In PRINCE2, which role is accountable for the business justification of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Executive

The Executive (Senior Responsible Owner) is accountable for the business justification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier is accountable for the suppliers' interests.

  • Executive

    Why this is correct

    The Executive owns the Business Case and is accountable for business justification.

  • Senior User

    Why it's wrong here

    The Senior User is accountable for the benefits.

  • Project Manager

    Why it's wrong here

    The Project Manager is responsible for maintaining the Business Case but is not accountable.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.