is defined in the Configuration Management Approach

    Why it's wrong here

    It is defined in the Change Control Approach.

  • It has the authority to approve changes within a defined limit

    Why this is correct

    This is the definition.

  • It can be an individual or a group

    Why this is correct

    Yes, it can be a person or committee.

  • It is always the Project Manager

    Why it's wrong here

    The Change Authority can be the Project Manager, but not always.

  • It is responsible for maintaining the Configuration Item Records

    Why it's wrong here

    Configuration management is separate.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.