PRINCE2F PRINCE2 Practices Practice Question
Which role is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager is responsible for maintaining the Business Case on behalf of the Executive. The Executive owns it but the PM updates it as needed.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Manager
Why this is correct
The Project Manager maintains the Business Case on behalf of the Executive.
- ✗
Executive
Why it's wrong here
The Executive owns the Business Case, but the Project Manager maintains it.
- ✗
Senior User
Why it's wrong here
The Senior User represents users' interests but does not maintain the Business Case.
- ✗
Project Assurance
Why it's wrong here
Project Assurance is independent and does not maintain the Business Case.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.