Which THREE of the following are components of the Project Initiation Documentation (PID)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Description

The PID includes the Business Case, Project Plan, Project Description, roles and responsibilities, etc. The Risk Register is a separate document, and the Checkpoint Report is a management product.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Description

    Why this is correct

    The Project Description is part of the PID.

  • Business Case

    Why this is correct

    The Business Case is part of the PID.

  • Project Plan

    Why this is correct

    The Project Plan is part of the PID.

  • Checkpoint Report

    Why it's wrong here

    The Checkpoint Report is produced during controlling a stage.

  • Risk Register

    Why it's wrong here

    The Risk Register is a separate document, though its contents may be summarised.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.